City of Chicago v. Roemheld

81 N.E. 45, 227 Ill. 160
Illinois Supreme Court·Decided April 18, 1907·Published·Cited by 3 cases

Opinion

Mr. Justice Farmer

delivered the opinion of the court:

This suit was brought in the superior court of Cook county by the appellees, who were contractors and had entered into a contract with appellant for the construction of two bridges, to recover of the city an amount claimed to be due them on account of extra work and material required by alterations made in the plans by appellant after letting the contract to appellees.

The original contract price for the two bridges ivas $425,000, and among other things it was provided in the contract that no claim should be made by the contractors for extra work or material unless the changes in or additions to the work requiring additional cost in construction should first have been ordered in writing by the commissioner of public works. Appellant also relied upon an ordinance which it introduced in evidence, containing, among other sections, the following:

“1609. No payment shall be made on any work or job done by contract for any extra work not specified in the contract, unless such extra work shall have been done by the written order of the commissioner of public works, to be annexed to such contract, directing the same, and stating that such work is not included in the contract: Provided, that any order given under this section shall state what the extras are, and that such extras are necessary for the proper completion of or for the security of the work previously done, and the reasons therefor.”

There was no conflict in the testimony. The only proof offered on the trial, except the ordinance mentioned and receipts for money paid appellees, was offered by appellees. This uncontradicted testimony shows that changes were made in the original plans and specifications in the city engineer’s department and under his direction, which involved an additional cost in material and labor in the construction of said bridges of $20,042.82. Working drawings were made in accordance with the changes, and these were approved, in writing, by the city engineer and his assistants. These drawings, seventy-six in number, each about two and one-half by three feet in size, were presented by the city engineer to the commissioner of public works for his approval. Said commissioner made no objections to the drawings nor to approving them and ordering the work done in accordance therewith, but did make some objection to the labor involved in signing all of them. He inquired of appellant’s engineer in charge of the bridge department, who presented them to him for his signature, whether it was necessary for him to sign all of them. The engineer, Mr. Philfelt, replied that he did not know, and thereupon the commissioner of public works signed his name to drawing No. 1 on a blank line prepared for that purpose immediately following the word “Approved.” Underneath the line upon which his signature was written are the words, “Commissioner of Public Works.” After the drawings were turned over to appellees one of them inquired of Mr. Philfelt why the commissioner of public works had not signed all of them, and was told by Mr. Philfelt the commissioner did not think it necessary. When the bridges were completed they were approved by the city engineers, accepted by the city and the original contract price paid. This suit, as before stated, was brought to recover the additional cost to appellees made necessary by the changes in the plans. A jury was waived and the cause tried by the court. The court refused to hold certain propositions of law presented by appellees. One of said propositions was to the effect that the appellees were entitled to recover the amount sued for. Other refused propositions were to the effect that if certain things recited in them had been proven, then appellees were entitled to recover. On behalf of appellant the court held in propositions of law that unless the evidence showed the work and material sued for had been ordered by the commissioner of public works, in writing, before the work was done or the material furnished, there could be no recovery, and that the contract between the parties could not be changed except in writing, signed by the commissioner of public works. The court gave judgment for appellant for costs. On appeal to the Appellate Court this judgment was reversed and a judgment entered in that court for appellees for $20,042.82, and this appeal is prosecuted from the judgment of the Appellate Court.

One of the errors assigned here is, that the Appellate Court erred in rendering judgment in favor of appellees.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Chicago v. Roemheld, 81 N.E. 45, 227 Ill. 160 (Ill. 1907).

81 N.E. 45 (City of Chicago v. Roemheld) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stahelin v. Bd. Ed. SD No. 4 DuPage County
230 N.E.2d 465 (Appellate Court of Illinois, 1967)
Delta Bag Co. v. Kearns
97 N.E. 679 (Illinois Supreme Court, 1912)
Roemheld v. City of Chicago
83 N.E. 291 (Illinois Supreme Court, 1907)