This text of 245 F.2d 188 (City of Burlington v. Century Indemnity Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Burlington v. Century Indemnity Co., 245 F.2d 188, 1957 U.S. App. LEXIS 3215 (2d Cir. 1957).

Opinion

HAND, Circuit Judge.

The defendant appeals from a judgment against it entered upon the verdict of a jury in an action upon a contract to execute a “performance bond.” The jurisdiction of the district court depended upon diverse citizenship, the defendant being a Connecticut corporation and the plaintiff a city in Vermont. The only question which we find it necessary to consider is whether the judge should have granted the defendant’s motion at the conclusion of the evidence to direct a verdict because the plaintiff had not proved any contract between the parties. The following is a statement of the evidence.

On September 21, 1951 the City entered into a contract with the Pierce Consulting Engineering Company (which we shall call the “Engineer”), to prepare and furnish engineering services and plans and specifications for an electrical generating station, which on April 8, 1952 was amended in matters not important to this controversy. On March 18, 1952, the “Engineer” contracted to furnish plans and specifications to the City for the construction of additional “distribution facilities.” The City had a Board of Light Commissioners who were in general charge of the work, and in March they and Pierce, the chief officer and owner of “Engineer,” negotiated regarding a performance bond that “Engineer” was to furnish for its execution of the contracts. In pursuance of this purpose Pierce approached a Boston insurance firm, known as Brewer and Lord, who were general agents of the defendant in Boston, and who turned over the proposal to Stockbridge, a representative of the defendant. Stock-bridge took the matter up with the defendant’s Hartford agent, Thompson, who was in charge of its bonding department; and in June Stockbridge asked Pierce for certain information that Thompson thought material to the decision. In replying Pierce sent to Stock-bridge copies of the contracts, information about his own credit and a number of other matters, and a statement of the condition of two jobs as of June 10th. On June 25, 1952, Stockbridge forwarded all this to Thompson in Hartford, and on July 3rd Thompson answered, returning what Stockbridge had sent and enclosing a proposed performance bond, to be executed by “Engineer” and the defendant that bound them to the City for $200,000 as principal and surety, conditioned upon “Engineer’s” furnishing the services required by the contract. This letter contained the following passage: “There are still several things we would like to have, namely a copy of the resolutions of September 10th, 1951, and an explanation of the debenture bonds payable in the amount of $44,600 shown in Pierce’s statement of April 30, to whom these are payable and when? We note that Pierce has a bank overdraft of $6,866.00 and it would be interesting to know what credit arrangements Pierce has with the bank. Of course it would be very desirable to see personal statements of the indemnitor.” Stockbridge wrote “Engineer” on July 8, enclosing the proposed performance bond, declaring that the defendant was “prepared to execute these Bonds * in your behalf,” and stating what the premiums would be.

Shortly thereafter Pierce appeared before the City Board of Light Commissioners with Stockbridge’s letter of July 8th and with some additional information, the contents of which are not very plain, but which, as he told the Board, was the best that he could get. He add *190 ed that he had done what he thought was necessary, and if they wanted to authorize further proceedings, it was at their expense. So far as appears, there for the time being the matter rested, until the City’s Board of Aldermen met on July 16, before whom the Mayor, who had obtained Stoekbridge’s letter, brought up the matter. Rowley (an insurance agent in the City of Burlington, who was secretary and director of Hickok and Boardman, Inc., a general insurance agency in Burlington) was present at this meeting. He got a photostatic copy of the letter and the proposed bond and unsuccessfully tried to induce two other companies to issue a bond such as Stoekbridge had proposed. About a month later Rowley called up the Hartford office of the defendant and asked to speak to Thompson, who was, however, on vacation. The operator then brought an unknown man to the telephone, who said that the defendant would “go along with the representative in Burlington, Hickok and Boardman, in the same manner that they would go along with their Boston agent.” Armed with this, on August 18th Rowley wrote a letter to the Board of Aldermen, as president of the “Burlington City Association of Insurance Agents, Inc.,” declaring that we ■“will be able to provide performance bonds” for “Engineer’s” contracts: “these bonds to be executed with the Century Indemnity Company in the same manner and on the same form as mentioned in the enclosed photostatic copy of a letter originally dated July 8, 1952.” He then went on to say that ordinarily "“the prime contractor” [is] “to furnish Bond in the full amount of the contract”; but that as in this case “much of the contract work will be performed by several independent contractors” it would be “necessary to acquire a completion Bond from each sub-contractor” and he suggested that the City “require each of these sub-contractors to furnish a Bond.” The Board referred this letter to the Electric Light Commission, which on the 21st voted that “no performance or completion bonds * * * seem necessary nor justified, considering costs.” In spite of this on the 25th the Board of Aldermen voted to instruct the Electric Light Commission to take out “performance bond on behalf of Pierce Consulting Engineering Co. * * * as recommended by the City Association of Insurance Agents in its communication dated August 18th.” In obedience to this vote the Commissioners on the 29th wrote to the Burlington City Association of Insurance Agents to “place performance bonds on the Pierce Consulting Engineering Company in the amount of $200,000 * * * as per your letter dated August 18th, 1952 to the Board of Aldermen.”

On the receipt of this letter Rowley spoke to Stoekbridge on the telephone, asking him “to take the necessary procedure to get the bond issued.” This talk was confirmed by a letter of Stuart, who like Rowley was an officer and employee of Hickok and Boardman, Inc. Part of this letter was as follows: “Pursuant to the recent telephone conversation between you and Mr. Rowley of this office and upon the authority of the Burlington Electric Light Commission, would you please complete the negotiations for the bonds with the Pierce Consulting Engineering Company, Inc., in the amount of $200,000. * * * These bonds are to be executed as of August 29th.” Pierce wrote Stoekbridge on the 23rd that Rowley had telephoned to ask “that we cooperate in obtaining a bond on the generating station. We understand the Burlington Agents are in the picture, and, in line with our endeavor to get the job done in Burlington, we are willing to cooperate with whatever insurance program is necessary." However, on the 29th Stoekbridge had an interview with Pierce to which he brought “several copies of our financial statement blank and Contractor’s Application Indemnity form,” and at which he told Pierce that he “was there to get the necessary underwriting information towards completion of our negotiations.” Pierce answered: “I don’t believe that you would want to bond us now,” and *191 he then showed Stockbridge several newspaper clippings which he suggested that Stockbridge should read.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
245 F.2d 188, 1957 U.S. App. LEXIS 3215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-burlington-v-century-indemnity-co-ca2-1957.