City of Detroit v. Porath

260 N.W. 114, 271 Mich. 42, 1935 Mich. LEXIS 772
CourtMichigan Supreme Court
DecidedApril 8, 1935
DocketDocket No. 120, Calendar No. 37,939.
StatusPublished
Cited by21 cases

This text of 260 N.W. 114 (City of Detroit v. Porath) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Detroit v. Porath, 260 N.W. 114, 271 Mich. 42, 1935 Mich. LEXIS 772 (Mich. 1935).

Opinion

Potter, C. J.

Plaintiff brought suit against defendant contractors doing business as Julius Porath & Son, and the sureties upon their bond, to recover *48 damages arising out of an alleged breach of a contract entered into by defendant contractors with plaintiff for the construction of section one of the Mill road an'd Southfield sewer, from River Rouge to Ford road, approximately 8,000 feet- in length, by defendant contractors for $690,762.50. The contract was entered into November 3, 1926, and the sewer completed and accepted about one year and nine months later. In February, 1930, a part of this sewer failed, at a point approximately 1,800 to 2,000 feet south of Ford road. Later, another part of it near Ford road collapsed. This resulted in an investigation of the sewer by plaintiff which employed the so-called Wrentmore commission to determine the cause or causes of the failure, and to plan and supervise the work of reconstruction. The sewer was repaired and the collapsed portions “rebuilt by the city under contract with one Healy, for which plaintiff claims $355,411.61 for repairs, including investigation services, labor and material, and other damages arising from the original defective construction of the sewer contrary to the contract, not included in the part of the same which collapsed, the gross amount claimed upon the trial being $355,-411.61, made up of:

Cleaning sewer barrel, 0-00 to 80-

32.5 ...........................$ 32,012.63

Uncovering sewer, break No. 2..... 10,066.28

Calking sewer.................... 20,665.13

Sewer repair, concrete, Sta. 0-0 to

1-00 ...... 20,814.18

Sewer repair, concrete, Sta. 28-49

to 37-65 ........................ 11,950.32

Driving sheeting ................. 19,579.39

Pumping......................... 35,957.93

*49 Miscellaneous material............$ 3,065.75

Cost of relining 2,856 ft. at $50..... 142,800.00

Cost of reconstructing in tunnel

Sta. 61-40 to 63-66, 226 ft.

Sta. 78-82 to 80-32.5, 150.5 ft.

376.5 ft. 58,500.00

Total.................$355,411.61

After the sewer was repaired and the collapsed portions thereof rebuilt, plaintiff instituted suit to recover what it claimed to be its damages, alleging the original contract with defendant contractors had not been carried out:

1— That inferior material and improper mixing of concrete had been used, resulting in poor concrete, which caused collapse of the sewer;

2— There had been faulty workmanship and negligent, careless and improper mixing and placing of concrete by defendant contractors, resulting in a compressive strength lower than required by the contract, plans and specifications;

3— The faulty workmanship and negligent, careless and improper mixing and placing of concrete for construction of the sewer had resulted in its walls being thinner than was required by contract; and the reduction in thickness of the walls of the sewer weakened the structure so as to cause collapse and complete failure of the sewer to carry the sewage and storm water for which it was constructed ;

4— The faulty workmanship and negligent, careless and improper precautions taken by defendant contractors for obtaining sufficient bond in the joints of the concrete and adequate keys at con *50 struction joints resulted in the sewer being insecurely connected together;

5— The failure to use steel tunnel liner plates at points where soil conditions were such as to make their use necessary to properly place the concrete caused the sewer to collapse and become useless;

6— —The faulty workmanship and negligent, careless and improper placing of the steel tunnel liner plates by defendant contractors caused the sewer to collapse and become useless for the purposes for which it was constructed under the plans and specifications of the contract;

7— —-The faulty workmanship and negligent, careless and improper mixing and placing of concrete by contracting defendants resulted in porous concrete which permitted infiltration of ground water and quicksand into the barrel of the sewer, with a consequent displacement of the foundation of the sewer which caused it to collapse;

