City of Dearborn v. DLZ CORP.

111 F. Supp. 2d 900, 2000 U.S. Dist. LEXIS 13079, 2000 WL 1269737
CourtDistrict Court, E.D. Michigan
DecidedSeptember 1, 2000
DocketCIV.00-71329
StatusPublished
Cited by4 cases

This text of 111 F. Supp. 2d 900 (City of Dearborn v. DLZ CORP.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Dearborn v. DLZ CORP., 111 F. Supp. 2d 900, 2000 U.S. Dist. LEXIS 13079, 2000 WL 1269737 (E.D. Mich. 2000).

Opinion

Opinion and Order

FEIKENS, District Judge.

I. Introduction

In its amended complaint, the City of Dearborn (“Dearborn”) alleges various fraud and misrepresentation counts, a conspiracy count, a negligence count, a breach of contract count, and an indemnification count against defendants. All its allegations focus on a contract that Dearborn entered into with Snell, Inc. (“Snell”), which is not named as a defendant. Dear-born names three corporate defendants, DLZ Corp. (“DLZ”), Dodson-Stilson, Inc. (“Dodson-Stilson”), and JDJ & A, Inc. (“JDJ & A”), and two individual defendants, Pratap Rajadhyaksha, Chief Operating Officer of Snell and vice-president and majority shareholder of DLZ, and Thomas Sisley, an employee of JDJ & A. The defendants move to dismiss the complaint. Additionally, Snell moves to intervene.

II. Factual Background

In order to treat its stormwater and wastewater in compliance with state and federal law, in October 1992, Dearborn solicited proposals for the construction of retention basins. During excessive flows, stormwater and wastewater would be captured in such basins and then bled back into the transportation systems for adequate treatment. In response, Snell proposed a retention treatment tunnel in lieu of the retention basins. Dearborn accepted this proposal and Snell and Dearborn executed a contract (the “Snell contract”) on May 20, 1993. Under the contract, Snell was to.design and provide .engineering services for the construction of the tunnel.

The tunnel project was not workable. Dearborn terminated Snell’s contract in 1994 and, in 1996, it terminated the tunnel project.

In 1998, Koenig Fuel and Supply Co., a contractor on the tunnel project sued Dearborn for damages in state court. (They eventually settled.) Dearborn then filed a third-party complaint in that case against Snell. It sued Snell for damages resulting from negligence, breach of contract, and for indemnification. On Snell’s first motion for summary disposition, the state court judge held that the claims for negligence and breach of contract were malpractice claims and were time-barred under Michigan’s two-year statute of limitations for malpractice claims. The state court judge also granted Snell’s second motion for summary disposition on the indemnification claim holding that, because of its revisions of the tunnel project, Dear-born had materially altered Snell’s risk.

In that case, Dearborn had also filed a motion to amend its complaint to add as defendants, DLZ Corp., Dodson-Stilson, Inc. — both defendants in this federal case — Cole Associates, Inc. and DLZ Laboratories. The state court judge denied that motion. The state court case is now on appeal.

On March 15, 2000, Dearborn filed the original complaint and an amended complaint on April 25, 2000 in the case before me.

III.The Defendants as Alter Egos to Snell

Because I consider evidence submitted by the parties, I treat this motion to dis *902 miss as a motion for summary judgment under Rule 56. See Fed.R.Civ.P. 12(c).

Dearborn’s complaint contains a telling, repeated peculiarity: it describes all of the defendants’ actions as having occurred “by and through Snell.” It does so because it had no contract with any of the defendants, only a contract with Snell. To get around the fact that it had no contract with any of the defendants, Dearborn alleges that those defendants in reality performed the contract for Snell. DLZ is the parent corporation and Snell its subsidiary. Dearborn alleges that the “defendants concealed the fact that DLZ and other DLZ subsidiaries would be involved in the project.” Amended Complaint ¶ 72. It alleges that the defendants, through Snell, misrepresented their own finances, experience, and personnel as Snell’s finances, experience, and personnel. See Count I of Amended Complaint, ¶ 97, 102, 103, 113; Count II, ¶¶ 116, 121, 122, 123, 130; Count IV, ¶¶140, 146, 149; Count VII, 172, 178. Dearborn’s descriptions of the defendants’ actions indicates that the complaint relies on an argument that the defendants were the alter ego of Snell. In effect, to get around the lack of a contract with the defendants and to make the defendants responsible for Snell’s obligations under the contract, Dearborn seeks to pierce Snell’s corporate veil.

Under Michigan law, a “ ‘corporate veil’ may be pierced only where an otherwise separate corporate existence has been used to subvert justice or cause a result that [is] contrary to some other clearly overriding public policy." Seasword v. Hilti, Inc., 449 Mich. 542, 548, 537 N.W.2d 221 (1995) (internal quotations and citations omitted) (emphasis added); see, also, U.S. v. Cordova Chemical Co. of Michigan, 113 F.3d 572, 580 (6th Cir.1990), vacated on other grounds, sub nom Michigan Department of Environmental Quality v. Bestfoods, 524 U.S. 924, 118 S.Ct. 2317, 141 L.Ed.2d 692 (1998). Thus, the allegation of functional integration of Snell and the defendants, through common ownership and personnel, would not alone be sufficient to pierce Snell’s corporate veil to foist liability onto the defendants unless there is an additional allegation that this integration was intended to “subvert justice” or cause a result “that is contrary to overriding public policy.”

Here, Dearborn’s alter ego argument rests on its allegations that the defendants unlawfully concealed their involvement in the Snell contract so that Snell would receive the contract and the defendants could avoid liability. Amended Complaint ¶¶ 72, 74, 77-80, 81, 83. But, Dearborn was aware of the defendants’ relationship to Snell before it entered into the Snell contract. Dearborn had hired Hinshon Environmental Group (“Hinshon”) to evaluate Snell’s tunnel proposal. In its report dated February 24, 1993 and revised on March 8, 1993, Hinshon described Snell under the heading, “Capability of Firms”:

SEG [Snell Environmental Group] is... a well-respected engineering design firm with a long history of involvement in wastewater projects in the state.... The firm- has recently been acquired by a larger corporate entity (DLZ) which is able to augment SEG’s capabilities. Tunnel design expertise to support the proposed Dearborn project is available through DLZ affiliates located in Cleveland, in addition to the staff resources available in SEG’s Lansing office. The combined talents should be more than adequate to successfully design and construct the proposed tunnel project.

Dearborn’s Amended Complaint, Exh. .T, p. 8-9. This report, contained in Dear-born’s complaint, belies Dearborn’s allegation that the integration of Snell and the defendants had the unlawful purpose of trying to conceal the defendants’ involvement in the Snell contract.

Without the allegation required under Michigan law, Dearborn’s alter ego argument fails and the complaint must be dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
111 F. Supp. 2d 900, 2000 U.S. Dist. LEXIS 13079, 2000 WL 1269737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-dearborn-v-dlz-corp-mied-2000.