City of Greensboro v. Southern Paving & Construction Co.

168 F. 880, 94 C.C.A. 292, 1909 U.S. App. LEXIS 4514
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 12, 1909
DocketNo. 868
StatusPublished
Cited by5 cases

This text of 168 F. 880 (City of Greensboro v. Southern Paving & Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Greensboro v. Southern Paving & Construction Co., 168 F. 880, 94 C.C.A. 292, 1909 U.S. App. LEXIS 4514 (4th Cir. 1909).

Opinion

DAYTON, District Judge.

The Southern Paving & Construction Company hereinafter designated the “contractor,” brought its action at law in the court below against the city of Greensboro, N. C., hereinafter designated the “city,” upon a street paving contract made between the Southern Contracting Company and said city, and subsequently assigned to and assumed by the said plaintiff company. By ihe terms of the contract the contractor was to furnish all necessary material and work required to grade and pave certain streets in the city in accordance with specifications annexed to the contract, and, further, in accordance with such plans and instructions as might, during the progress of the work, be furnished by the city's engineer. The provisions of the contract material to the controversy here were to the effect that the contractor should start the work at such point as the engineer should from time to time direct, and observe .his directions as to the manner, completeness, and rate of progress of the execution of the work; that the contractor, by direction of the engineer, should remove and reconstruct at his own cost work found by the engineer not to have been done in accordance with the contract; that the city, through its engineer, should have right to make alterations in plans and grade lines before or after commencement of the work, and, if at extra cost, at a stipulated price; also to require the performance of extra work directed by the engineer in writing to be done, to be paid for upon an estimate of the engineer based upon the contract price; ihat the engineer’s decision should be final in constructing the plans and specifications; and “to prevent all disputes and altercations” the city engineer was to — ■

"be referee in nil cases and determine tlie amount, quality, acceptability and fitness of the several kinds 'of work i! * * and to decide all questions [882]*882which may be raised relative to the fulfillment of the contract by the contractor, that his estimates and decisions shall be final and conclusive, and that such estimates or decisions in case any question shall arise, shall be a condition precedent to the right of the contractor to receive any money under this agreement”

It was further provided:

“The contractor further agrees to be responsible for any work until its completion and final acceptance, and it is fully understood by the contractor that the acceptance of the work will not relieve him of any obligations to do reliable work as hereinbefore prescribed, and that any omission and disproof of any work by the said engineer at or before the time of the monthly or other estimate shall not be construed to be an acceptance of any defective work, and •that no acceptance whether final or otherwise, will relieve the said contractor or sureties on his bond from any of its obligations under the guaranteeing the said work for three years.”

It was provided, in the “Notice to Bidders and Specifications,” among other things, “Approximate estimates shall be made and payment given semimonthly. Ten per cent, of each approximate estimate shall be retained by the city until the completion of the work,” that “in case of any disagreement or dispute as to the true meaning of any point in the specifications, or as to the character of any part of the work, the decision of the city engineer shall be final and binding upon all the parties,” and that “before the final acceptance of the work, and payment of the balance due, the contractor shall furnish to the city proper evidence that all claims for labor and material have been paid, and that no legal claims can be filed against the city for such labor and material.”.

The contractor’s complaint charged full and complete performance of the contract on its part under the direction and with the approval of the city’s engineer, and that after allowance of all payments, admitted and set forth, there was still due contractor, for contract work and extras, $12,981.69.

The answer of the city substantially sets up four defenses to this claim: First. That the plaintiff had no right to sue, because it had assigned its claim to another, and had no real interest, therefore, in the demand. Second. The contract providing that all questions arising “as to the amount, quality, acceptability, fitness or final completion of the work” should be passed upon by the city engineer, and his decision should be final and a condition precedent to the contractor’s right to receive any money thereunder, it is charged that before institution of the suit and after alleged completion of the work certain questions were raised by the city as to the character of the work done, fully set forth, which questions were not submitted to the engineer, were not passed upon by him, and that therefore the contractor’s action was prematurely brought and should be dismissed. Third. That the contractor did not, prior to the institution of his action, furnish it with “proper evidence that all claims for labor and material have been paid and that no legal claims can be filed against the city for such labor and material” as provided by the contract to be a condition 'precedent to the payment of balance due him, and therefore his action should be dismissed as prematurely brought. Fourth: That, contrary to the requirements of the contract and the ‘‘notice to bidders and specifica[883]*883tions,” (1) the soft and boggy places in the subgrade were not filled with broken stone, or other hard material, and rolled and compacted. (2) That in preparing the concrete for the concrete base, instead of using the proportions of cement, sand, and stone as provided, said defendant in error used one part cement to five or six of sand to twelve or fifteen of stone, causing the said concrete base to be weak and of comparatively little value. (3) That said concrete base as constructed was less than four inches in thickness instead of five as provided. (4) That the brick used were not up to specifications, many of them being too soft, not having parallel sides and straight edges, and were not uniform in texture and appearance. (5) That the filler was improperly placed in the joints of said brick. (6) That the stone and sand used in said concrete were not kept free from dirt. (7) That in many places brickbats were used in lieu of bricks in laying said pavement. (8) That many of the brick used were chipped or broken. (9) That special rail brick were not laid along street car tracks. (10) That many of the brick laid along the car tracks were so placed as to stand higher than the surface of the street, making the same uneven and rough. That, in consequence, the contractor has failed to comply with its contract, but has constructed a pavement much inferior and worth, much less than the contract price. That this was accomplished by the misrepresentations and fraudulent acts of the contractor fully set forth, whereby the city engineer was deceived as to the quality of such work and was misled into making approximate estimates, eight in all, of the work done, seven of which were paid by the city. At this point it may be proper to state, although it is but incidentally referred to in this pleading, that it is shown elsewhere in the record and conceded that, after these seven estimates had been paid and after the eighth had been given, but before its payment, two citizens of the city, as taxpayers, secured from a state court an injunction against the city forbidding it to pay any further sums to the contractor by reason of the defective character of the work as indicated, and no other estimates of any kind were thereafter made by the engineer and no further payments were made by the city.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koich v. City of Helena
315 P.2d 811 (Montana Supreme Court, 1957)
City of Charlotte v. Atlantic Bitulithic Co.
228 F. 456 (Fourth Circuit, 1915)
Coal & Iron Ry. Co. v. Reherd
204 F. 859 (Fourth Circuit, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
168 F. 880, 94 C.C.A. 292, 1909 U.S. App. LEXIS 4514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-greensboro-v-southern-paving-construction-co-ca4-1909.