8— -With the movement and displacement of the foundation of the sewer, the structure, already weak by reason of inferior concrete and thin walls, developed large cracks through which water and quicksand percolated, and the collapse and failure of the sewer became progressive;

9— The faulty workmanship and inadequate and improper control and management of the construction methods used in building the sewer by contracting defendants resulted in improper alignment of the walls and irregular grade of the sewer which materially reduced the capacity of the sewer and rendered it useless to the city;

10— Defendant contractors neglected to and did not construct the sewer in accordance with the provisions of the contract, plans and specifications; the work was not done in a thorough and workmanlike *51 manner; plaintiff, when it made monthly payments and when it made final payment to defendants, had no knowledge of the defective material and faulty workmanship in the sewer and no knowledge it was not constructed in accordance with the terms of the contract, plans and specifications ;

11— The contracting defendants, their agents, servants and employees, by fraud and collusion, obtained monthly payments and final payment on the contract from plaintiff, although knowing at the time the sewer was not constructed in accordance with the terms of the contract, plans and specifications and was defective;

12— The contracting defendants represented to plaintiff the sewer was constructed in accordance with the terms of the contract, plans and specifications ;

13— Contracting defendants, in order to conceal faulty construction and defects and failure to comply with the terms of the contract, plans and specifications, carried on the work of construction so as to conceal such facts from plaintiff;

14— At numerous places in the sewer, defective concrete was concealed by being plastered over with cement mortar, and by reason of the failure of defendant contractors to construct the sewer in ac- . cordance with the contract, plans and specifications, and its faulty method of construction, it collapsed and became defective, dangerous and unsafe, and wholly unfit for the purposes for which it was constructed.

All of these claims upon the part of plaintiff were denied in the several answers filed.

The contract provided the commissioner of public works of the city should issue monthly certificates showing the estimated amount due the contractor, *52

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chalk Supply LLC v. Ribbe Real Estate LLC
Michigan Court of Appeals, 2020
Alticor, Inc. v. National Union Fire Insurance
345 Fed. Appx. 995 (Sixth Circuit, 2009)
Tigg Corporation v. Dow Corning Corporation
822 F.2d 358 (Third Circuit, 1987)
Beattie v. Firnschild
394 N.W.2d 107 (Michigan Court of Appeals, 1986)
Slocum v. Ford Motor Company
314 N.W.2d 546 (Michigan Court of Appeals, 1981)
Lynch v. Sign of the Beefeater, Inc.
282 N.W.2d 321 (Michigan Court of Appeals, 1979)
Turner v. Bituminous Casualty Co.
244 N.W.2d 873 (Michigan Supreme Court, 1976)
Ferguson v. Gonyaw
236 N.W.2d 543 (Michigan Court of Appeals, 1975)
Jones v. Bloom
200 N.W.2d 196 (Michigan Supreme Court, 1972)
Mysliwiez v. Newark-Ferguson Electronics, Inc.
178 N.W.2d 73 (Michigan Court of Appeals, 1970)
People v. Childers
174 N.W.2d 565 (Michigan Court of Appeals, 1969)
Ruhala v. Roby
150 N.W.2d 146 (Michigan Supreme Court, 1967)
Petrosky v. Dziurman
116 N.W.2d 748 (Michigan Supreme Court, 1962)
Gordon v. Sutherland
131 So. 2d 520 (District Court of Appeal of Florida, 1961)
Monaghan v. Pavsner
80 N.W.2d 218 (Michigan Supreme Court, 1956)
City of Detroit v. City of Highland Park
39 N.W.2d 325 (Michigan Supreme Court, 1949)
Brkal v. Pletcher
18 N.W.2d 815 (Michigan Supreme Court, 1945)
Anderson v. Jersey Creamery Co.
270 N.W. 725 (Michigan Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
260 N.W. 114, 271 Mich. 42, 1935 Mich. LEXIS 772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-detroit-v-porath-mich-1935.