City of Colleyville, Texas v. Mart, Inc.

Court of Appeals of Texas·Decided October 23, 2025·No. 02-25-00276-CV·Published

Opinion

In the Court of Appeals Second Appellate District of Texas at Fort Worth ___________________________ No. 02-25-00276-CV ___________________________

CITY OF COLLEYVILLE, TEXAS, Appellant

V.

MART, INC., Appellee

On Appeal from the 236th District Court Tarrant County, Texas Trial Court No. 236-353845-24

Before Sudderth, C.J.; Wallach and Walker, JJ. Memorandum Opinion by Justice Walker MEMORANDUM OPINION

I. INTRODUCTION

This is an accelerated, permissive appeal from the trial court’s order granting in

part Appellee Mart, Inc.’s motion for partial summary judgment. See Tex. Civ. Prac.

& Rem. Code Ann. § 51.014(d), (f); Tex. R. App. P. 28.1. The trial court’s order

declared that the liquidated-damages provision in a contract between Mart and

Appellant City of Colleyville is an unenforceable penalty.

We granted the City’s petition for permissive appeal to determine whether the

trial court erred by declaring that the liquidated-damages provision is an

unenforceable penalty. See Tex. R. App. P. 28.3. Because the City did not satisfy its

burden to show that the amount of liquidated damages called for is a reasonable

forecast of just compensation, we will affirm.

II. FACTUAL AND PROCEDURAL BACKGROUND

On February 7, 2022, the City and Mart entered into a construction services

agreement (Contract) for renovations related to the City’s senior center (the Project).1

The Contract contained the following relevant provisions:

• [The City] agrees to pay [Mart] for all services authorized in writing and properly performed by [Mart] in a total amount not to exceed [three million four hundred and thirty-one thousand and no/100 dollars] ($3,421,000.00).”

1 The Contract incorporated other “Contract Documents,” including the City’s plans, invitation for bid, and written notice to proceed.

2 • “If discrepancies are found that may impact construction of the Project, it shall be [Mart’s] obligation to seek clarification as to which requirements or provisions control before undertaking any work on that component of the Project.”

• “The time for performance under this Agreement is Two Hundred and Seventy (270) calendar days. Accordingly, [Mart] shall complete all work related to the Project on or before the 270th calendar day following the date of [the City’s] written notice to proceed to [Mart].”

• “In the event [Mart’s] performance of this Agreement is delayed or interfered with by acts of the [City] or others, [Mart] may request an extension of time for the performance of same as hereinafter provided, but shall not be entitled to any increase in fee or price, or to damages or additional compensation as a consequence of such delays.”

• “No allowance of any extension of time, for any cause whatever (including an event of force majeure), shall be claimed by or granted to [Mart], unless (i) [Mart] shall have made written request to [the City] for such extension within forty-eight (48) hours after the cause for such extension occurred, and (ii) [the City] and [Mart] have agreed in writing that such additional time shall be granted.”

• “[Mart] understands and agrees that time is of the essence of this contract, and that for each day of delay beyond the number of calendar days agreed upon for the completion of the work herein specified and contracted for (after due allowance for such extension of time as may otherwise be provided for extension of time herein), [the City] may withhold permanently from the Contract Price an amount equal to $5,000 per day, which the parties agree represents a reasonable estimation of the actual costs that would be incurred by the [City] in the event of such delay.”2

The City issued its written notice to proceed on March 9, 2022, obligating Mart

to complete the Project by December 4, 2022. However, after beginning

This portion of the Contract—the liquidated-damages provision—is Section 2

7(D).

3 construction, Mart discovered that the City’s plans and specifications were

incomplete, inaccurate, or defective. Mart had to send numerous requests for

information to the City’s architect, seeking corrections or modifications to the plans.3

Mart contended that it had to halt construction on the Project because of the plan’s

defects and that it had to wait on the City’s architect to make corrections to the plans

or provide alternative instructions.4 By December 4, 2022, the Project remained

uncompleted. In the course of the project, Mart submitted five change orders

requesting various extensions of time. The City approved each of Mart’s requests,

and the Project was extended for a total of thirty-two days.

On February 17, 2023, the City notified Mart by letter of its intent to withhold

liquidated damages pursuant to Section 7(D) of the Contract.5 The relevant portions

of the letter read:

Section 7(D) of the Agreement states the City “may withhold permanently from the Contract Price an amount equal to $5,000 per day, which the parties agree represents a reasonable estimation of the actual costs that would be incurred by the City in the event of such delay.”[ ] Mart requested, and the City agreed to two change orders granting you a

3 Mart sent more than 130 requests for information to the City’s architect. The City’s architect submitted late responses to many of Mart’s information requests, several of which were more than a month past due. 4 The City “does not dispute that the corrections and modifications to the plans were necessary and that it was not possible for Mart to continue work on the Project until corrections were made.”

At the time of the City’s letter, Mart was sixty days beyond the Contract’s 5

prescribed time for performance.

4 fourteen-day time extension.[ ] Yet even including these approved delays, Mart is [sixty] days past due. Pursuant to [S]ection 7(D), the City is entitled to withhold $300,000 in liquidated damages as of today. The Project was completed on December 29, 2023.

The City has had multiple conversations with you about the ongoing delays, including an in-person meeting during which you estimated a completion date of April 15, 2023. The purpose of this letter is to formally notify you that the City reserves the right to withhold the above amount and any additional amounts accrued after today and through the date of Project completion from the final contract price.

As stated in the Agreement, time remains of the essence. Please proceed with haste to complete the Project as agreed.

Following the City’s letter, Mart continued submitting requests for information

from the City’s architect but made no additional requests for extensions of time.

Because of the various delays, the Project was not completed until December 29,

2023.6 Relying on the Contract’s liquidated-damages provision, the City withheld

$1,106,503.86 from Mart. Mart sued the City for (1) breach of contract, (2) suit on

sworn account, (3) quantum meruit, (4) declaratory relief—that the liquidated-

damages provision is an unenforceable penalty, and (5) attorney’s fees. The City

brought counterclaims against Mart for (1) breach of contract, (2) breach of

warranties, (3) declaratory relief—that the liquidated-damages provision is

enforceable, and (4) attorney’s fees.

6 The Project was completed 358 days beyond the Contract’s prescribed time for performance.

5 Mart moved for partial summary judgment on its claims of (1) declaratory

judgment, (2) breach of contract, and (3) suit on sworn account. With respect to its

Free access — add to your briefcase to read the full text and ask questions with AI

City of Colleyville, Texas v. Mart, Inc., (Tex. Ct. App. 2025).

City of Colleyville, Texas v. Mart, Inc. (City of Colleyville, Texas v. Mart, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Flores v. Millennium Interests, Ltd.
185 S.W.3d 427 (Texas Supreme Court, 2005)
20801, INC. v. Parker
249 S.W.3d 392 (Texas Supreme Court, 2008)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Travelers Insurance Co. v. Joachim
315 S.W.3d 860 (Texas Supreme Court, 2010)
Stewart v. Basey
245 S.W.2d 484 (Texas Supreme Court, 1952)
Phillips v. Phillips
820 S.W.2d 785 (Texas Supreme Court, 1992)
Baker v. International Record Syndicate, Inc.
812 S.W.2d 53 (Court of Appeals of Texas, 1991)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
MMP, Ltd. v. Jones
710 S.W.2d 59 (Texas Supreme Court, 1986)
FPL Energy, LLC v. TXU Portfolio Management Co.
426 S.W.3d 59 (Texas Supreme Court, 2014)