City of Henderson v. Kentucky Peerless Distilling Co.

170 S.W. 210, 161 Ky. 1, 1914 Ky. LEXIS 5
CourtCourt of Appeals of Kentucky
DecidedNovember 13, 1914
StatusPublished
Cited by5 cases

This text of 170 S.W. 210 (City of Henderson v. Kentucky Peerless Distilling Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Henderson v. Kentucky Peerless Distilling Co., 170 S.W. 210, 161 Ky. 1, 1914 Ky. LEXIS 5 (Ky. Ct. App. 1914).

Opinion

Opinion op the Court by

Judge Turner

— Affirming.

This is an equitable action by tbe appellee against tbe City of Henderson and its mayor seeking to enjoin them from disconnecting a private sewer which appellee had constructed and which had been connected with one of the city sewers. The injunction was granted by the lower court and the city and mayor have appealed.

A motion has been entered in this court to strike from the files the bill of exceptions and to dismiss the appeal, and those motions having been passed to a hearing on the merits will be first disposed of.

It appears that in the lower court the action was heard on oral testimony taken in open court by the official stenographer. At the same term of the court, after the entry of the judgment, the appellant was by an order given until the second day of the January term, 1914, to file a bill of exceptions and the bill of evidence. Between the September term and the ensuing January term a new board of council for the city and a new city attorney had been elected.

On the first day of the January term the new city attorney, ascertaining that the bills of exceptions and evidence had not been prepared, entered a motion asking that the time be extended for the filing until the 13th day of that term, which motion was sustained and an order to that effect entered. The new council, however, had a meeting on the second day of that term of the Henderson Circuit Court, and directed the city attorney not to prosecute an appeal from the judgment; thereupon on the third day of the term by agreement the order extending the time for the filing of the bill of exceptions and evidence was set aside, and the action filed away. Thereafter, however, the new council and the new city attorney having become more familiar with the issues involved in the case, and conceiving them to be of great import[3]*3anee to the city, rescinded its action directing its city attorney not to prosecute the appeal, and directed him to prosecute it, and employed associate counsel.

On the 13th day of the term the court was not actually in session, having adjourned over for a day or two; and accordingly on that day the counsel for the city filed in the clerk’s office a bill of exceptions and a bill of evidence, and thereafter, when the court reconvened, entered a motion to set aside the order which by agreement had been entered setting aside the order granting the extension of time. The court, after a full hearing and the filing of affidavits on both sides, set aside the order granting the extension, and permitted the bill of exceptions and the bill of evidence to be filed, and certified and approved the same.

Counsel for appellee are basing their motion upon the rule that bills of exceptions cannot be filed in vacation; but where during a term of court an adjournment is had over for a few days the interim cannot be said to be vacation. It is during term time just as if the court actually had been in session. In this case the appellants did all that could be required of them by tendering their bill of evidence and bill of exceptions in the clerk’s office within the time prescribed by the order of the court. They had no control over the action of the court in adjourning over and cannot be held responsible therefor.

The court during the term had full power to modify or set aside any of its orders made during that term, and its action in setting aside the order, which had set aside the former order granting the extension, left in full force the original order extending the time.

For the reasons we have given the motion to strike from the files the bill of exceptions and dismiss the appeal are overruled.

Canoe Creek is a water course which traverses a portion of the City of Henderson, and for a long term of years had been used as an outlet for a part of the city’s sewage. Several years ago a number of damage suits were instituted against the city and the Peerless Distilling Company and its manager because of alleged damage done to certain property and residents along that creek due to its pollution, which was alleged to have been caused by the drainage from the city and from the distillery.

[4]*4The city and distillery were finally held liable for this damage in an opinion of this court. City of Henderson v. Robinson, 152 Ky., 245.

The city desiring to protect itself from future similar damage suits, constructed a 10-inch sewer from Canoe Creek on the east to the Ohio Eiver on the west, a distance of something over a mile, thereby diverting the city sewage away from Canoe Creek; but this new sewer did not run nearer than 2,200 feet to the. distillery property, and its sewage continued to go into Canoe Creek. The distilling company seeking a way to connect with this new sewer, and thereby relieve itself from future damage suits, after having been notified in July, 1912, by the city health authorities to abate the nuisance on its premises (presumably the running of sewage into Canoe Creek), made the following application to the city engineer:

“R. W. Ball, City Engineer, City of Henderson, Ky.
“Dear Sir:
“The undersigned desires permission to tap the Sandefur Mill and Canoe Creek sewer, - street, at a point about 360 feet west of Canoe Creek with 10" pipe to be used for said tap, and agree to comply with the rules as stipulated in ordinance, nor will I permit any one to connect to the tap made by me unless permitted by the Common Council.
‘ ‘ The Kentucky Peerless Distilling Co. ’ ’

Which application was approved in writing by the city engineer on July 27th, 1912, and on that same day the distilling company obtained from the city clerk of Henderson the following permit:

“Kentucky Peerless Distilling Co. having complied with the ordinance governing the tapping of sewers in the City of Henderson, is hereby authorized to tap the Sandefur Mill and Canoe Creek sewer on-side of about 360 feet west of Canoe Creek between-streets, the work to be done under the supervision of the City Engineer.
“ (Signed) J. G. Adams, City Clerk.”

Immediately thereafter the distilling company, at considerable cost to itself, proceeded to ’connect with the new sewer, and that connection was made under the direction and supervision of the city engineer, and it is [5]*5that connection which it is sought by the injunction to prevent the city from severing.

The appellee in applying to the city engineer and in getting the permit from the city clerk acted under the provisions of the following ordinance of the City of Henderson, which became effective October 19th, 1897, to-wit:

“An ordinance regulating the tapping of sewers in the City of Henderson, and fixing the fee to be charged therefor.
“Be it ordained by the Common Council of the City of Henderson, Ky.
‘ ‘ Conditions.
“Sec. 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Engle v. City of Louisville
227 S.W.2d 407 (Court of Appeals of Kentucky, 1950)
Clover Farm Dairy Company v. Gillum
299 S.W. 1065 (Court of Appeals of Kentucky (pre-1976), 1927)
Chesapeake & Ohio Railway Co. v. Maggard's Administrator
235 S.W. 736 (Court of Appeals of Kentucky, 1921)
Eubanks v. Commonwealth
211 S.W. 556 (Court of Appeals of Kentucky, 1919)
Kraver v. Smith
177 S.W. 286 (Court of Appeals of Kentucky, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
170 S.W. 210, 161 Ky. 1, 1914 Ky. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-henderson-v-kentucky-peerless-distilling-co-kyctapp-1914.