City of Columbia Heights v. John H. Glover Houses, Inc.

217 N.W.2d 764, 300 Minn. 31, 1974 Minn. LEXIS 1304
CourtSupreme Court of Minnesota
DecidedApril 26, 1974
Docket44384
StatusPublished
Cited by2 cases

This text of 217 N.W.2d 764 (City of Columbia Heights v. John H. Glover Houses, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Columbia Heights v. John H. Glover Houses, Inc., 217 N.W.2d 764, 300 Minn. 31, 1974 Minn. LEXIS 1304 (Mich. 1974).

Opinion

Yetka, Justice.

Appeal from an order issued on May 4, 1973, by the Anoka County District Court approving a certificate of attorney of plaintiff, city of Columbia Heights. This order finalized proceedings, instituted by plaintiff in 1965, to condemn certain parcels of real estate owned by John H. Glover Houses, Inc., defendant and appellant herein. We reverse.

A summary of the facts is as follows:

On November 15,1965, pursuant to plaintiff’s petition for condemnation of certain parcels of real estate owned by defendant, the district court issued an order appointing commissioners to ascertain the amount of damages sustained by defendant on account of the condemnation. Defendant did not oppose the issuance of this order.

On January 10, 1966, the commissioners awarded the sum of $1,500 for “all damages whatever as may have been sustained by the defendants * * * not only as to property actually taken in the proceedings, but also as to other property or properties owned by the defendants, * * * as is affected by said taking but not actually taken in this proceedings.”

Defendant promptly appealed to the district court on grounds that the award of the commissioners did not adequately compensate for consequential damages resulting from flooding and other *33 causes and “for damages caused by the continuous tortious acts and conduct of the Petitioner.”

Trial was set for May 17, 1967. On that day a pretrial conference was held in the chambers of the Honorable Leonard Keyes, Judge of Anoka County District Court. No record was made of this conference. The only evidence on the record as to what transpired at this pretrial conference are certain affidavits. The affidavit of Judge Keyes, supported by the affidavit of Spencer Sokolowski, who was also present at this conference, were filed. In substance, the affidavit of Judge Keyes recites that the matter was settled by the parties, defendant agreeing to accept $1,500 for “all damages whatever as may have been sustained by the defendants * * * not only as to property actually taken in the proceedings, but also as to other property or properties owned by the defendants * * * as is affected by said taking but not actually taken in [the] proceedings.”

No stipulation of settlement was ever entered in the record, nor were written stipulations signed by the parties.

On May 22, 1967, plaintiff mailed a check in the amount of $1,500 to defendant, who retained but never negotiated said check. No further steps in this action were taken by either party until March 22, 1973, when plaintiff stopped payment on the above check. On March 23, 1973, plaintiff deposited $1,500 with the district court to be paid out at the direction of that court. Thereafter, on April 23, 1973, plaintiff filed a certificate of attorney along with a motion requesting approval of said certificate. Supporting affidavits were filed at this time.

Pursuant to this motion, the district court, on April 23, 1973, issued an order requiring defendant to appear at a hearing to be held May 4, 1973, and show cause why the court should not grant plaintiff’s motion for approval of the certificate of attorney. This order, along with all the materials filed by plaintiff on April 23, 1973, was served on defendant on April 26, 1973.

Defendant had been represented by one Theodore B. Miksza at the pretrial conference of May 17, 1967. On May 2, 1973, de *34 fendant contacted one Steven R. Rutziek to represent it at the hearing to be held on May 4, 1973.

Hearing on the motion for approval of the certificate of attorney was held on May 4, 1973. Counsel for defendant opposed approval on grounds that another lawsuit was involved in the matter. Counsel for defendant further requested a continuance on grounds that he had only two days’ notice and had been unable to locate defendant’s former counsel during that time and thus had inadequate time to properly prepare for the hearing. Defendant’s counsel further alleged the matter had not been “settled” because defendant had not signed any stipulations or releases. The court refused to grant a continuance and then approved plaintiff’s certificate of attorney, thereby finalizing the condemnation proceedings. Minn. St. 1969, § 117.20, subd. 6.

The parties conceded at oral argument that there is in fact another lawsuit pending, brought by the property owner against the city, which is in the nature of inverse condemnation and included claims for damages for nuisance and trespass. It is the defendant’s contention that it has sustained damages to other property it owns adjacent to the property that is subject to this condemnation proceeding by reason of other construction actions by plaintiff, and that the condemnation action here, if finalized, would bar further prosecution of that action because of the doctrine of res ad judicata. Defendant alleges the lower court refused to allow an explanation of the implications of the court’s action as it would affect the inverse condemnation action. The parties further concede that the city of Columbia Heights has already moved to dismiss the other cause of action based upon the trial court’s decision in this action, thereby bearing out defendant’s fears.

The question raised on this appeal was whether the matter had been settled by the parties so as to allow the district court to properly approve plaintiff’s certificate of attorney and thus finalize the matter. If no settlement was in fact reached, is the *35 defendant guilty of laches by its conduct following the pretrial conference?

We hold that defendant is not guilty of laches in this case. We recognize that laches may be invoked against a party who fails to exercise reasonable diligence in bringing litigation to a close. Wheeler v. Whitney, 156 Minn. 362, 194 N. W. 777 (1923). However, defendant has not passively failed to litigate its claims arising from the condemnation proceedings at issue in this appeal because it is currently prosecuting another lawsuit involving the same land and claims which were the subject of the condemnation proceedings.

We further hold that the certificate of attorney was improperly approved because no settlement had been reached in the condemnation proceedings. This is not a case where a party has silently retained a check tendered in full payment of a disputed claim. Rather, this is a case where plaintiff was well aware that defendant was litigating a separate lawsuit which was so closely related to the condemnation proceedings that plaintiff, upon approval of the certificate of attorney moved for summary judgment in this other lawsuit. It is therefore apparent that defendant did not negotiate the settlement check or sign any stipulations or releases for fear that doing so would prevent it from litigating its other cause of action.

Further, it is elementary that the necessary prerequisite to settlement is agreement as to what in fact was settled. In this case there is ambiguity as to what the commissioners’ award actually included.

The commissioners’ award seemed to include damage for the land and consequential damages for adjoining land.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dolly v. Nichols
386 N.W.2d 261 (Court of Appeals of Minnesota, 1986)
Peppin v. W.H. Brady Co.
372 N.W.2d 369 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
217 N.W.2d 764, 300 Minn. 31, 1974 Minn. LEXIS 1304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-columbia-heights-v-john-h-glover-houses-inc-minn-1974.