City of Houston v. Allco, Inc.

238 S.W.3d 849, 2007 WL 3040285
Court of Appeals of Texas·Decided November 28, 2007·No. 01-02-00812-CV·Published·Cited by 4 cases

Opinion

OPINION ON REMAND

LAURA CARTER HIGLEY, Justice.

The Supreme Court of Texas remanded this case to us for a determination of whether the City of Houston’s immunity from suit is waived pursuant to Local Government Code sections 271.151-.160. City of Houston v. Allco, Inc., 206 S.W.3d 113, 114 (Tex.2006).

We affirm.

Factual and Procedural Background

In 1994, Allco entered into a contract (“the contract”) with the City of Houston (“the City”) to provide “sewer rehabilitation services.” The contract contemplated that Allco would be entitled to compensation for “extra work,” i.e., work that was not already approved under the contract. To receive such compensation the contract required that Allco give notice to and obtain approval from the City’s engineer for the extra work before the work was undertaken. The contract also provided that, subject to the City engineer’s approval, Allco was entitled to compensation “when direct and unavoidable extra cost to [Allco] is caused by the failure of the City to provide information or material, if any, which is to be furnished by the City.”

Unrelated to the contract, residents of the Kennedy Heights region of Houston filed a toxic tort suit in 1995 against Chevron U.S.A., Inc. in Texas state court. The residents alleged that Chevron contaminated the soil in their neighborhoods with petroleum by-products. On July 10, 1995, the state court ordered the City to notify counsel for the tort plaintiffs of any sewer work being performed in the Kennedy Heights subdivision. That order was dissolved by further order on August 11, 1995.

In June 1996, Allco was conducting sewer rehabilitation work for the City under work order number 38 in the Crestmont subdivision — an area included within the scope of the Kennedy Heights tort litigation. At that time, the City had not informed Allco of the Kennedy Heights litigation filed in state court. Also unknown to Allco, another lawsuit had been filed by Kennedy Heights residents in Houston federal court. On June 18, 1996, at 5:10 p.m., a federal marshal served Allco with a temporary restraining order signed by the federal judge in the second Kennedy Heights suit. The order required Allco to cease further excavation work on the Crestmont project. At that time, Allco had 70 to 80 open trenches in the Crest-mont subdivision. Allco faxed a copy of the temporary restraining order to the City’s public works department.

The following day, Allco entered into an agreed order, which required Allco to establish a plan to “rope off’ the construction site and areas where the excavated dirt was stored and to provide the tort plaintiffs access to monitor the site. Allco hauled the dirt, which had been excavated prior to Allco’s receiving the restraining order, to an esplanade where the dirt was covered and a fence was erected.

Although the contract permitted Allco to use the excavated dirt to refill the trenches it had dug, Allco believed that the language of the agreed order, requiring it to secure the dirt, prevented Allco from using that dirt to refill the trenches. As a result, Allco purchased and trucked in new dirt — an expense it would not have normally incurred under the contract. During these activities, city inspectors were present at the work site.

*851 On June 21,1996, an assistant city attorney sent Mco a letter, demanding that Allco dispose of the “excess excavated material and debris.” If Allco did not do as requested, the assistant city attorney warned that Allco would be in breach of the contract. After receiving the letter, Allco paid for the transport and disposal of the excavated dirt. As part of the disposal process, Allco hired a company to test the excavated dirt to determine whether it was contaminated. By the end of July 1996, the excavated dirt had been trucked to a landfill for disposal at Allco’s expense.

On February 10, 1998, Allco submitted a claim to the City for the extra work associated with the Kennedy Heights litigation. The city attorney denied the claim six months later. In April 1999, Allco sought approval for the extra work from the City’s engineer. The City did not respond.

Allco filed suit against the City, alleging breach of contract and seeking $89,806.48 in damages for the extra work it had completed in the Crestmont subdivision. Following a bench trial, the trial court signed a judgment in favor of Allco. The court found that Allco was entitled only to part of the damages it requested, awarding All-co $27,468.88 in damages, which represented the cost of testing, of moving, and of ultimately disposing of the excavated dirt, and included $1,375.00 in attorney’s fees paid by Allco to defend against the federal court restraining order.

In support of its judgment, the trial court signed findings of fact and conclusions of law, including the following findings: (1) the contract provides for extra work; (2) the contract “requires notice, relative to extra costs, and Allco used this format in complying with the claim filing process”; (3) Allco reasonably believed that the assistant city attorney instructed it to remove the soil; (4) Allco reasonably responded to the agreed order and the assistant city attorney’s directive in removing the excavated soil; (5) Allco detrimentally relied on the directive of the assistant city attorney and the agreed order in making its decision to remove the excavated dirt; (6) Allco would have sought written authorization from the City for the extra work had the City informed Allco of the Kennedy Heights litigation; and (7) Allco acted reasonably and in the interest of public safety in removing potentially contaminated soil.

The City appealed the trial court’s judgment to this Court. Among its contentions on appeal, the City asserted that Allco was not entitled to reimbursement for the extra work associated with the Kennedy Heights litigation because Allco had not complied with the contract by obtaining approval from the City’s engineer before commencing the extra work. We disagreed, concluding that the City, by its conduct, had waived the contractual notice and approval requirements with regard to extra work. City of Houston v. Allco, Inc., No. 01-02-000812-CV, 2004 WL 1471818 at *4-5 (Tex.App.-Houston [1st Dist.] 2004, July 1, 2004), rev’d on other grounds, 206 S.W.3d at 114. In upholding the trial court’s breach of contract award to Allco, we wrote,

Assuming the contract provisions at issue in this case are conditions precedent to the City’s contractual obligation to pay Allco for extra work, the controlling findings of fact in this case support a conclusion that the City waived performance of these conditions by its words and deeds. Specifically, the findings of fact relating to the City’s failure to inform Allco of the Kennedy Heights litigation and the assistant city attorney’s directive to dispose of the excavated soil support such conclusion.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Houston v. Allco, Inc., 238 S.W.3d 849, 2007 WL 3040285 (Tex. Ct. App. 2007).

238 S.W.3d 849 (City of Houston v. Allco, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Triple B Services, LLP v. City of Conroe
Court of Appeals of Texas, 2022
Jones v. City of Dallas
310 S.W.3d 523 (Court of Appeals of Texas, 2010)
City of Houston v. Petroleum Traders Corp.
261 S.W.3d 350 (Court of Appeals of Texas, 2008)