City of Charleston v. Public Service Commission

99 S.E. 63, 83 W. Va. 718, 1919 W. Va. LEXIS 221
CourtWest Virginia Supreme Court
DecidedMarch 26, 1919
StatusPublished
Cited by6 cases

This text of 99 S.E. 63 (City of Charleston v. Public Service Commission) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Charleston v. Public Service Commission, 99 S.E. 63, 83 W. Va. 718, 1919 W. Va. LEXIS 221 (W. Va. 1919).

Opinions

Kitz, Judge:

In July, 1918, the West Virginia Water and Electric Company, a public service corporation supplying water to the inhabitants of the city of Charleston and the town of South Charleston, made application • to the Public Service Commission for authority to increase its rates. A protest was made by the city of Charleston on behalf of itself and the citizens of said city against the allowance of such increase, upon the.grounds that the applicant was not furnishing an adequate supply of water for the purpose of fire protection, as required by its franchise, nor was the said applicant furnishing an adequate supply of pure wholesome water for consumption by the inhabitants thereof, as required by the terms of said franchise, but on the other hand alleged that the water being furnished by the said applicant was not only entirely inadequate to meet the needs of said city and its inhabitants, but was so impure and unwholesome that one or more severe disease epidemics had resulted from its use.

After extended hearings, the Commission on the 20th of November, 1918, entered an order finding as matter of fact that the applicant had been grossly derelict in its duty to the public, and that it had not made reasonable effort to comply with its public duty, but further found that the applicant had begun and was rapidly completing certain improvements and extensions to its plant which would make it adequate for the present needs of the city and its inhabitants, and that until the completion of these improvements certain temporary arrangements had been effected which in a large measure relieved against the complaint of shortage of water supplied, as well as the complaint of the impurity thereof; and further found that from the evidence then before the Commission, and the reports of its officers [720]*720and agents, the applicant was not receiving a fair return upon its investment devoted to the public sepvice; that there were gross inequalities in the rates charged by the applicant, some consumers paying substantially less than the cost of the service to them, while others were paying approximately the cost thereof; that the Commission was not in possession of sufficient data at that time to make a general readjustment of the rates, but that in order to furnish temporary relief to the applicant it would be allowed to increase its rates twenty per cent, over the rates then in force, such increase to be effective until the first of July, 1919, or until .the further order of the Commission, and providing that in the meantime said water eompany should keep careful reports and make a complete return to the Public Service Commission when required, with the view to an adjustment of its rates upon a basis equitable and fair to all parties, and also providing that the engineer and other agents of the Commission carefully observe the operation of the plant in the meantime in order that all information valuable to the Commission in making such readjustment might be available at the expiration of the experimental time fixed in the order. The city of Charleston subsequently moved the Commission to suspend this order and to rehear the proceeding, but this motion was denied on the 30th day of January, 1919, on the ground that the order was simply temporary in its effect, and that the Commission would not be in position to make permanent adjustment'of the rates until such information was secured by it as could only be available from observing the plant in operation, under the conditions provided for in the former order. An application was then made to this court to suspend the order of the Commission allowing the increased rate.

The Commission urges that this court is without jurisdiction to suspend such order, for the reason that it is only a temporary and interlocutory one, and that the jurisdiction of this court to prohibit the execution of the Commission’s orders only goes to such orders as are final,, and relies upon the case of City of Bluefield v. Bluefield Water Works & Improvement Company, 81 W. Va. 201, in support of this [721]*721contention. The petitioner contends that that case does not apply here for the reason that the Public Service Commission never had jurisdiction to entertain the application for increased rates, because the applicant water company was not furnishing an adequate supply of wholesome water at the time it made said application, nor was it doing so at the time the order allowing the increased rate was entered; and further that the order is so far final as justifies a review thereof under the provisions of § 16 of eh. 15 0 of Barnes’ Code.

If, as contended, this Court is without jurisdiction to review such an order of the Commission as is involved here, that will end the ease. It'is true we held in the Bluefield case, above cited, that orders of the Public Service Commission valuing the property of and fixing the rates to be charged by a public service corporation for experimental purposes, and retaining the ease for future action after the result of such experiments is ascertained, are not final orders subject to be controlled by this Court. In attempting to apply the conclusion reached in that case we must consider the language used in connection with the facts involved in the controversy. There an increase in the rates had been granted by an experimental order, and neither the city nor any of the inhabitants were complaining of the increase allowed, but the water company was complaining that the increase allowed it was not sufficient, and it was determined that that order -would not be reviewed. The discussion indulged in in the opinion discloses that this conclusion was based largely on the ground that the order was a proper one, and it can reasonably be drawn from that opinion that the court would have exercised jurisdiction if it had reached the conclusion that the order involved was unreasonable. It is true § .16 of the Public Service Commission Act provides for invoking the jurisdiction of this Court to review an order of the Public Service Commission by any party feeling aggrieved by a final order thereof. In what sense did the Legislature use the word final in that statute? Of course, if we say that the word final there means the last order in the ease, or the order disposing of it finally, then

83 W. Va. [722]*722the order complained of here is not such an order. If, however, we take the view that what the Legislature meant was such an order as grants relief to one party or the other, and •changes the situation of the parties to their material advantage or disadvantage, the order complained of here is such •an order. While in its strict sense a final order is the last •or concluding order in a ease, in the popular sense, and in ¡the sense in which it is most used by the lawmakers, as well as by the legal’ profession, it is ordinarily considered to be such an order as is subject to review by appeal, writ of error, or other appellate process, and our statutes providing for appellate process in other cases' do not in all instances contemplate the last or concluding order in the case as the only •one subject to review by such process. We are of the opinion that the Legislature in the use of this term meant to •cover all such orders as change the position of the parties, •as take from one and give to the other something that he 'was not entitled to, and could not receive before. If we do not give the statute this construction, then the Public Service Commission. may, by these provisional or experimental orders, put its actions in most cases beyond the review of this Court for such a period of time as would make the relief of little value when it was finally obtained.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Columbia Gas of West Virginia, Inc. v. Public Service Commission
311 S.E.2d 137 (West Virginia Supreme Court, 1983)
Elliott v. Empire Natural Gas Co.
256 P. 114 (Supreme Court of Kansas, 1927)
City of Huntington v. Public Service Commission
110 S.E. 192 (West Virginia Supreme Court, 1921)
City of New York v. New York Telephone Co.
115 Misc. 262 (New York Supreme Court, 1921)
Citizens' Passenger Railway Co. v. Public Service Commission
75 Pa. Super. 238 (Superior Court of Pennsylvania, 1920)
Chicago Railways Co. v. City of Chicago
292 Ill. 190 (Illinois Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
99 S.E. 63, 83 W. Va. 718, 1919 W. Va. LEXIS 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-charleston-v-public-service-commission-wva-1919.