City of Detroit v. A. W. Kutsche & Co.

16 N.W.2d 128, 309 Mich. 700
CourtMichigan Supreme Court
DecidedOctober 11, 1944
DocketDocket No. 16, Calendar No. 42,720.
StatusPublished
Cited by32 cases

This text of 16 N.W.2d 128 (City of Detroit v. A. W. Kutsche & Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Detroit v. A. W. Kutsche & Co., 16 N.W.2d 128, 309 Mich. 700 (Mich. 1944).

Opinion

Reid, J.

The bill was filed for an injunction restraining defendant A. W. Kutsche & Company *703 from presenting' before an arbitration board its claim against the city arising out of a contract for construction of a sludge digestion tank, elutriation tanks and gas. holder for a sewage treatment plant, and to restrain three defendants, members of a board of arbitration, from proceeding to arbitrate the claim of A. W. Kutsche & Company, hereinafter referred to as the defendant. The members of the board make no defense.

The contract provided for arbitration of claims and disputes arising under it, but plaintiff claims that the provisions therefor were revocable unilaterally, that defendant lost the right and plaintiff lost the benefits of arbitration by defendant’s failure to give timely notice of the various items of its claims from time to time as they arose, thus preventing plaintiff from demanding arbitrations as the work progressed, and that defendant failed to make timely demand for general arbitration. '

Defendant denies these statements and theories and claims that plaintiff does not come into the equity court with clean hands and that plaintiff has 'an adequate remedy at law. The parties agree that the provisions for arbitration in question do not come under or within the Michigan arbitration statute. The general policy of this State is favorable to arbitration, as shown by 3 .Comp. Laws 1929, § 15394, as amended by Act No. 182, Pub. Acts 1941 (Comp. Laws Supp. 1943, § 153945.Stat. Ann. 1943 Rev. § 27.2483), enacted after this controversy arose. See, also, Alpena Lumber Co. v. Fletcher, 48 Mich. 555, 569. If parties desire arbitration, courts should encourage .them, but the nature of such a contract requires faithful compliance with its terms, otherwise the parties will find themselves in the forum they sought to avoid.

*704 The contract provides, among other things ¡

“19. Arbitration.

“The contract contains a provision for arbitration as to any matter of dispute involving time or financial considerations and said arbitration shall be a condition precedent to any right of legal action under the contract. * * * “20. Claims for extra cost.

“If the contractor claims that any instructions by drawings or otherwise involve extra cost under this contract, he shall give the commissioner written notice thereof within 48 hours after the receipt of such instructions and in any event before proceeding to execute the work, except in emergency endangering life or property, and the procedure shall be as provided for changes in the work. No such claim shall be valid unless so made. * * * “27. Damages.

“Any claim for damage arising under this contract shall be made in writing to the party liable within a reasonable time of the first observance of such damage and not later 'than the time of final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration, f * * ‘£ 34. Engineer’s decisions.

“The engineer shall, within a reasonable time after their presentation to him, make decisions in writing on all claims of the city or the contractor and on all other matters relating to the execution and progress of the work, or the interpretation of the contract documents.

“All such decisions of the engineer shall be final except in cases where time or financial considerations are involved, which, if no agreement in regard thereto is reached, shall be subject to arbitration. * * #

£ £ 39. Arbitration.

“Any decision of the commissioner where time or financial considerations are involved shall be sub *705 mitted to arbitration upon the demand of either party to the dispute.

“The contractor shall not cause a delay of the work during any arbitration proceedings, except by agreement with the commissioner.

“The demand for arbitration shall be filed in writing with the commissioner, in the case of an appeal from his decision, within ten days of its receipt and in any other case within a reasonable time after cause thereof and in no case later than the time of final payment, except as otherwise expressly stipulated in the contract. If the commissioner fails to make a decision within a reasonable time, an appeal to arbitration may be taken as if his decision has been rendered against the party appealing.”

