City of Elgin v. Elgin Memory Care, LLC

2020 IL App (2d) 200070-U
CourtAppellate Court of Illinois
DecidedFebruary 3, 2020
Docket2-20-0070
StatusUnpublished

This text of 2020 IL App (2d) 200070-U (City of Elgin v. Elgin Memory Care, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Elgin v. Elgin Memory Care, LLC, 2020 IL App (2d) 200070-U (Ill. Ct. App. 2020).

Opinion

2020 IL App (2d) 200070-U No. 2-20-0070 Order filed February 3, 2020

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT ______________________________________________________________________________

CITY OF ELGIN, an Illinois Municipal ) Appeal from the Circuit Court Corporation, ) of Kane County. ) Plaintiff-Appellee, ) ) v. ) No. 17-CH-846 ) ELGIN MEMORY CARE, LLC, ) ) Defendant-Appellant ) ) (Mace Iron Works, Inc., Accurate Housing ) Systems, Inc., Global Builders, Inc., and ) Honorable Elgin Memory Care Property Owners ) Kevin T. Busch, Association, Inc., Defendants). ) Judge, Presiding. ______________________________________________________________________________

JUSTICE SCHOSTOK delivered the judgment of the court. Justices Hutchinson and Hudson concurred in the judgment.

ORDER

¶1 Held: The trial court did not abuse its discretion in denying the defendant’s motion for a temporary restraining order because the defendant failed to raise a fair question as to the likelihood of success on the merits of its claims.

¶2 On September 21, 2017, the plaintiff, City of Elgin, filed a complaint against the

defendants, Elgin Memory Care, LLC (EMC), Mace Iron Works, Inc., Accurate Housing Systems,

Inc., Global Builders, Inc., and Elgin Memory Care Property Owners Association, Inc. The City 2020 IL App (2d) 200070-U

sought an order to demolish improvements on property owned by EMC in Elgin. In May 2018,

the parties reached an agreement on the issue, requiring EMC to take certain actions by June 15,

2019. EMC was unable to comply with the terms of the agreement. On January 13, 2020, EMC

filed a motion for a temporary restraining order (TRO) and preliminary injunction to prevent the

City from demolishing the improvements on its property. On January 22, 2020, the trial court

denied EMC’s motion for TRO. EMC appeals from this order. We affirm.

¶3 I. BACKGROUND

¶4 In August 2015, EMC was issued a building permit to construct a proposed 69,000-square-

foot nursing and personal care facility on a parcel of land located at 3271 U.S. Highway 20 in

Elgin. The permit expired on April 27, 2016. On June 20, 2016, a permit extension was approved

with said extension expiring on December 21, 2016. At some point during this time frame, a

general contractor, Global Builders, entered a construction agreement with EMC and commenced

construction on the project.

¶5 On September 23, 2016, Global Builders filed a complaint against EMC for breach of

contract and to foreclose its mechanic’s lien on the subject property. That case was docketed in

Kane County as case No. 16-CH-964. The complaint indicated that Global Builders had entered

into a construction agreement with EMC. Global Builders had completed some construction on

the subject property and EMC owed Global Builders over $2 million dollars. The record indicates

that a concrete slab was poured, utilities were brought to the site, and framing and partial sheathing

of the exterior and interior walls and the roof of the structure had been completed. The record

indicates that additional parties were named as counter-plaintiffs to the mechanic’s lien claim:

Mace Iron Works and Accurate Housing Systems.

-2- 2020 IL App (2d) 200070-U

¶6 EMC failed to complete construction of the proposed facility by the time the permit expired

in December 2016. On September 21, 2017, the City filed a two-count verified complaint against

EMC and the lien claimants, Global Builders, Mace Iron Works, and Accurate Housing Systems.

The City sought demolition or repair of the uncompleted facility pursuant to the provisions of the

Illinois Municipal Code (Code) governing the demolition of private property (65 ILCS 5/11-31-1

et seq. (West 2016)). The City argued that, if EMC could not complete construction of the

proposed facility, the improvements should be demolished, and the property restored to its

preconstruction condition. The City filed a later statement in support of its complaint alleging that

the subject property, in its current condition, was not only “dangerous and unsafe” but also

“uncompleted and abandoned” within the meaning of section 11-31-1 of the Code.

