City of Chicago v. Mohr

74 N.E. 1056, 216 Ill. 320
CourtIllinois Supreme Court
DecidedJune 23, 1905
StatusPublished
Cited by11 cases

This text of 74 N.E. 1056 (City of Chicago v. Mohr) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Chicago v. Mohr, 74 N.E. 1056, 216 Ill. 320 (Ill. 1905).

Opinion

Mr. Justice Boggs

delivered the opinion of the court:

The appellee filed a bill in chancery in the circuit court of Cook county for a decree restraining the city of Chicago from entering into or executing any contracts for the construction of a new boiler plant at the Fourteenth street pumping station of the Chicago water-works, and from taking any steps to carry out such contract or paying out any moneys on account thereof.

The amended bill, upon which the case was tried, alleges that the complainant is (a) the owner of taxable property in the city, and (b) a contributor to the city water rates and a water-rate payer. It alleges that the city is incorporated under the “Act to provide for the incorporation of cities and villages,” approved April io, 1872, and that the laws of the State now in force in regard to the letting of contracts by a city are embraced in that act, and require that any public works, when the cost thereof shall exceed $500, shall be let to the lowest responsible bidder in the manner prescribed by the ordinance; that the ordinances of the city required that “when any public improvement shall be ordered by the city council, * * * a plan or profile of the work to be done, accompanied with specifications for the doing of the same, shall be first placed on file in the office of said department [of public works] before any such advertisement shall be made, which said plan, profile and specifications shall at all times be open for inspection. * * * All contracts exceeding in amount the sum of $500 for work, materials or supplies, relating to any of the matters under the cognizance of the department of public works, shall be let by the commissioner of public works to the lowest reliable and responsible bidder or bidders whose bid does not exceed the estimate;” that the bidding should be by sealed bids and should be opened at an hour designated in the notice.

The bill also alleges that the city had determined to construct a new steam boiler plant at the Fourteenth street station and the commissioner of public works had undertaken to prepare plans and specifications for the work, copies of which are attached to the bill, but it is alleged that there was no plan or profile prepared as is required by section 1612 of the ordinance; that the plans and specifications were informal, insufficient and incomplete; that the specifications contained a clause providing for a comparison of bids, which required all bidders to submit detailed plans, drawings and specifications of the boilers, stokers, coal-conveyor plant, ashbiris, coal-bins, buckets, etc.; that the commissioner advertised for bids; that.when the bids were opened they were found to be so widely variant that in order to pass upon them it was necessary to make a comparison not only of the price, but in regard to a number of points; that the commissioner made a comparison on some points of supposed relative merit; that the bids were as follows: John Mohr & Sons, a corporation, $98,000; John O’Neil, $98,000; S. Freeman & Sons Manufacturing Company, of Racine, Wis., $95,000; Springfield Boiler Works, $126,000. It alleges that neither the advertisement nor the plans and specifications on file in commissioner’s office furnished any full, definite or precise information of the work to be done, and that those bidding had no intelligent basis for their bids, and that the advertisement, plans and specifications did not meet the requirements of the law, and that there was no uniformity in relation to the work bid upon by the different bidders, and that it w.as impossible for any person to arrive at any conclusion as to which bidder was the lowest responsible bidder without, or even by, comparing the work proposed to be undertaken as well as by comparing the prices, and that this plan of receiving bids destroys competitive bidding and fails to comply with the requirements of the statutes, ordinances and laws relating to the letting of contracts; that the plant was to consist of six boilers, arranged in three sets or batteries of two boilers to each battery. It alleges that the specifications require a feed water-purifier for each boiler, and that the bid submitted by the S. Freeman & 'Sons Manufacturing Company provided for but three instead of six purifiers, and that after the bids were opened Freeman undertook to supplement his bid and agreed to furnish six purifiers in all, and that by Freeman’s action in leaving out three of the purifiers he was enabled to make his bid lower than it would otherwise have been, and thereby competition was destroyed, and Freeman did not bid upon the same work that Mohr bid upon.

Under the head of “Special and general requirements” in the specifications, appears the following, to-wit:

“Time of installation—As the time required for the installation of the boilers is an essential element of this contract, bidders will stipulate the length of time required by them to install the first battery after being duly notified in writing by the commissioner of public works that the existing battery of three boilers is ready for removal. They will also stipulate the length of time required for the removal of the old boilers and their appurtenances, and the installation, ready for operation, of the second battery, after proper notification has been given by the commissioner of public works to proceed with the work. Similarly, a time limit will be specified for the removal of the old boilers and the installation of the third battery. It is stipulated and agreed that the entire coal-conveying plant shall be complete and-ready for operation within one week after the limit of time guaranteed for the installation of the third battery of boilers. This element of time, as guaranteed, will be taken into consideration in canvassing the bids. The work in the shops shall begin immediately after the signing of the contract. It is also stipulated and agreed that the work of installation of the plant called for by these specifications shall be begun immediately after due notice has been given in writing by the commissioner of public works that the contractor can proceed with his operations in the boiler room, and such work shall be continued in such order and manner as to secure the completion of the work to be done under this contract, and of each of the batteries, in the order and within the time specified by the contractor and made a part of this contract. Should the contractor neglect or refuse or fail to complete the successive parts of the work in the order or within the time guaranteed, then and in that event it is hereby understood and agreed that the city will deduct and retain out of such moneys as will b'e due or which may become due and payable to the contractor, the sum of $50 per day for each and every day that each battery is delayed in its completion beyond the specified time, such moneys to be taken and considered as liquidated damages which the city will sustain by reason of such default. If, in the event that the successive batteries shall be completely ready for firing in less time than that guaranteed, then the city agrees to pay the contractor as a reward $50 for each and every day that each battery is completed before the limit of time guaranteed.”

The bill alleges that Freeman’s bid provided that he would have the first battery of boilers in place within one hundred days after written notice to remove the present battery No. 1, and the second battery in place within one hundred and forty days after notice that present battery No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Intergovernmental Solid Waste Disposal Ass'n
605 N.E.2d 654 (Appellate Court of Illinois, 1992)
George W. Kennedy Construction Co. v. City of Chicago
481 N.E.2d 913 (Appellate Court of Illinois, 1985)
Young v. Village of Glen Ellyn
458 N.E.2d 1137 (Appellate Court of Illinois, 1983)
M. A. Lombard & Son Co. v. Public Building Commission
428 N.E.2d 889 (Appellate Court of Illinois, 1981)
Leo Michuda & Son Co. v. Metropolitan Sanitary District
422 N.E.2d 1078 (Appellate Court of Illinois, 1981)
Rossetti Contracting Co. v. Brennan
508 F.2d 1039 (Seventh Circuit, 1974)
Coller v. City of St. Paul
26 N.W.2d 835 (Supreme Court of Minnesota, 1947)
Auto Car Co. v. Zanesville
29 Ohio Law. Abs. 140 (Muskingum County Court of Common Pleas, 1939)
Murphy v. City of Greensboro
129 S.E. 614 (Supreme Court of North Carolina, 1925)
Root v. Douglas County
180 N.W. 46 (Nebraska Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
74 N.E. 1056, 216 Ill. 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-chicago-v-mohr-ill-1905.