City of Brookhaven v. Multiplex, LLC

CourtCourt of Appeals of Georgia
DecidedJuly 27, 2023
DocketA23A0843
StatusPublished

This text of City of Brookhaven v. Multiplex, LLC (City of Brookhaven v. Multiplex, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Brookhaven v. Multiplex, LLC, (Ga. Ct. App. 2023).

Opinion

FIRST DIVISION BARNES, P. J., LAND, J., and WATKINS, J.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

July 27, 2023

In the Court of Appeals of Georgia A23A0843. CITY OF BROOKHAVEN v. MULTIPLEX, LLC.

LAND, Judge.

In this contract dispute, the City of Brookhaven appeals from the trial court’s

grant of summary judgment to Multiplex, LLC on the City’s claim for liquidated

damages. The City argues that the trial court erred in holding that the contract’s

“delay” clause was not an enforceable liquidated damages provision. We find no error

and affirm.

“Summary judgment is appropriate when no genuine issues of material fact

remain and the moving party is entitled to judgment as a matter of law. On appeal, we

review a trial court’s grant of summary judgment de novo, construing the evidence

and all inferences drawn from it in a light favorable to the nonmovant.” (Citations and punctuation omitted.) Stolte v. Hammack, 311 Ga. App. 710, 710 (716 SE2d 796) (2011).

Viewed in the light most favorable to the City, the record shows that in June

2017, the City negotiated a land swap with the Dekalb County School District for the

construction of a new park and elementary school. The project required the

demolition of an existing park, and the City did not want the neighborhood to go

without a park for an extended period of time. Accordingly, in the “Scope of Work”

document outlining the bid requirements for the construction of the new park, the

City included a deadline for completion of construction and a damages provision for

delays.

Multiplex was the lowest bidder, and the City entered into a contract with

Multiplex (the “Contract”).1 In relevant part, the Contract stated that “[t]he services

to be performed under this Contract shall commence on the date hereof. The initial

term of this Contract shall be through December 31, 2017. Time is of the essence for

this Contract. All work must be completed by December 31, 2018.”

1 The City also hired an architecture firm to “supervise, manage, and administer” the contract between the City and Multiplex.

2 The Contract also specifically incorporated several attachments, including the

“Scope of Work” addendum.2 The Scope of Work addendum contained a liquidated

damages provision (the “Delay Clause”), which stated that

[Multiplex] shall have 180 days from the notice to proceed to complete the project. Failure to complete the required construction as specified will result in the assessment of Liquidated Damages at the rate of $1,000.00 per calendar day.

The Contract was signed on June 15, 2017. While a “start date” of June 15 was

verbally communicated to Multiplex, it is undisputed that the City did not issue a

written notice to proceed.3 It appears construction began sometime in July. In October

2017, the City held a meeting with Multiplex to address delays in the project.4 On

2 In contrast to the Contract’s deadline for all work to be completed by December 31, 2018, the Scope of Work addendum provided that “[w]ork is expected to begin within 10 days of approval of the contract and all work must be completed within 180 [] calendar days.” 3 “Notice to proceed” is not defined in the contract and the Delay Clause does not specify whether the notice to proceed must be in writing. According to Section 20 of the “General Conditions” addendum, however, “all notices or other writings which the City is required or permitted to give the Service Provider may be hand delivered, mailed via U.S. Certified Mail or sent next-day delivery by a nationally- recognized overnight delivery service . . . .” 4 According to Section 3.3 of the “General Conditions” addendum, “[t]he City may order [Multiplex] to suspend, delay, or interrupt all or any part of the work . . . for such period of time as he may determine appropriate for the convenience of the

3 December 1, the City notified Multiplex that it was in breach of the Contract’s

timeline for completion, extended the completion deadline to December 31, and

warned Multiplex that the City would enforce the Contract’s Delay Clause if the

project was not completed by that date.

The project was not completed by December 31, however, and on January 3,

2018, the City notified Multiplex that it was in breach of the Contract. It is undisputed

that the park was substantially completed on September 28, 2018.

