City of Corpus Christi v. Heldenfels Bros., Inc.

802 S.W.2d 35, 1990 WL 198324
CourtCourt of Appeals of Texas
DecidedJanuary 10, 1991
Docket13-90-063-CV
StatusPublished
Cited by30 cases

This text of 802 S.W.2d 35 (City of Corpus Christi v. Heldenfels Bros., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Corpus Christi v. Heldenfels Bros., Inc., 802 S.W.2d 35, 1990 WL 198324 (Tex. Ct. App. 1991).

Opinion

OPINION

DORSEY, Justice.

The City of Corpus Christi (City) appeals from a judgment rendered against it and in favor of Heldenfels Brothers, Inc. (Helden-fels), on a claim for the value of materials and services furnished by Heldenfels under a subcontract for use in a City recreation center building. After a bench trial, based on theories of quantum meruit, unjust enrichment and negligent failure of the City to require its general contractor to provide a proper payment bond, the trial court rendered judgment for Heldenfels for the reasonable value of its materials and services in the amount of $23,250, plus interest and attorney’s fees. The City appeals by nineteen points of error, while Heldenfels brings one cross-point. We reverse the judgment of the trial court and render judgment that Heldenfels take nothing.

On May 18, 1983, the City hired La-Man Constructors, Inc., (La-Man) as general contractor to build improvements on City park land for the Meadow Park Recreation Center. The general contract provided for a lump-sum payment to La-Man of $267,-748.00, and La-Man agreed to provide the standard performance and payment bonds by corporate sureties duly authorized to do business in Texas, as required by the City on all such contracts in accordance with the MacGregor Act. Tex.Rev.Civ.Stat.Ann. art. 5160 (Vernon Supp.1990). La-Man provided documents which facially appeared to be the required bonds. Although the City accepted these purported bonds after only a cursory review procedure, it later discovered after La-Man abandoned the project, that the bonding company did not exist and that the bonds were fraudulent.

La-Man hired Heldenfels as subcontractor for $26,000.00 to provide concrete T-beams to support the roof covering the recreation center. Heldenfels constructed the T-beams, delivered them to the project, and completed all of its responsibilities under the subcontract before the end of October 1983. During the course of the project, the City made monthly payments to La-Man for the work completed, while retaining 10% until final completion of the project. La-Man’s own estimates as provided to the City listed $32,500.00 as the amount of its general contract price allocated for the T-beams. On October 5, 1983, the City authorized a payment to La-Man for the T-beams of $29,250.00 (not including $3,250.00 for retainage).

*38 However, on October 11, 1983, a City inspector first noticed what appeared to be cracks in the T-beams. The City called a meeting with La-Man to discuss the problem on October 28, 1983, at which representatives from Heldenfels also appeared. In addition, in accordance with the general contract, the City retained $20,000.00 from La-Man’s next payment in November 1983, in order to protect itself against the possibility of defects. After several engineers examined the structure and submitted reports exonerating Heldenfels, the City abandoned its inquiry into possible defects in the T-beams in April 1984.

Meanwhile, on December 1, 1983, La-Man unexpectedly abandoned the project and is now in bankruptcy proceedings, leaving Heldenfels and other subcontractors unpaid. In February 1984, the City hired a new general contractor, Black Brothers (B & B), to complete the project for $83,-000.00. During the interim period between general contractors, the City did little to advance the project aside from maintaining the structure and hiring one of the subcontractors under separate agreement to complete minor repair work on the roof for $300.00. B & B substantially completed the project on June 22, 1984. The City claimed a number of incidental expenses associated with La-Man’s walkout and liquidated damages for delay in completion, leaving only $2,184.00 in excess funds which the City acknowledges may be due to La-Man.

The present suit is one of several to reach this court brought by subcontractors on the Meadow Park Recreation Center project seeking payment from the City. See City of Corpus Christi v. Acme Mechanical Contractors, Inc., 736 S.W.2d 894 (Tex.App. — Corpus Christi 1987, writ denied); City of Corpus Christi v. S.S. Smith & Sons Masonry, Inc., 736 S.W.2d 247 (Tex.App. — Corpus Christi 1987, writ denied). Generally in construction contracts, in the absence of an express agreement otherwise, a subcontractor is not in privity with the owner and must look to the general contractor alone for payment, while the owner is liable for payment only to the general contractor. City of Corpus Christi v. Acme Mechanical Contractors, Inc., 736 S.W.2d 894, 898 (Tex.App. — Corpus Christi 1987, writ denied). In addition, as a matter of public policy, liens are not generally permitted on public improvements where payment and performance bonds are required. See Quincy Lee Co. v. Lodal & Bain Engineers, 602 S.W.2d 262, 264 (Tex.1980); Cameron County Savings Association v. Cornett Construction Co., 712 S.W.2d 580, 583 (Tex.App. — Corpus Christi 1986, writ ref’d n.r.e.); Barfield v. Henderson, 471 S.W.2d 633, 636-37 (Tex. Civ.App. — Corpus Christi 1971, writ ref’d n.r.e.); Tex.Rev.Civ.Stat.Ann. art. 5160 (Vernon Supp.1990).

Because the City had no direct contractual obligation with Heldenfels to pay for the T-beams, nor was the City’s property encumbered by a mechanic’s lien, Heldenfels, in order to recover, had to rely on some other theory of liability. Heldenfels chose the theories of implied contract and negligence against the City. The trial court returned numerous findings and conclusions against the City on grounds of quantum meruit, unjust enrichment and negligent failure to require La-Man to provide a proper payment bond. By its nineteen points of error the City challenges each of the three grounds upon which the trial court granted judgment for Heldenfels. Heldenfels complains by its cross-point that the trial court erred in failing to award it the full $26,000 amount of its subcontract with La-Man.

By points of error one through five the City challenges recovery based on the theory of quantum meruit. Specifically, by points one and two the City challenges the legal and factual sufficiency of the evidence to show that the circumstances reasonably notified the City that Heldenfels was expecting to be paid by it. The trial court’s findings of fact are reviewable for legal and factual sufficiency of the evidence by the same standards applied in reviewing sufficiency of the evidence to support a jury answer. Okon v. Levy, 612 S.W.2d 938, 941 (Tex. Civ.App. — Dallas 1981, writ ref’d n.r.e.).

*39 Quantum meruit is an action independent of any contract, based on an implied agreement to pay for benefits rendered and knowingly accepted. Vortt Exploration Co. v. Chevron U.S.A., Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peiqing Cong v. Conocophillips Co.
250 F. Supp. 3d 229 (S.D. Texas, 2016)
Ge Betz Inc. v. Moffitt-Johnson
301 F. Supp. 3d 668 (S.D. Texas, 2014)
Hern Family Ltd. Partnership v. Compass Bank
863 F. Supp. 2d 613 (S.D. Texas, 2012)
Casstevens v. Smith
269 S.W.3d 222 (Court of Appeals of Texas, 2008)
Doss v. Homecomings Financial Network, Inc.
210 S.W.3d 706 (Court of Appeals of Texas, 2007)
Friberg-Cooper Water Supply Corp. v. Elledge
197 S.W.3d 826 (Court of Appeals of Texas, 2006)
Walker v. Cotter Properties, Inc.
181 S.W.3d 895 (Court of Appeals of Texas, 2006)
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
Mowbray v. Avery
76 S.W.3d 663 (Court of Appeals of Texas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
802 S.W.2d 35, 1990 WL 198324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-corpus-christi-v-heldenfels-bros-inc-texapp-1991.