City of Lewiston v. Lindsey

853 P.2d 596, 123 Idaho 851, 1993 Ida. App. LEXIS 29
CourtIdaho Court of Appeals
DecidedMarch 3, 1993
Docket19542
StatusPublished
Cited by8 cases

This text of 853 P.2d 596 (City of Lewiston v. Lindsey) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Lewiston v. Lindsey, 853 P.2d 596, 123 Idaho 851, 1993 Ida. App. LEXIS 29 (Idaho Ct. App. 1993).

Opinion

SILAK, Acting Judge.

In order to obtain the right-of-way for a street improvement project, the City of Lewiston filed an eminent domain action to acquire real property owned by Margaret E. Lindsey. Lindsey counterclaimed alleging causes of action for negligence, inverse condemnation and breach of promise. With respect to the City’s condemnation action, the parties later agreed that Lindsey be compensated $18,000 for the condemned property, and the trial proceeded solely on the issues raised in Lindsey’s counterclaim. After the parties had presented their cases, but before the matter was submitted to the jury, the district court granted the City’s motion for a directed verdict. Lindsey timely appealed, challenging the order directing a verdict in favor of the City.

FACTS AND PROCEDURAL HISTORY

This case arose during the planning and development of a street improvement project in the City of Lewiston. On September 26, 1983, the city council of Lewiston passed a resolution declaring its intention to perform a federally funded street improvement project to be known as the seventeenth-eighteenth street project. The preliminary design phase of the project commenced on December 12, 1983, when the Idaho Department of Transportation (IDT) approved the project as proposed by the City and agreed to work with the City to qualify the project for federal funding. According to the project’s preliminary design and right-of-way plans, a parcel of land owned by Lindsey was located within the project’s proposed right-of-way, and therefore was projected for acquisition by the City. IDT approved the City’s preliminary design and right-of-way plans on September 14, 1984, completing the preliminary design phase of the project and commencing the final design phase. It is undisputed that sometime during the final design phase—when the final plans were being prepared but before construction was commenced—the City was to acquire the private property needed for the project’s right-of-way.

About three years after entering the final design phase, on August 31, 1987, the City commenced the process of acquiring Lindsey’s property by having the property appraised. On September 28,1987, about a month after the appraisal was completed, the City commenced negotiations with Lindsey by offering her $11,000 for the property. Lindsey rejected the City’s offer and on August 31, 1988, following unsuccessful negotiations, the City filed an eminent domain action against Lindsey to have the amount of compensation determined judicially.

Lindsey subsequently filed a counterclaim against the City alleging that on February 12, 1985, the City advised her of its intention to acquire her property for approximately $40,000, and that she was further advised at that time that her daughter, who occupied the premises, would need to be relocated and the premises vacated. Lindsey further alleged that she promptly relocated her daughter and vacated the premises but that the City failed to move promptly to acquire the premises as the City represented; not making an offer of purchase to Lindsey until September of 1987, about two and one-half years later. Lindsey’s claim was one for inverse condemnation, alleging that during those two and one-half years the City greatly impeded her use of the property, which interference constituted an unconstitutional taking of her property without compensation. Lindsey’s counterclaim did not state any legal theory of recovery other than for inverse condemnation. However, by the time of trial, Lindsey had also asserted that her allegations supported an action for negligence against the City. Also by the time *853 of trial, the parties had stipulated that the City was condemning Lindsey’s property for a proper public purpose, and that just compensation for Lindsey’s property would be $18,000 plus interest from August 31, 1988, the date of the summons in the City’s condemnation action. This stipulation resolved the issues raised by the City’s condemnation action, leaving only Lindsey’s counterclaims for inverse condemnation and negligence to be resolved at trial.

In support of her claims, Lindsey testified at trial that during December of 1984, John Block, a principal planner on the City’s staff, represented to her that the City would acquire her property within the next thirty to sixty days and that the City would pay her approximately $40,000 for the property. Lindsey also introduced as evidence a letter sent to her by the City dated February 12, 1985, which stated as ■follows:

In response to your request to receive the current status of property negotiations on the 18th Street Project, I would like to offer the following information.
The additional private property required to construct the project has been identified. Your entire property at 1733 8th Avenue Boulevard including the structure will have to be acquired as part of the project in order to construct the street improvements. In order to begin right-of-way negotiations, the environmental assessment report must be approved. At this point, the environmental assessment report is under review by the appropriate state and federal agencies. Although predicting the date when approval will be given is difficult, our schedule requires that right-of-way negotiations commence within the next two months in order to have construction begin in the summer of 1986.

Lindsey testified that based on Block’s oral statements in December of 1984, and the above-quoted letter of February 1985, she understood that she had thirty to sixty days to vacate the subject premises. Lindsey testified that in reliance on the City’s representations, she went to a bank and secured a loan for about $40,000 to finance the relocation of her daughter. Lindsey also testified that she intended to repay the loan with the money she believed the City was shortly going to pay her for the property. Finally, Lindsey testified that for two and one-half years following the City’s letter of February 12, 1985, the City unreasonably delayed the acquisition of her property, and that during that time she contacted the City on numerous occasions to ascertain the status of the acquisition process and the City continuously represented to her that acquisition would take place in the near future, and therefore she should neither occupy nor improve the premises. Lindsey claimed that the City’s failure to promptly acquire and compensate her for the property, at the same time it prohibited her from renting or improving the property, caused her the following damages: $14,440 in lost rent; $60,000 for the cost of relocating her daughter; $500,000 in late fees, collateral forfeitures, and lost business opportunities as a result of being unable to repay the bank loan; and $1,000,000 for pain and suffering, impaired health, and public humiliation.

To refute Lindsey’s counterclaims, the City presented evidence at trial to show that neither Block nor any other city official ever told Lindsey that the City would acquire her property within thirty to sixty days, only that it desired and expected that negotiations would begin within that time period; that neither Block nor any other city official ever told Lindsey the City would pay her approximately $40,000 for the property; and that the City never advised Lindsey about what she could or could not do with her property nor interfered with or limited Lindsey’s use of her property in any other way prior to the filing of its condemnation action in August of 1988.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williamson v. Ada County
509 P.3d 1133 (Idaho Supreme Court, 2022)
Carlson v. Stanger
200 P.3d 1191 (Idaho Court of Appeals, 2008)
Dorea Enterprises, Inc. v. City of Blackfoot
163 P.3d 211 (Idaho Supreme Court, 2007)
Covington v. Jefferson County
53 P.3d 828 (Idaho Supreme Court, 2002)
Beco Construction Co. v. Harper Contracting, Inc.
936 P.2d 202 (Idaho Court of Appeals, 1997)
Western Stockgrowers Ass'n v. Edwards
894 P.2d 172 (Idaho Court of Appeals, 1995)
Cannon Builders, Inc. v. Rice
888 P.2d 790 (Idaho Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
853 P.2d 596, 123 Idaho 851, 1993 Ida. App. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-lewiston-v-lindsey-idahoctapp-1993.