City of Cooper City v. PCH Corp.

496 So. 2d 843, 11 Fla. L. Weekly 2042, 1986 Fla. App. LEXIS 9783
CourtDistrict Court of Appeal of Florida
DecidedSeptember 24, 1986
DocketNo. 85-887
StatusPublished
Cited by1 cases

This text of 496 So. 2d 843 (City of Cooper City v. PCH Corp.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Cooper City v. PCH Corp., 496 So. 2d 843, 11 Fla. L. Weekly 2042, 1986 Fla. App. LEXIS 9783 (Fla. Ct. App. 1986).

Opinion

COLBATH, WALTER N., Jr., Associate Judge.

Comprehension of the rather involved and complicated facts of this case requires introduction of two additional actors other than the appellant Cooper City (City) and appellee PCH Corp. (PCH); they are, Cooper City Utilities (Utilities) and City of Sunrise (Sunrise).

Overly simplified and broadly generalized, the facts are as follows. On June 22, 1977, PCH and Utilities entered into a Developer’s Agreement in which PCH gave Utilities the exclusive right to provide water and sewage treatment to 520 acres of land which PCH owned and was readying for development, for which PCH agreed to pay $450 per connection. The agreement was to terminate May 31, 1981, but could be extended by PCH. Successors of each party to the agreement were to be bound by its terms. In and around May 1981, PCH contacted Utilities to extend the agreement and learned that Utilities had sold out to Sunrise. PCH then contacted Sunrise and learned that it was involved in litigation with City over ownership of Utilities. PCH decided to intervene in that lawsuit to protect its interests but was persuaded by City not to do so because settlement was imminent; PCH deferred and the lawsuit settled with City becoming the new owner of Utilities. Thereafter PCH, Utilities, City and Sunrise met and negotiated, resulting in a Modified Developer’s Agreement which reaffirmed much of the original agreement and specifically reaffirmed the $450 connection fee. A condition of the settlement of the lawsuit and the Modified Developer’s Agreement was ratification of City becoming Utilities’ new owner by a referendum vote of City’s resi[845]*845dent voters. The referendum passed and shortly thereafter, despite the terms of the Modified Developer’s Agreement, City passed an ordinance increasing the connection fee to be charged PCH from $450 to $1,550. PCH then brought this suit against City seeking declaratory and other relief. After a lengthy trial the court below found for PCH and entered its order which (1) enjoined City from charging and collecting $1,550 per connection and (2) required City to refund all such fees paid plus legal interest thereon. It is from that order that this appeal was taken.

Unique to this case and not set forth in the facts above is that at all relevant times City was geographically divided, i.e., it contained an eastern section and a western section not connected to each other. The eastern and older portion contained an existing water and sewage treatment plant (east plant) which was close to capacity and in need of repair, which plant served the majority of City’s residents. The western and newer section housed the Utilities plant (west plant) which was relatively new and nowhere near capacity and which is the subject of this litigation.

City contends that a municipality can defray the fair share of increased capital costs for furnishing utility service to new customers by establishing a charge in excess of the contracted amount as an inherent and implicit reasonable exercise of its police powers. On the other hand, PCH contends that the increased connection fee of $1,550 imposed by City through its ordinance was (a) an unreasonable exercise of governmental authority, (b) arbitrary and discriminatory, (c) did not defray costs on a fair share pro rata basis, and (d) was an unconstitutional impairment of contract.

City sought to increase the connection charge to new users for the following reasons:

(a) To provide for expansion of the west plant to approximately double its size for future user needs due to anticipated build-out.
(b) To implement a water distribution interconnect between plants recommended by City’s consulting engineer.
(c)To implement two federal programs, i.e. the THM program for water treatment and the 201 program for sewage treatment.

Testimony of City’s consulting engineer, Mr. Humphrey, reveals that the west water plant had adequate present capacity to serve PCH land as well as other developers, but that the sewer plant probably did not. Mr. Humphrey further admitted that the THM and 201 programs would benefit both existing and new users and that existing users would not pay anything for the benefit, the sole cost being borne by new users out of the $1,550 connection fee. Mr. Humphrey stated that although the estimated combined costs of those two programs were over nine million dollars at the time of his study, the estimated costs at the time of trial were slightly over four million. There was also evidence that the cost of these programs could be defrayed by federal grant moneys and possibly through a future bond issue.

Another witness, Mr. Lukin, an engineer with Utilities at the time the original Developer’s Agreement was entered into, testified that he designed the Utilities plant with adequate capacity to serve both PCH land and that of another developer and that the $450 connection fee would fully reimburse the owner for its capital investment. In addition, he testified that no expansion was necessary to serve PCH.

In the instant case it appears that the parties agree on the legal principles involved but disagree on their application to the facts. In Contractors and Builders Association of Pinellas County v. City of Dunedin, 329 So.2d 314, 317, 318 (Fla.1976), appeal after remand, 358 So.2d 846 (Fla. 2d DCA 1978), cert. denied, 444 U.S. 867, 100 S.Ct. 140, 62 L.Ed.2d 91 (1979), the Florida Supreme Court found that in principle there is “nothing wrong with transferring to the new. user of a municipally owned water and sewer system a fair share of the costs new use of the system involves.” The court concluded that an ordi[846]*846nance to raise moneys to expand a water and sewer system to meet increased demand, thereby shifting to the new user such expense, was clearly proper. The Dunedin court went on to state, “The cost of new facilities should be borne by new users to the extent new use requires new facilities, but only to that extent.” Id. at 321. (Emphasis supplied.)

City in its brief states the primary issue on appeal as follows:

Whether a municipality can defray the fair share of the increased capital costs for furnishing utility service to new development by establishing a contribution charge in excess of the amount identified in a pre-existing developer agreement which is inherently and implicitly subject to the reasonable exercise of police powers?

City contends that this question must be answered in the affirmative and in support thereof relies on H. Miller & Sons v. Hawkins, 373 So.2d 913 (Fla.1979). The facts in H. Miller are somewhat similar to the case at bar wherein a utility agreed to construct a new plant to accommodate Miller’s projected new development and Miller agreed to pay a $250 connection fee per unit. Three years later the Public Service Commission authorized a $275 connection fee and thereafter the utility billed Miller at the increased rate and Miller protested. The Commission ruled in favor of the utility and the supreme court agreed, stating,

The Commission’s decision was based upon the well-settled principle that contracts with public utilities are made subject to the reserved authority of the state, under the police power of express statutory or constitutional authority, to modify the contract in the interest of the public welfare without unconstitutional impairment of contracts.

Id. at 914.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blasland, Bouck & Lee, Inc. v. City of North Miami
283 F.3d 1286 (Eleventh Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
496 So. 2d 843, 11 Fla. L. Weekly 2042, 1986 Fla. App. LEXIS 9783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-cooper-city-v-pch-corp-fladistctapp-1986.