City of Camden v. Ward

52 A. 392, 67 N.J.L. 558, 38 Vroom 558, 1902 N.J. LEXIS 126
CourtSupreme Court of New Jersey
DecidedJune 16, 1902
StatusPublished
Cited by4 cases

This text of 52 A. 392 (City of Camden v. Ward) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Camden v. Ward, 52 A. 392, 67 N.J.L. 558, 38 Vroom 558, 1902 N.J. LEXIS 126 (N.J. 1902).

Opinion

The opinion of the court was delivered by

Dixon, J.

On December 30th, 1898, the defendant Ward entered into a written contract with the city of Camden to pave Federal street, in that city, with asphalt pavement on concrete foundation, at designated prices, and to complete the work by November 1st, 1899. One clause of the contract is as follows:

“If for any reason the contractor fails to comply with the directions of the commissioner of streets as to commencing the work, or after commencing he shall stop or shall prosecute the work without due diligence, or with an insufficient force of men, in the opinion of the commissioner of streets, then the commissioner of streets may procure the necessary materials and labor and proceed with the construction of the work called for by these plans and specifications, and the expense incurred by him in such procedure shall be deducted fro'm any money or funds then due, or that may thereafter become due, to the contractor from the city of Camden on account of the contract performed under these specifications. [560]*560If such.' money or funds be insufficient to pay such expense incurred, then the said contractor and his sureties shall be liable to pay such excess, upon demand, to the city of Camden."

,On January 10th, 1899, the defendants, Ward and the National Surety Company, gave their bond to the city in the yenal sum of $18,776, conditioned to be void if the said Ward should in all things perform the contract. On this bond the present suit was brought.

At the trial of the cause in the Camden Circuit the following facts appeared-: Ward commenced his work on the street about April 24th, 1899, and continued until May 24th, 1899, when the work ceased, and Ward told the street commissioner of the city that he was not able to proceed with it. On May 31st, 1899, the street commissioner notified both defendants, in writing, that, unless within ten days they proceeded with the work, he would proceed with it according to. the contract. On June 11th, 1899, the work not having been resumed, the committee on streets of the city directed the street commissioner to proceed according to the contract, and on June 16th, 1899, -the street commissioner notified the defendants; in writing, that he had invited proposals for completing the contract. Requests for such proposals were sent to seven paving companies stationed in different places, from Philadelphia to Detroit, and on June 26th, 1899, the commissioner notified the defendants that the only bid received was from the Vulcanite Paving Company, of Philadelphia, and gave them the details of that bid.' The notice further stated that he proposed to award the contract to that company on the bid, and would ask the council, at its meeting on June 29th, 1899, to ratify such award. At that meeting the council ratified the award, and accordingly the contract -was made between the city and the Vulcanite Paying Company for the completion of the work. On July 15th, 1899, the commissioner notified the defendants that, pursuant to his previous notice, he was now about to proceed with and complete the work, for which they-would be held responsible according to the contract, and if at any time they were ready, with a sufficient force of [561]*561men. and materials, to resume the work, they would be permitted to do so. To these notices no replies were sent, except', that, on June 23d, June 29th, August 3d and September 9th,. 1899, Ward gave written notice that he was not in default,, that he was mailing arrangements to proceed, and that he protested against the making of any contract affecting the street. Ward never did resume, or offer to resume, the work, and, so far as appears, he was not making, or attempting to make, any arrangements for its resumption. The work was finally completed by the Vulcanite Paving Company, under its contract with the city, and the claim by the city on the bond of the defendants was for the difference between the cost of completion and the price under the Ward contract, being $14,856.78.

At the Circuit a verdict was directed in favor of the plaintiff for this sum as damages.

On error to this court the defendants rely upon points now to be considered.

First. It is insisted that to show a breach of the contract by Ward there must have been some formal decision to that effect by the street commissioner, under the clause of the contract above recited.

Perhaps such a decision might have been necessary if the question was whether Ward had been prosecuting the work without due diligence, or with an insufficient force of men; for what was due or insufficient would be a matter of judgment. But the alleged breach consisted of stopping the work, and as to that there was no room for judgment; the matter was one of mere fact. As to such a breach we think the contract called, not for an opinion of the commissioner, but for proof of the fact. Such proof, without contradiction, was produced at the trial.'

Secondly. It is urged that the street commissioner did not, as the contract required of him, procure the materials and labor necessary to complete the work, but that the city itself, under a new contract, completed the work.

It is true that the work was completed under a contract [562]*562made with the city, but the testimony was entirely clear that such contract was only the means adopted by .the street commissioner for procuring the necessary labor and materials. The work was not one for which he could readily purchase materials and employ laborers in the open market; for it required a special product and skilled workmen already under the control of companies engaged in that kind of paving, so that the practicable method of procuring the labor and materials was by engaging one of those companies to furnish them. Eor such an engagement the credit of the city was almost essential. It was within the power of the street commissioner, under the contract, to employ the means actually adopted for the completion of the work. Nor is there any force in the suggestion that the various steps taken to that end were controlled by the agencies of the municipality. Each step was taken by the street commissioner himself, but -he properly applied for and received the approval of the city authorities, just as, by his various notices to the defendants, he gave them opportunity to approve or object. Such action on his part was entirely consistent with due exercise of his authority under the contract.

Next the defendants contend that the plaintiff was bound to show that the work was completed at a reasonable price, or at least that reasonable care had been taken to do so, and they complain that on the trial they were denied the opportunity of showing that, with reasonable care, the work could have been done at less expense.

If, on the default of the defendants, the city itself had, either under the terms of the agreement or without any express provision therefor, assumed control of the work, no doubt any expense incurred through a lack of reasonable care and judgment would not have been chargeable to the defendants. But such is not the ease. Here the parties have chosen that the responsibility of finishing the work, in case of the contractor’s default, should not be cast upon the city, but they have selected another person for that purpose, and have thus agreed to abide by such care and judgment as he might exercise. They have not bargained with each other as to the [563]*563degree of his skill or diligence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Borough of Totowa v. American Surety Co. of New York
188 A.2d 586 (Supreme Court of New Jersey, 1963)
City of Montpelier v. National Surety Co.
122 A. 484 (Supreme Court of Vermont, 1923)
Ellyson v. Lord
99 N.W. 582 (Supreme Court of Iowa, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
52 A. 392, 67 N.J.L. 558, 38 Vroom 558, 1902 N.J. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-camden-v-ward-nj-1902.