City of Holyoke Gas & Electric Department v. Securities & Exchange Commission

972 F.2d 358, 297 U.S. App. D.C. 305
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 24, 1992
DocketNos. 91-1001, 91-1091, 91-1092, 91-1132 and 91-1220
StatusPublished
Cited by1 cases

This text of 972 F.2d 358 (City of Holyoke Gas & Electric Department v. Securities & Exchange Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Holyoke Gas & Electric Department v. Securities & Exchange Commission, 972 F.2d 358, 297 U.S. App. D.C. 305 (D.C. Cir. 1992).

Opinion

Opinion for the Court filed by Circuit Judge D.H. GINSBURG.

D.H. GINSBURG, Circuit Judge:

Nine municipal utilities and three state agencies (hereinafter collectively the Mun-is) petition for review of the decision of the Securities and Exchange Commission to approve the acquisition of the Public Service Company of New Hampshire (PSNH) by Northeast Utilities. The Munis argue that the SEC committed numerous errors in approving the acquisition; for the reasons set out below we reject their arguments and deny the petitions for review.

I. Background

PSNH provides retail or wholesale electric service to approximately 75% of the population of New Hampshire and has a 35.6% ownership interest in the nuclear power plant at Seabrook, New Hampshire. In 1988 the Company filed a voluntary petition in bankruptcy court for reorganization under chapter 11 of the Bankruptcy Code. Two years later the bankruptcy court approved a reorganization plan under which Northeast Utilities, a large electric utility holding company, would acquire PSNH. In re Public Serv. Co. of New Hampshire, 114 B.R. 804 (Bankr.D.N.H.1990). Northeast then petitioned various regulatory agencies, including the SEC, the Federal Energy Regulatory Commission, and the Nuclear Regulatory Commission, for approval of the acquisition, and gave premerger notification of the acquisition to the Antitrust Division of the Department of Justice and the Federal Trade Commission.

The Munis intervened before the SEC to oppose Northeast’s application to acquire PSNH (and to issue securities necessary to finance the acquisition). The Munis argued that the acquisition was contrary to the public interest on a number of grounds, including that the likely benefits of the merger did not exceed its likely costs, that the merger would have an anticompetitive effect in the New England markets for the generation and transmission of bulk electric power, that Northeast’s corporate structure was unduly complex, and that Northeast’s earning power would be insufficient to satisfy the financial obligations that it would incur in acquiring PSNH. The Munis requested an evidentiary hearing before the SEC in order to pursue these claims.

While the SEC considered the positions of the parties before it, the FERC was conducting its own proceeding regarding the proposed acquisition. Two of the issues contested in the FERC proceeding were among those also put before the SEC — whether the likely benefits of the merger exceed its likely costs and whether the merger would have an anticompetitive effect in the relevant markets. After an extensive evidentiary hearing, the Administrative Law Judge hearing the FERC case released an initial decision on December 20, 1990. Northeast Utils. Serv. Co., 53 F.E.R.C. ¶ 63,020 (1990). The AU found that the likely benefits of the acquisition do exceed its likely costs, slip op. at 7-15, but that the acquisition would give Northeast so large a share of the bulk power generation and transmission markets as to raise a concern that Northeast might be able to behave anticompetitively, id. at 15-24. The AU recommended approval of the acquisition nonetheless, subject to certain conditions designed to prevent Northeast from engaging in anticompetitive practices after the merger. Id. at 24-51.

The following day the SEC issued its own order approving the acquisition. Northeast Utils., Holding Co. Act Rel. No. 35-25221, 47 S.E.C. Docket 1887 (Dec. 21, 1990) (SEC Order). Contrary to the FERC, the SEC found that the acquisition would have no anticompetitive effect in the relevant markets. Slip op. at 40. Like the FERC AU, the SEC determined that the likely benefits of the merger exceed its likely costs, id. at 51-53; the SEC also held that Northeast’s corporate structure was not unduly complex, id. at 45-50, that Northeast’s post-merger earnings would be sufficient to satisfy the financial obligations that it would incur in acquiring [308]*308PSNH, id. at 28-31, and that no hearing was necessary, id. at 59-69.

The Munis filed petitions for rehearing with the SEC. In a Supplemental Order the SEC changed its position on one issue, holding that the acquisition indeed “raises the potential for anticompetitive behavior.” Northeast Utils., Holding Co. Act Rel. No. 35-25273, 48 S.E.C. Docket 776, slip op. at 5 (Mar. 15, 1991) (Supplemental Order). Recognizing the FERC’s greater expertise with the operational issues involved, however, the Commission deferred to the FERC to frame the conditions necessary in order to minimize the risk to competition. Id. at 6-9. The SEC noted that if the conditions imposed by the FERC were inadequate to prevent Northeast from engaging in anticompetitive behavior after the acquisition, the SEC could reopen its proceeding and “rescind or further condition its approval” of the acquisition. Id. at 9 n. 15, citing the Public Utility Holding Company Act of 1935 (PUHCA) § 20(a), 15 U.S.C. § 79t(a). The SEC also pointed out that the allegedly undue complexity of Northeast’s corporate structure was unrelated to its acquisition of PSNH, id. at 11-12; again rejected the Munis’ other arguments and denied their request for an evidentiary hearing, id. at 9-14; and affirmed its earlier order approving the acquisition, id. at 15.

Some time after the SEC released it Supplemental Order, the FERC accepted the recommendation of its AU to approve the acquisition (modifying some of the conditions to be imposed). Northeast Utils. Serv. Co., 56 F.E.R.C. ¶ 61,269 (1991), reh’g denied, 58 F.E.R.C. ¶ 61,070 (1992), petitions for review pending sub nom. Northeast Utilities Service Co., et al. v. FERC, Nos. 92-1165, et al. (1st Cir.). The NRC has also since approved the acquisition. 57 Fed.Reg. 24,064 (1992). Neither the FTC nor the Department of Justice took any action to stop the merger under the antitrust laws. See 56 Fed.Reg. 7710 (1991).

II. Analysis

Seeking review of the SEC decision, the Munis argue that the Commission erred in (1) finding that the likely costs of the acquisition exceed its likely benefits, (2) deferring to the FERC the question of anti-competitive effect of the acquisition, (3) refusing to order Northeast to simplify its corporate structure, (4) finding that the earning power of the post-merger Northeast will be sufficient to satisfy the financial obligations that Northeast will incur in acquiring PSNH, and (5) denying the Mun-is’ requests for an evidentiary hearing. We consider each argument in turn.

A. The Benefits and Costs of the Acquisition

Under PUHCA § 10(c)(2), 15 U.S.C. § 79j(c)(2), the SEC may not approve an acquisition “unless the Commission finds that such acquisition will serve the public interest by tending towards the economical and efficient development of an integrated public-utility system.” As the SEC interprets § 10(c)(2), the agency is required to withhold its approval if the likely costs of the acquisition exceed its likely benefits. See SEC Order, slip op. at 51-53. In other words, the SEC looks for a net social gain.

The Commission adopted the estimate of costs and benefits that Northeast submitted to it. Because that estimate is supported by substantial evidence in the record, we do not disturb it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
972 F.2d 358, 297 U.S. App. D.C. 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-holyoke-gas-electric-department-v-securities-exchange-cadc-1992.