City of Chicago v. Duffy

53 N.E. 982, 179 Ill. 447
Illinois Supreme Court·Decided April 18, 1899·Published·Cited by 6 cases

Opinions

Mr. Justice Phillips

delivered the opinion of the court:

Defendant in error, who was plaintiff in the trial court, brought suit against the plaintiff in error, who was the defendant, and each party will be hereafter spoken of in this opinion as of the relation occupied therein. The plaintiff alleged that he entered into a contract in writing with the defendant, by which he agreed to build and construct a water tunnel and shafts in the city of Chicago from a shaft to be located at the west end of the proposed ten-foot water tunnel situated in the neighborhood of North Green street, near Grand avenue, thence to a terminus at some point west of Rockwell street to be determined by the commissioner of public works. The work was to be done according to the terms, conditions and directions set forth in the contract and the plans and specifications attached thereto and made a part thereof. The following work to be done by the plaintiff under this contract was designated in the plans and specifications: “Second section, eight feet internal diameter. From shaft at west end of ten-foot tunnel to the terminus west of Rockwell street. The clear width of the tunnel shall be eight feet and the clear heig'ht eight feet two inches; the top and bottom arches shall be semi-circles; the tunnel shall be lined with brick masonry in three rings, or abont thirteen inches in thickness.”

The proposal" of the plaintiff to do this work according to the specifications was submitted, and he proposed to do all the work and furnish all the material in section 2 at prices designated in the proposal, which, as submitted, was, that he would do the work in section 2 for “shafts ten feet internal diameter, per lineal foot, $30; tunnel in earth, eight feet internal diameter, per lineal foot, $13.55; tunnel in rock, eight feet internal diameter, per lineal foot, $17.75; rock excavation over and above the cost of lineal foot of tunnel or shaft, per cubic yard, $10; cast-iron in covers, etc., per pound, six cents.”

On the 13th day of September, 1895, an agreement was signed by Joseph J. Duffy on the one part, and the' mayor, comptroller and commissioner of public works of the city of Chicago on the other part, by which the city agreed to pay for the work to be performed in accordance with the proposal. The specifications attached to the agreement provided: “When the tunnel is partly in earth and partly in rock the contractor will be paid an additional price per cubic yard for rock excavation over and above the unit price per lineal foot of tunnel in earth. When the tunnel is in rock the brick lining may, if deemed secure by the city engineer, be reduced one ring less of brick, and in all cases the masonry shall be brought to a true circular section. In every instance all spaces left between the outside of the regular brick work and the excavation shall be filled in with solid brick masonry, but no allowance will be made for such additional work and material.”

The only substantial provisions of the contract with reference to the time of making compensation for doing the work and the manner in which it should be done, except the promise to pay according to the proposal, are the following: “And no estimate will be issued to said contractor or contractors until all claims for labor on this contract shall have been satisfied. It is also agreed by said city that if the rate of progress shall be satisfactory to said commissioner of public works, estimates in its usual form will be issued to said party of the first part, during the making of said improvements, for eighty-five per cent of the value of the work done and in place at the time of issuing such estimate, the remaining fifteen per cent being reserved until the final completion and acceptance of said work. No payment will be made for any extra work not specified in this contract, unless such extra work shall have been done by the written order of the commissioner of public works, to be attached to such contract, directing the same, and stating that such work is not included in the contract, what the extras are, and that such extras are necessary for the proper completion of or for the security of the work previously done, and the reasons therefor.”

Plaintiff entered upon the performance of his contract and excavated 4707 lineal feet of tunnel in solid rock. As this work progressed it was inspected by defendant’s engineers and was found satisfactory, and estimates were made from time to time and vouchers given to plaintiff and paid, but the parties differed about the construction of the contract and defendant’s officers refused to include in the estimates and vouchers any sum or allowance for rock excavation above the price of §17.75 per lineal foot. Plaintiff claimed that he was entitled to §10 per cubic yard besides the lineal foot price.

This difference having arisen between the plaintiff and the city as to the construction of the contract and the amount plaintiff should receive for work done thereunder, the plaintiff brought his' action of assumpsit against the defendant for the eighty-five per cent provided by the contract to be paid upon the estimates as the work progressed. The declaration filed on this contract set out the same, with the specifications, in hœc verba, together with the proposal. Subsequently an additional count was filed, which contained an averment as follows: “And plaintiff avers that defendant, at and for a longtime prior to the making of said contract, had in existence and in operation a water-works system, from which it derived revenues and income, and had therefrom a water fund, as authorized and provided by the statutes of Illinois in that behalf, and that the work contemplated to be done by said contract was a proper and necessary extension of said water-works and system, and that the payments for such work contemplated by said contract to be made by defendant to plaintiff were by the contemplation and agreement of the parties thereto to be made from said water fund,-and not otherwise; that this plaintiff has oftentimes since said sum became payable, requested the defendant to pay the same to him, yet the defendant, not regarding its said promise and agreement so by it in and by said contract in manner and form aforesaid made to pay said sum to plaintiff, has at all times refused, and still refuses, to pay to plaintiff said sum, or any part thereof.” Thereafter’various amendments were made to the declaration.

Under the above quotation from the additional count, and during the trial, the following stipulation and waiver were filed: “During the trial plaintiff filed with the clerk and submitted to the court a waiver as to the fund from which payment was to be made, which was marked ‘Exhibit 107,’ and is in words and figures following: ‘And plaintiff avers that said parties, at the time of making said contract, ■ agreed, as part of said contract, that all moneys by said contract provided to be paid to plaintiff were payable out of the ‘water fund’ of and belonging to defendant, derived and to be derived from sales of water by defendant from the water system and waterworks, and extensions thereof, belonging to defendant, and that such agreement as to the fund from which payments as aforesaid were to be made to plaintiff was not expressed in said contract; and plaintiff avers that the tunnel to be constructed by plaintiff according to the terms of said contract was an extension of the water system of defendant; and plaintiff waives right to payment out of any and all moneys raised by taxation and out of all funds and moneys of defendant other than said water fund.’”

Free access — add to your briefcase to read the full text and ask questions with AI

City of Chicago v. Duffy, 53 N.E. 982, 179 Ill. 447 (Ill. 1899).

53 N.E. 982 (City of Chicago v. Duffy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re the Appeal of Lord
25 Haw. 76 (Hawaii Supreme Court, 1919)
Whitener v. Moss
1918 OK 513 (Supreme Court of Oklahoma, 1918)
Zukas v. Appleton Manufacturing Co.
200 Ill. App. 403 (Appellate Court of Illinois, 1916)
City of Chicago v. Duffy
75 N.E. 912 (Illinois Supreme Court, 1905)
City of Chicago v. Duffy
117 Ill. App. 261 (Appellate Court of Illinois, 1904)
City of Chicago v. McKechney
91 Ill. App. 442 (Appellate Court of Illinois, 1900)