City of DeKalb Ex Rel. International Pipe & Ceramics Corp. v. Sornsin

196 N.E.2d 502, 46 Ill. App. 2d 161, 1964 Ill. App. LEXIS 597
CourtAppellate Court of Illinois
DecidedFebruary 24, 1964
DocketGen. 11,834
StatusPublished
Cited by4 cases

This text of 196 N.E.2d 502 (City of DeKalb Ex Rel. International Pipe & Ceramics Corp. v. Sornsin) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of DeKalb Ex Rel. International Pipe & Ceramics Corp. v. Sornsin, 196 N.E.2d 502, 46 Ill. App. 2d 161, 1964 Ill. App. LEXIS 597 (Ill. Ct. App. 1964).

Opinion

CARROLL, J.

This is an action at law brought by a subcontractor to recover an unpaid balance due it for materials furnished to and used by a contractor in the construction of a certain public improvement for the City of DeKalb.

On March 11,1957 M. M. Sornsin d/b/a M. M. Sornsin Co. (referred to herein as Sornsin), entered into a contract with the City of DeKalb for the construction of a storm sewer addition. Pursuant to Paragraphs 15 and 16, Chap 29, Illinois Revised Statutes 1957, Sornsin executed and delivered to the City of DeKalb a performance bond dated March 11, 1957 with New Amsterdam Casualty Co. as surety, a condition of said bond being prompt payment by the principal to all persons supplying labor or materials for use in the prosecution of work or performance of Sornsin’s contract with DeKalb. Lock Joint Pipe Co. (herein referred to as Lock Joint) and whose successor is National Pipe and Ceramic Corporation, furnished materials to Sornsin which were used in performance of his contract. Sornsin failed to pay Lock Joint the balance due for such materials amounting to $70,964.26. The last delivery of materials by Lock Joint was made some time prior to November 14, 1957 and on or prior to that date all work provided to be done by Sornsin under the contract was completed and the improvement turned over to DeKalb which thereupon took possession of the same. Final payment on the contract pursuant to the engineer’s final certificate was made February 14, 1955. On July 30, 1559, which was more than 180 days after the furnishing of the last item of materials, Lock Joint filed a verified notice of its claim on the contractor’s bond with the mayor, clerk and treasurer of DeKalb.

This suit was filed June 23, 1959 more than 18 months after Sornsin completed his work, and more than 6 months after issuance of the engineer’» final estimate and the making of the final payment on the contract. On August 26, 1959, plaintiff filed an amended complaint in three counts. The trial court granted plaintiffs’ motion far summary judgment on Count 2 and entered, judgment in its favor for the balance due Lock Joint plus interest at five per cent from February 16, 1959. Defendant’s motion for summary judgment on each of the three counts of the amended eomplaint was denied. Defendant has prosecuted this appeal from the judgment entered on Count 2 and plaintiff has cross-appealed from the portion of its judgment allowing interest from February 14, 1959 to May 17, 1963. Defendant also appeals from the order denying its motion.

It is alleged in Count 2 that the bond executed and delivered by Sornsin with New Amsterdam Casualty Co. as surety is deemed to contain the following provisions of Sections 15 and 16, Chap 29, Illinois Revised Statutes, 1957.

“The principal and sureties on this bond agree to pay all persons, firms and corporations having contracts with the principal or with subcontractors, all just clamas due them under the provisions of such contracts for labor performed or materials furnished, in the performance of the contract on aceount of which this bond is given, when such claims are not satisfied out of the contract priee of the contract on aceount of which this bond is given, after final settlement between the officer, board, commission or agent of the State or of any political subdivision thereof and the principal has been made.”

It is further alleged in said eount that it is a proceeding instituted- pursuant to the provisions of Section 15, Chap 29, Illinois Revised Statutes 1957. Count 2r contains no allegations with reference to the date upon which Lock Joint last furnished materials or that it filed a verified notice of its claim for material within 180 days after such date or dates, and it is not alleged in said count that plaintiff’s action is brought within six months after acceptance of the project by DeKalb. It is thus apparent that in Count 2 plaintiff has proceeded upon the theory that an action may be predicated on the provisions which a contractor’s bond is deemed to contain by force of Section 1 of the Act (referred to as Section 15) relating to bonds of contractors entering into public improvement contracts without alleging performance of the conditions precedent to an action on such a bond as set out in Section 2 (referred to by plaintiff as Section 16) of said Aet. Defendant contends that plaintiff cannot recover on the bond in this case because it has not met the conditions precedent set forth in the Act in that (1) it failed to file a verified notice of its claim with DeKalb within 180 days after the date of the last furnishing of material as required by said Act and (2) it did not bring its suit within six months after acceptance of the improvement by DeKalb which is the time limitation placed on such a suit by the Act.

The Act under which this suit is brought was enacted in 1931 and is entitled “An Act in relation to bonds of contractor’s entering into contracts for public construction.” It consists of two sections. Section 1 (par 15 of c 29, Rev Stats) as originally enacted provided that officials, boards, commissioners, or other agents in making contracts for public work of any kind shall require the general contractor to furnish a bond which “shall be conditioned for the payment of material used in such work and for all labor performed in such work, whether by subcontractor nr otherwise.” By amendment in 1941 there was added to Section 1 the .provision which was set out in Count 2 of the amended complaint and which we have quoted verbatim herein. Section 2 of the Act as amended (par 16, c 29, Rev Stats) insofar as pertinent here provides that:

“Every person furnishing material or performing labor, either as an individual or as a subcontractor for any contractor, with the State, or a political subdivision thereof where bond shall be exeeuted-as provided in this Act,-shall have-the right to sue on such bond in the name of the State, or the political subdivision thereof entering into such contract, as the case may be, for his use and benefit, and in such suit the plaintiff shall file a copy of such bond, certified by the party or parties in whose charge such bond shall be, which copy shall, unless execution thereof be denied under oath, be prima facie evidence of the execution and delivery of the original; provided, however, that this Act shall not be taken to in any way make the State, or the political subdivision thereof entering into such contract, as the case may be, liable to such subcontractor, materialman or laborer to any greater extent than it was liable under the law as it stood before the adoption of this Act . . . Provided, further, that no action shall be brought until the expiration of one hundred and twenty (120) days after the date of the last item of work or the furnishing of the last item of materials, except in cases where the final settlement between the officer, board, bureau or department of municipal corporation and the contractor shall have been made prior to the expiration of the one hundred and twenty (120) day period in which case action may be taken immediately following such filial settlement; nor shall any action of any kind be brought later than six (6) months after the acceptance by the State or political subdivision thereof of the building project or work. Such suit shall be brought only in the circuit court of this State in the judicial district in which the contract is to be performed.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
196 N.E.2d 502, 46 Ill. App. 2d 161, 1964 Ill. App. LEXIS 597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-dekalb-ex-rel-international-pipe-ceramics-corp-v-sornsin-illappct-1964.