City of Kirbyville v. Thackwell

108 S.W.2d 226, 1937 Tex. App. LEXIS 804
CourtCourt of Appeals of Texas
DecidedJuly 21, 1937
DocketNo. 3200.
StatusPublished
Cited by1 cases

This text of 108 S.W.2d 226 (City of Kirbyville v. Thackwell) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Kirbyville v. Thackwell, 108 S.W.2d 226, 1937 Tex. App. LEXIS 804 (Tex. Ct. App. 1937).

Opinion

O’QUINN, Justice.

Appellant, City of Kirbyville, is a municipal corporation, duly chartered under the provisions of chapter 1, title 28, Revised Statutes of Texas (now Vernon’s ■Ann.Civ.St. Arts. 961-976). As such municipal corporation, it installed, and in 1934 was operating, a system of waterworks for the convenience of its citizens. In 1934, appellant’s city council decided to install a sewer system, and began negotiations with the Federal PWA agency to finance the project. For that purpose, PWA agreed to buy appellant’s bonds in the amount of $38,000, to be secured by a pledge of the revenues from the sewer system, and to give appellant a grant of $12,000, but required appellant to employ a competent consulting civil and sanitary engineer to design, survey, prepare plans, maps, specifications, estimates, and all other necessary work preparatory to obtaining a loan from the PWA to be used in the erection and installing the sewer system, and to supervise the construction of the system when operation work began. Appellaiit entered into a contract with ap-pellee to do the work required of the engineer, and he completed same up to where the specifications, maps, blueprints, estimates, etc., were ready for filing with the PWA office at Fort Worth, Tex., and same were so filed, along with appellant’s contract of employment with appellee, and after inspection by the PWA authorities were approved by PWA, and the loan of $38,000 duly granted and approved. The bonds of appellant for said sewer project were accordingly voted and approved by the Attorney General of the state of Texas, and everything ready for the letting of the contract for the building of the sewer system. Appellant, in its written contract with appellee, agreed to pay him for his services 6 per cent, of the cost of the sewer system, which was estimated at $44,-463.87, to be paid as follows: 50 per cent, upon the letting of the contract for the construction of the system, and the remainder from month to month during the progress of the work in the proportion of the work completed during each month until the whole was paid computed upon the final cost of the system. Appellant agreed to employ a' competent inspector, who should be kept at all times on the ground, during the actual construction work. As before stated, bonds in the sum of $38,000 were voted by appellant as required by PWA pledging only the revenue of the sewer system to liquidate the bonds which was the original offer of PWA. But after the election PWA decided that the revenue from the sewer system alone would not liquidate the bonds and directed appellant to hold another election pledging also the revenues from the city waterworks as security and as a liquidating fund for the bonds. This election was held as required by PWA and resulted in favor of the bonds. The election was held in strict accordance with law, and the bonds were approved by the-Attorney General of Texas, and by counsel for PWA. In the meantime a new city administration was elected by appellant, which determined to switch from PWA to WPA as its financing agency. Pending negotiations between appellant and WPA, appellant’s city council passed an ordinance canceling all proceedings with PWA and WPA, relating to the installation of the sewer system. Appellant then gave notice to appellee of its declining to proceed further with the construction of'the sewer system, and that it would not build same, and discharged him from further services in connection therewith. Whereupon appellee demanded of appellant pay for the services he had rendered under his contract with the city, which it refused to pay, and this suit was brought by him to recover for his said services, which he alleged were worth $2,000.

Appellant answered by general demurrer, special exceptions pointing to uncertainty in plaintiff’s pleading, general denial, and specially the lack of sufficient funds with which to build the sewer system, and its inability to secure such funds, and further its good faith in its efforts to secure sufficient funds to finance the project, wherefore it was without fault, and appellee was not entitled to recover in any sum. The case was tried to a jury upon the following special issues, answered as indicated:

“Special Issue No. 1
“Do you find from a preponderance of the evidence .that the defendant, City of Kirbyville, declined to proceed to let the contract for the construction of its sewer system and disposal plant undei the P. W. A. grant?”
*228 Answer: “It did decline to let the contract.”
“Special Issue No. 2
“Do you find from a preponderance of the evidence that the defendant. City of Kirbvville, informed the plaintiff, H. L. Thaclcwell, that it would not proceed to let the contract for the construction of its sewer system and disposal plant under the P. W. A. grant?"
Answer: “Tt did inform the plaintiff that it would not proceed to let the contract.”
“Special Issue No. 3
“Find from a preponderance of the evidence when — that is, on or about what date ■ — the defendant, citv of Kirbyville, informed the plaintiff. H. L. Thaclcwell, that it would not proceed to let the contract for the construction of its sewer system and disposal plant.”
Answer: “Sept. 16th, 1935.”
“Special Issue No. 4
“Find from a preponderance of the evidence when — that is, on or about what date— the defendant, City of Kirbyville, decided to decline to proceed to let the contract for the construction of its sewer system and disposal plant under the P. W. A. grant.”
Answer: “Sept. 13th, 1935.”
“Special Issue No. 5
“What do you find from a preponderance of the evidence to be the reasonable cost of the work of constructing the sewer system and disposal plant that the defendant, City of Kirbyville, had intended to construct, at the time when said defendant declined to proceed to let the contract for said construction work of its sewer system and disposal plant?”
Answer: “$44,000.00.”
“Special Issue No. 6
“What do you find from a preponderance of the evidence would have been a reasonable time in which to construct the sewer system and disposal plant that the defendant, City of Kirbyville, had intended to construct ?”
Answer: “Four months.”
“Special Issue No. 7
“What do you find from a preponderance of the evidence would have been the reasonable cost to plaintiff, H. L. Thackwell, to employ a competent inspector to be maintained at all times on the ground during the actual construction work?”
Answer: “$600.00.”
“Special Issue No. 8
“What do you find from a preponderance of the evidence to be the reasonable value of plaintiff’s advisory services, general administration of the business and supervision of the work in connection with the construction of the sewer system

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Raynes v. Germany
144 S.W.2d 981 (Court of Appeals of Texas, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
108 S.W.2d 226, 1937 Tex. App. LEXIS 804, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-kirbyville-v-thackwell-texapp-1937.