City of Fort Lauderdale v. Ross, Saarinen, Bolton & Wilder, Inc.

815 F. Supp. 444, 1992 U.S. Dist. LEXIS 20938, 1992 WL 448861
CourtDistrict Court, S.D. Florida
DecidedOctober 26, 1992
Docket90-6598-CIV
StatusPublished
Cited by2 cases

This text of 815 F. Supp. 444 (City of Fort Lauderdale v. Ross, Saarinen, Bolton & Wilder, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Fort Lauderdale v. Ross, Saarinen, Bolton & Wilder, Inc., 815 F. Supp. 444, 1992 U.S. Dist. LEXIS 20938, 1992 WL 448861 (S.D. Fla. 1992).

Opinion

ORDER DENYING MOTION TO DISMISS

PAINE-, District Judge.

Background

In July 1990, CITY OF FORT LAUDER-DALE (the “CITY”) sued ROSS, SAARINEN, BOLTON & WILDER, INC., and its successor, CAMP,' DRESSER & MCKEE, for breach of contract and negligence, 1 alleging that:

1. In July 1969, the CITY retained PHILPOTT, ROSS & SAARINEN, .INC., which became ROSS, SAARINEN, BOLTON & WILDER, INC., and is now CAMP, DRESSER &. MCKEE (collectively “ROSS”), to serve as consulting engineer for the design and construction of a one-mile long water transmission main.

2. Between 1974 and February 4, 1987, the CITY used the pipeline to transmit potable water, unaware of. any defect in its design and construction.

3. On July 9, 1985, a rupture occurred in the water transmission main. The ruptured pipe was replaced and the main returned to service.

4. On February 4, 1987, a second rupture occurred.

5. Following the second rupture, the CITY conducted an investigation, which revealed that a latent design defect rendered the entire pipeline worthless.

(Complaint (Exhibit to DE 1) 2 at ¶¶ 7-11, 14-17, 21).

*446 ROSS filed a Motion to Dismiss (DE 7), arguing that (i) the entire case is time-barred, and (ii) allegations in the breach of contract count contradict the express contractual terms.

Analysis

A motion to dismiss may raise two distinct issues: whether the plaintiff has stated his purported claim with sufficient detail, and whether the claim as stated is recognized by the law.

As to factual detail, the Federal Rules of Civil Procedure are very liberal. The complaint need only contain “a short and plain statement of the claim____” Fed. R.Civ.P. 8(a). “All that is required is that the defendant be on notice as to the claim being asserted against him and the grounds on which it rests.” Sams v. United Food & Commercial Workers Int’l Union, 866 F.2d 1380, 1384 (11th Cir.1989) (collecting cases). The parties may, through discovery, inquire further into the details underlying the claim. Bazal v. Belford Trucking Co., Inc., 442 F.Supp. 1089, 1102 (S.D.Fla.1977); see generally C. Wright and A. Miller, Federal Practice and Procedure § 1202 (2d Ed.1990).

[2] As to the viability of a cause of action, the Court must first accept all of the plaintiffs allegations as true. E.g., Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974); Jacobs v. Board of Regents, 473 F.Supp. 663, 665 (S.D.Fla.1979). Consideration of matters beyond the four corners of the complaint is improper. Milburn v. United States, 734 F.2d 762 (11th Cir.1984). A motion to dismiss should not be granted unless the plaintiff can prove no set of facts in support of his claim entitling him to relief. Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 101-02, 2 L.Ed.2d 80 (1957).

1. Statute of Limitations

The statute of limitations is ordinarily an affirmative defense, which must be pled and proven by the defendant. But when a complaint shows on its face that the limitations period has run, the defect may be raised by a motion to dismiss. Avco Corp. v. Precision Air Parts, Inc., 676 F.2d 494, 495 (11th Cir.1982).

ROSS argues, and the CITY agrees, that the contract and negligence counts are governed by a single statute providing for the commencement within four years of any action “founded on the design, planning, or construction of an improvement to real property.” Fla.Stat. § 95.11(3)(c). If the action involves a latent defect, the four-year period begins when .'“the defect is discovered or should have been discovered with the exercise of due diligence.” Id.

In this case, the CITY flatly alleges that it was “unaware” of the defect in pipe design on February 4, 1987, the date of the second rupture. (Complaint at ¶ 15). ROSS nonetheless argues that the limitations period must, as a matter of law, be measured from the first rupture (DE 7 at 7). Its argument is based upon three Florida cases: Havatampa Corp. v. McElvy, Jennewein, Stefany & Howard, Architects/Planners, Inc., 417 So.2d 703 (Fla.2d Dist.Ct.App.1982), Conquistador Condominium VIII Ass’n, Inc. v. Conquistador Corp., 500 So.2d 346 (Fla. 4th Dist.Ct. App.1987), and Almand Constr. Co., Inc. v. Evans, 547 So.2d 626 (Fla.1989).

In Havatampa, the owner “knew that the roof was leaking” when it took possession of a newly constructed manufacturing facility. 417 So.2d at 704. Despite inspections and repairs, the roof leaked “more or less continuously” for the next four-and-one-half years, when an independent consultant reported that the defect was complex and not easily discoverable. Id. The owner thereafter sued the architect, contractor, subcontractors, materialmen, and bonding company.

The appellate court, affirming a summary judgment for the defendants, held that the owner “cannot rely on a lack of knowledge of the specific cause of the problem to protect it against expiration of the four[-]year statute of limitations.” 417 So.2d at 704. The court rejected any suggestion that one must have “knowledge of the specific nature of the defect causing an obvious problem before the statute of limitations commences to run.” Id. (criticizing School Bd. of Seminole County v. GAF Corp., 413 So.2d 1208 (Fla. 5th *447 Dist.Ct.App.1982)). 3

In Conquistador, unit owners took control of a condominium in 1974 and discovered roof leaks by 1976. During a 1979 meeting, the condominium association reported that “much of [sic] all the trouble is the result of inadequate and shoddy construction — ” 500 So.2d at 347. That same year, the unit owners began spending money to repair the roof. But they did not file suit until five years later.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
815 F. Supp. 444, 1992 U.S. Dist. LEXIS 20938, 1992 WL 448861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-fort-lauderdale-v-ross-saarinen-bolton-wilder-inc-flsd-1992.