City of Dallas v. Brown

31 S.W. 298, 10 Tex. Civ. App. 612, 1895 Tex. App. LEXIS 142
CourtCourt of Appeals of Texas
DecidedMay 8, 1895
DocketNo. 1175.
StatusPublished
Cited by2 cases

This text of 31 S.W. 298 (City of Dallas v. Brown) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Dallas v. Brown, 31 S.W. 298, 10 Tex. Civ. App. 612, 1895 Tex. App. LEXIS 142 (Tex. Ct. App. 1895).

Opinion

FINLEY, Associate Justice.

This suit was instituted by plaintiff, F. O. Brown, appellee, in the Fourteenth Judicial District Court of Texas, Dallas County, on November 30, 1892, to recover of the defendant city of Dallas, appellant, the sum of $3008,14, for the cost of paving and grading four feet in width on Pacific avenue, from Griffin street to the Houston & Texas Central Railroad; said four feet alleged to be extra and over and above that contracted to be improved. Plaintiff’s petition alleged that Laing & Smoot, a firm of contractors, entered into a contract with the cityof Dallas, on June 28, 1890, whereby they agreed to excavate, pave, and curb said Pacific avenue between said points, according to plans and specifications on file in the office of the city engineer, for the sum of $31,500, and that according to said plans for said work, all that part of said Pacific avenue within the lines of the outside ends of the ties of the tracks of the Texas & Pacific Railway were to be excluded from the contract, and excluding that portion, the part to be paved under the contract was thirty-seven feet. That before said contract was made the city council of defendant had passed a resolution providing for said work and advertising for bids, to be based on the plans and specifications on file in the city engineer’s office. That said Laing & Smoot, before making their bid, examined said plans and specifications, and that said plans showed that the part of the street to be improved according to said plans should be only *615 thirty-seven feet wide, and that upon the faith of said plans they bid upon the same, said bid being first itemized, and in the alternative for the aggregate sum of $31,500, which aggregate sum was intended by them to be about the same as the detailed bid, on the basis that said improvement was to be only thirty-seven feet wide. That the city of Dallas accepted said aggregate bid, and entered into said contract on June 28, 1890. That said contract provided that said Laing So Smoot should grade, excavate, and completely pave said street from curb to curb, and also provided that the city engineer or his assistant should stake out said work, and the contractor should preserve all stakes. That the city engineer staked the same out forty-one feet wide. That said contractors called the attention of the city’s engineer and street committee to the fact, and were directed to do the work as staked out; that the work was fully completed, and on February 25, 1891, was accepted by defendant’s city council, and said city then paid to Laing So Smoot on said work said sum of $31,500; that by reason of the improvement of said street by said Laing So Smoot forty-one feet wide, instead of thirty-seven feet wide as provided in said contract, said Laing So Smoot did extra paving of the value of $2707.98, and extra grading of the value of $300.16, according to the price named in their detailed bid to the city upon said work, and claimed that said Laing So Smoot was thereby entitled to the payment of said sum by defendant city; that said city failed and refused to pay the same, and that the claim of Laing So Smoot therefor was, before the filing of this suit, assigned by them for value to plaintiff, F. O. Brown.

Plaintiff also alleged in substance, that at and before this contract was made between Laing & Smoot and appellant, appellant and the Texas So Pacific Railway Company had an understanding or agreement in and by which the latter was to pay to the city one-half of the cost of the improvement of said Pacific avenue. And that upon the completion of said work and the acceptance thereof by the city, it caused an estimate of the cost thereof by the city to be made and presented to said railway company; that said estimate was upon the basis that the street improved was forty-one feet wide, and prices charged therefor were the same as in the detail bid of Laing & Smoot. And that immediately thereafter said railway company paid to appellant the amount of said estimate, to wit, $18,300. And that the appellant received said money and retained the same, and refuses to pay appellee the cost of said extra four feet, one-half of which was so paid to it by said railway company.

That Laing So Smoot immediately after said work was completed and accepted, presented their claim for said extra four feet width of street to the city council, but that it declined and refused to take any other action thereon than refer the same to the city attorney, where it still rests.

Said petition also sought to recover of defendant city the value of certain property of plaintiff alleged to have been converted by it, and *616 also certain sums alleged to be due on sundry other contracts, but the finding of the jury on said matters is not sought to be disturbed by the parties to this suit by this appeal, the only matters involved in this appeal being the question as to the right of plaintiff to recover of defendant on said contract for extra pavement and grading of Pacific avenue, as hereinbefore set out, and the amount of said recovery, if any. The defendant by its second amended original answer presented a general demurrer and special exceptions to said petition, which were by the court overruled, to which action defendant’s exceptions were duly made and noted by the court; said answer also presented a general denial of the allegations, and special pleadings: (1) That no valid debt was created or existed against defendant by reason of the contract for said improvement or the making thereof, because no provision was at any time made by said city for the payment of said debt as provided by sections 5 and 7, article 11, of the Constitution of the State of Texas. (2) That defendant’s charter provides that the cost of such improvements shall be paid by the owners of the property abutting on the street so improved, and that said charter provision is a measure and limitation of defendant’s power to make such improvement. (3) That said contract was made subject to defendant’s ordinances, and that said ordinances provide that a contractor or contractors for such improvement shall have no claim upon the city for payment for such work.

The cause was tried October 3,1894, before a jury, and resulted in a verdict against the defendant on said count for extra cost of paving Pacific avenue in the sum of $3654.88, and for certain property converted, $450.91, aggregating $4105.79, including interest, and in favor of the defendant on the other counts in said petition, for which sum judgment was accordingly entered against defendant city. From this judgment the-city appealed and has assigned errors.

For the purpose of expediting the determination of said cause, a brief statement of the case and the facts proven in said cause, as provided by articles 1414 and 1415, Revised Statutes, was agreed upon by the parties and approved tby the court.

The facts proven upon the trial, as recited in the agreed statement, are as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orange County v. Hogg
269 S.W. 225 (Court of Appeals of Texas, 1925)
City of Aransas Pass v. Eureka Fire Hose Mfg. Co.
227 S.W. 330 (Court of Appeals of Texas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
31 S.W. 298, 10 Tex. Civ. App. 612, 1895 Tex. App. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-dallas-v-brown-texapp-1895.