City of Dublin v. Beatley

2018 Ohio 3354, 119 N.E.3d 826
CourtOhio Court of Appeals
DecidedAugust 21, 2018
Docket18 CAE 01 0007
StatusPublished
Cited by2 cases

This text of 2018 Ohio 3354 (City of Dublin v. Beatley) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Dublin v. Beatley, 2018 Ohio 3354, 119 N.E.3d 826 (Ohio Ct. App. 2018).

Opinion

Baldwin, J.

{¶ 1} Appellant, Jack K. Beatley, appeals the Delaware County Common Pleas Court's December 26, 2017 denial of Appellant's Challenge to the Necessity of the Appropriation, and Appellee's Right to Appropriate the Property. Appellee is the City of Dublin. Jon Peterson, Delaware County Treasurer, is a nominal party but did not participate in this appeal.

STATEMENT OF FACTS AND THE CASE

{¶ 2} This case arises from Appellee's attempt to appropriate a portion of Appellant's property, namely, approximately 0.155-acre fee simple interest, all of which is encumbered with a roadway easement (also known as Present Road Occupied or P.R.O.), without limitation to existing access; an approximately 0.045-acre permanent slope, grading, and drainage easement; and an approximately 0.037-acre temporary construction easement, for the construction of the Glick Road Shared-Use Path (the Project).

{¶ 3} Appellee has been working to complete the Project since late 2012 or early 2013 when they approached Appellant and described their plans. Appellant reportedly rejected the plan and vowed to fight the Appellee if it continued with the Project.

{¶ 4} On February 24, 2014 Appellee adopted Resolution 15-14 (the "Resolution"), declaring Appellee's need for the property from Appellant and its intent to appropriate that property. A copy of that resolution was personally delivered to Appellant on March 3, 2014. On May 5, 2014 Appellee adopted Ordinance Number 26-14 (the "Ordinance"), authorizing Appellee to proceed with an appropriation action and take all steps necessary to appropriate the property interest from Appellant. Coincidentally, Appellant attended the City Council meeting on that date and made his opposition to the Project clear. On August 4, 2016 Appellee served a notice of intent to acquire and good faith offer letter (the "notice") as well as a copy of the city's appraisal report on Appellant personally. Because there was no agreement regarding the appropriation of the property interests of the Appellant, Appellee filed its petition for appropriation in the Delaware County Court of Common Pleas. Appellant filed a motion to dismiss the petition and the trial court denied that motion. On November 21, 2017, Appellant filed his answer challenging the necessity of the appropriation as well as Appellee's right to make the appropriation. The Appellee requested the trial court set a hearing to determine these challenges pursuant to the requirements of R.C. 163.09 (B)(1) which states that the trial court " shall set a day, not less than five nor more than fifteen days from the date the answer was filed to hear these matters." (Emphasis added). A hearing was scheduled for Friday, December 1, 2017.

{¶ 5} Appellee presented the testimony of Paul Hammersmith, Director of Engineering for Appellee since January 2002. Mr. Hammersmith confirmed that the Project involved the use of the property sought for public purposes, namely a shared-use path that would be part of the public infrastructure. The path was part of a larger project connecting these paths throughout the Appellee's territory to accommodate pedestrians and non-motorized vehicles. Mr. Hammersmith described the property rights sought as necessary for the completion of the project.

{¶ 6} Appellee offered into evidence the resolution and ordinance authorizing the appropriation as well as two exhibits describing the Appellee's general plan for such paths in the municipality and maps showing current and future shared use paths.

{¶ 7} Appellant testified and presented several exhibits. He claimed the project would interfere with access to his property and suggested that the Appellant should consider a different location for the path. He also expressed the concern that the path would be installed within fifteen feet of the face of his house, placing him in violation of local setback requirements. Appellant conceded on cross-examination that he had "not been able to come to an agreement with the City of Dublin about the proposed acquisition" (Tr, page 92, l. 17-19) and contended that the Appellant could construct the shared use path within the current easement without acquiring any additional property interest from Appellee.

{¶ 8} The trial court issued its decision on December 26, 2017 concluding "that the appropriation is in fact necessary and that Dublin is entitled to proceed with its efforts to appropriate Beatley's property." (Judgment Entry, December 26, 2017, page 1) Appellee filed his notice of appeal on January 25, 2018 and submitted six assignments of error:

{¶ 9} "I. THE TRIAL COURT COMMITTED AN ERROR OF LAW IN ITS CONCLUSION THAT SUBJECT MATTER JURISDICTION WAS NOT LACKING."

{¶ 10} "II. THE TRIAL COURT ERRED IN ITS DETERMINATION THAT DUBLIN HAD A RIGHT TO APPROPRIATE MR. BEATLEY'S REAL PROPERTY FOR A USE DESCRIBED AS A "MULTI-USE" PATH."

{¶ 11} "III. THE TRIAL COURT ERRED IN ITS DETERMINATION THAT DUBLIN HAD A RIGHT TO APPROPRIATE EXCESS PROPERTY BEYOND THAT REQUIRED FOR THE MULTI-USE PATH."

{¶ 12} "IV. THE TRIAL COURT ERRED IN ITS DETERMINATION THAT DUBLIN ESTABLISHED THAT THE TAKING WAS NECESSARY."

{¶ 13} "V. THE TRIAL COURT ERRED IN ITS CONCLUSION THAT DUBLIN HAD A RIGHT TO MAKE THE TAKE(sic), WHEN DUBLIN FAILED TO DEMONSTRATE COMPLIANCE WITH R.C. 163.04(E)."

{¶ 14} "VI. THE TRIAL COURT ERRED IN ITS ADMISSION OF EVIDENCE AND TESTIMONY RECEIVED FROM MR. HAMMERSMITH."

STANDARD OF REVIEW

{¶ 15} The Appellant's first assignment of error addresses the subject matter jurisdiction of the trial court and, on that issue, our review is de novo . Dotts v. Schaefer , 5th Dist. Tuscarawas No. 2014 AP 03 0012, 2015-Ohio-781 , 2015 WL 965720 , ¶ 9. We are limited to determining whether there is competent and credible evidence to support the trial court's finding of a lack of abuse of discretion when reviewing assignments Two through Four. As we held in Atwood Regional Water & Sewer Dist. v. Smith , 5th Dist. Tuscarawas No. 2016 AP 05 0026, 2017-Ohio-206 , 2017 WL 235304 , ¶ 33 :

Here Appellee * * * adopted a resolution of necessity for the appropriation. Thus, under R.C. § 163.09(B), the burden of proof fell upon [Appellant] to demonstrate that the appropriation was not necessary. In order to find that there was no necessity for the appropriation, the trial court would have had to determine that Appellee * * *abused its discretion. In reviewing the trial court's conclusion that there was no such abuse of discretion, we are limited to determining whether the decision was supported by competent and credible evidence. City of Toledo v. Kim's Auto & Truck Service, Inc., 6th Dist. No. L-02-1318, 2003-Ohio-5604 [

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mill Creek Metro. Dist. Bd. of Commrs. v. Less
2022 Ohio 1289 (Ohio Court of Appeals, 2022)
Ohio Power Co. v. Duff
2020 Ohio 4628 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 3354, 119 N.E.3d 826, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-dublin-v-beatley-ohioctapp-2018.