The benefit that plaintiff would derive from timely notice of a claim is that while the controversy was fresh, the engineer and others could see the status of the construction still in progress, and witnesses would still be available and' would possess a better recollection of the matters. In consequence, the plaintiff could seasonably demand arbitration and better present its case. Demand for arbitration could not be made until the claim was presented. Defendant appropriately cites from McCullough v. Clinch-Mitchell Construction Co. (C. C. A.), 71 Fed. (2d) 17:

“It is common knowledge that arbitration provisions of this character are almost universal in construction contracts to prevent the harassments, delays, and losses likely to result to some or all of the parties thereto arising from differences ocr curring during the progress of the work. All construction contracts involve matters as to character of materials, of work, and of methods of doing the work. Determination of such is necessarily a matter of judgment and often the diverse interests of *706 the parties cause difference of opinion with resulting disputes concerning them. It is to the interest of all parties that these disputes he promptly determined and by some one having special knowledge of such matters and who can act upon personal knowledge of the controlling facts.”

Plaintiff justly complains of the loss of such benefits through defendant’s delay.

The contract was entered into February 23, 1938. The work was to be completed December 31, 1938, the price $261,963.04, all of which was paid except $13,245.75 withheld until final estimate. The work was substantially or 97 per cent, completed on March 1, 1939. Some items of construction claimed as uncompleted were pointed out by plaintiff in July, 1939. ■ Nearly all items of plaintiff’s claim occurred before March 27, 1939. All were for matters occurring during the construction. Many of the items were without the 48-hours’ notice required in article 20 and many without any notice whatever. Correspondence over contract matters took place. On September 19, 1938, plaintiff wrote defendant:

“Should you still feel you have a claim against us in this, the procedure for arbitration is well outlined in the contract documents. * * * We again want to emphasize the importance of proceeding without delay in accordance with the instructions given you in Mr. Johnson’s letter of September 16th and again point out to you that you have the privilege to arbitrate any decision or instruction involving financial considerations, in your opinion, in accordance with article 39 * * ■ * We wish also to point out that any delay

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yaser Saidizand v. Gojet Airlines LLC
Michigan Court of Appeals, 2026
Ari-El Financial LLC v. Joe Barbat
Michigan Court of Appeals, 2026
Shaunte Johnson v. Best Buy Company Inc
Michigan Court of Appeals, 2025
Doe v. The Coliseum, Inc.
E.D. Michigan, 2024
Samantha Lichon v. Michael Morse
Michigan Supreme Court, 2021
Jordan Smits v. Michael Morse
Michigan Supreme Court, 2021
Samantha Lichon v. Michael Morse
Michigan Court of Appeals, 2019
Altobelli v. Hartmann
884 N.W.2d 537 (Michigan Supreme Court, 2016)
Wold Architects and Engineers v. Strat
713 N.W.2d 750 (Michigan Supreme Court, 2006)
Pack v. Damon Corp.
320 F. Supp. 2d 545 (E.D. Michigan, 2004)
Hetrick v. Friedman
602 N.W.2d 603 (Michigan Court of Appeals, 1999)
Rembert v. Ryan’s Family Steak Houses, Inc
596 N.W.2d 208 (Michigan Court of Appeals, 1999)
Amtower v. William C Roney & Co.
590 N.W.2d 580 (Michigan Court of Appeals, 1999)
Rembert v. Ryan's Family Steak House, Inc.
575 N.W.2d 287 (Michigan Court of Appeals, 1998)
Rembert v. Ryan's Family Steakhouse, Inc.
226 Mich. App. 822 (Michigan Court of Appeals, 1997)
Heurtebise v. Reliable Business Computers, Inc
550 N.W.2d 243 (Michigan Supreme Court, 1996)
Heurtebise v. Reliable Business Computers, Inc.
523 N.W.2d 904 (Michigan Court of Appeals, 1994)
McKinstry v. Valley Obstetrics-Gynecology Clinic, PC
405 N.W.2d 88 (Michigan Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
16 N.W.2d 128, 309 Mich. 700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-detroit-v-a-w-kutsche-co-mich-1944.