In February 2019, the City filed suit against Multiplex, alleging claims of

breach of contract, along with interpleader claims against subcontractors of

Multiplex, claiming that Multiplex had failed to complete the project and that the City

was entitled to liquidated damages in the amount of $271,000.00 for an alleged 271

days of delays. Multiplex answered the complaint and asserted counterclaims, seeking

damages due to the City’s alleged failure to pay Multiplex for work performed. The

City apparently resolved its claims with the third-party interpleader defendants and

City. The time for completion of the work shall be extended by the number of days the work is suspended. The City shall not be responsible for any claims, damages or costs stemming from any delay of the work.” Multiplex argues that construction was delayed by stop work orders from the City and severe weather.

4 amended its complaint, leaving only its claims for liquidated damages and attorney’s

fees.

In November 2021, Multiplex moved for summary judgment on the City’s

breach of contract claim for liquidated damages. The City filed a cross-motion for

summary judgment on its claim for liquidated damages and on all of Multiplex’s

counterclaims. Following a hearing, the trial court granted summary judgment to

Multiplex and denied the City’s cross-motion in its entirety. This appeal followed.

In three enumerations of error, the City argues that the trial court erred in

finding that the Contract’s Delay Clause was an unenforceable penalty. We disagree.

In public works contracts, liquidated damages provisions “are not looked upon

with disfavor,” Fortune Bridge Co. v. Dept of Transp., 242 Ga. 531, 534 (250 SE2d

401) (1978); rather, “[p]ublic works construction contracts may include both

liquidated damages provisions for late construction project completion and incentive

provisions for early construction project completion when the project schedule is

deemed to have value.” OCGA § 36-91-24. OCGA § 13-6-7 further provides that “[i]f

the parties agree in their contract what the damages for a breach shall be, they are said

to be liquidated and, unless the agreement violates some principle of law, the parties

are bound thereby.”

5 “In deciding whether a contract provision is enforceable as liquidated damages,

the court makes a tripartite inquiry.” Southeastern Land Fund, Inc. v. Real Est. World,

Inc., 237 Ga. 227, 228 (227 SE2d 340) (1976). “Specifically, the injury must be

difficult to estimate accurately, the parties must intend to provide damages instead of

a penalty, and the sum must be a reasonable estimate of the probable loss.”

(Punctuation and footnote omitted.) J.P. Carey Enterprises, Inc. v. Cuentas, Inc., 361

Ga. App. 383, 388 (1) (864 SE2d 588) (2021).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Peanut Co. v. Bass
547 S.E.2d 637 (Court of Appeals of Georgia, 2001)
Southeastern Land Fund, Inc. v. Real Estate World, Inc.
227 S.E.2d 340 (Supreme Court of Georgia, 1976)
Daniels v. Johnson
381 S.E.2d 87 (Court of Appeals of Georgia, 1989)
Roswell Properties, Inc. v. Salle
430 S.E.2d 404 (Court of Appeals of Georgia, 1993)
Physician Specialists in Anesthesia, P.C. v. MacNeill
539 S.E.2d 216 (Court of Appeals of Georgia, 2000)
Fuqua Construction Co. v. Pillar Development, Inc.
667 S.E.2d 633 (Court of Appeals of Georgia, 2008)
Fortune Bridge Co. v. Department of Transportation
250 S.E.2d 401 (Supreme Court of Georgia, 1978)
Mariner Health Care Management Co. v. Sovereign Healthcare, LLC
703 S.E.2d 687 (Court of Appeals of Georgia, 2010)
Stolte v. Hammack
716 S.E.2d 796 (Court of Appeals of Georgia, 2011)
JR Real Estate Development, LLC v. Cheeley Investment, L.P.
709 S.E.2d 577 (Court of Appeals of Georgia, 2011)
Gwinnett Clinic, Ltd. v. Boaten
798 S.E.2d 110 (Court of Appeals of Georgia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
City of Brookhaven v. Multiplex, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-brookhaven-v-multiplex-llc-gactapp-2023.