¶7 On May 15, 2018, the City and EMC entered a stipulation and agreed order. The agreed

order imposed two obligations upon EMC. First, EMC agreed that it would demolish the

previously constructed above-ground elements of the proposed facility and perform other site

restoration activities by July 15, 2018. If EMC failed to meet this deadline, the agreed order

provided that the City would be authorized to perform that above-ground demolition work.

Second, EMC agreed that if it did not recommence construction of the proposed facility by June

15, 2019, then it would remove the remaining improvements by July 15, 2019. The remaining

improvements were defined as, but not limited to, “the slab, foundation, light standards, parking

facilities, curb and gutter, and utilities to the property line.” The agreed order provided that if

EMC failed to recommence construction by the agreed deadline, then the City would be authorized

to perform the demolition and removal of the remaining improvements.

¶8 As of June 14, 2019, EMC had performed the required demolition of the above-ground

improvements and other site restoration but had not recommenced construction of the proposed

-3- 2020 IL App (2d) 200070-U

facility. On that date, EMC filed a motion to modify the agreed order, seeking a six-month

extension of time in which to recommence construction or perform demolition of the remaining

improvements. EMC alleged that it was in the process of obtaining the necessary financing to

complete construction. EMC explained that its efforts to obtain funding had been hindered because

it was named as a defendant in a civil suit filed by the Securities and Exchange Commission (SEC)

(case no. 1:17-cv-04686) in the U.S. District Court for the Northern District of Illinois, Eastern

Division. However, as of May 13, 2019, EMC had been dismissed from the civil suit and, since

that time, EMC alleged that it had been diligently pursuing the steps necessary to recommence

construction on the project. At a status hearing on July 18, 2019, EMC voluntarily withdrew its

motion to modify the agreed order.

¶9 On January 13, 2020, EMC filed its emergency motion for TRO and preliminary

injunction. EMC alleged that the subject property had undergone substantial improvement with

almost $3 million of site utility and concrete work. On information and belief, EMC believed the

City had entered into a contract to complete the demolition of the remaining improvements on the

subject property. EMC argued that the City had not provided proper notice to all interested parties

of the proposed demolition of the subject property. EMC also argued that there was no urgent

basis to demolish the subject property as the City had waited almost seven months to enforce its

right to do so under the agreed order. Finally, EMC alleged that preservation of the subject

property was an ascertainable right in need of protection, irreparable harm would occur if the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mohanty v. St. John Heart Clinic, S.C.
866 N.E.2d 85 (Illinois Supreme Court, 2006)
Foutch v. O'BRYANT
459 N.E.2d 958 (Illinois Supreme Court, 1984)
Bradford v. Wynstone Property Owners' Ass'n
823 N.E.2d 1166 (Appellate Court of Illinois, 2005)
City of Chicago v. General Realty Corp.
273 N.E.2d 712 (Appellate Court of Illinois, 1971)
In Re Marriage of Rolseth
907 N.E.2d 897 (Appellate Court of Illinois, 2009)
Corral v. Mervis Industries, Inc.
839 N.E.2d 524 (Illinois Supreme Court, 2005)
People Ex Rel. Devine v. Murphy
693 N.E.2d 349 (Illinois Supreme Court, 1998)
Yellow Cab Co. v. PRODUCTION WORKERS UNION
416 N.E.2d 48 (Appellate Court of Illinois, 1980)
Smith v. Airoom, Inc.
499 N.E.2d 1381 (Illinois Supreme Court, 1986)
Gakuba v. Kurtz
2015 IL App (2d) 140252 (Appellate Court of Illinois, 2015)
In re Marriage of Tutor
2011 IL App (2d) 100187 (Appellate Court of Illinois, 2011)
In re Marriage of McLauchlan
2012 IL App (1st) 102114 (Appellate Court of Illinois, 2012)
Capstone Financial Advisors, Inc. v. Plywaczynski
2015 IL App (2d) 150957 (Appellate Court of Illinois, 2016)
Fauley v. Metropolitan Life Insurance Co.
2016 IL App (2d) 150236 (Appellate Court of Illinois, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2020 IL App (2d) 200070-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-elgin-v-elgin-memory-care-llc-illappct-2020.