City of Brookhaven v. Multiplex, LLC

Court of Appeals of Georgia·Decided July 27, 2023·No. A23A0843·Published

Opinion

FIRST DIVISION

BARNES, P. J.,

LAND, J., and WATKINS, J.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed.

https://www.gaappeals.us/rules

July 27, 2023

In the Court of Appeals of Georgia A23A0843. CITY OF BROOKHAVEN v. MULTIPLEX, LLC.

LAND, Judge.

In this contract dispute, the City of Brookhaven appeals from the trial court’s grant of summary judgment to Multiplex, LLC on the City’s claim for liquidated damages. The City argues that the trial court erred in holding that the contract’s “delay” clause was not an enforceable liquidated damages provision. We find no error and affirm.

“Summary judgment is appropriate when no genuine issues of material fact remain and the moving party is entitled to judgment as a matter of law. On appeal, we review a trial court’s grant of summary judgment de novo, construing the evidence and all inferences drawn from it in a light favorable to the nonmovant.” (Citations and

punctuation omitted.) Stolte v. Hammack, 311 Ga. App. 710, 710 (716 SE2d 796) (2011).

Viewed in the light most favorable to the City, the record shows that in June 2017, the City negotiated a land swap with the Dekalb County School District for the construction of a new park and elementary school. The project required the demolition of an existing park, and the City did not want the neighborhood to go without a park for an extended period of time. Accordingly, in the “Scope of Work” document outlining the bid requirements for the construction of the new park, the City included a deadline for completion of construction and a damages provision for delays.

Multiplex was the lowest bidder, and the City entered into a contract with Multiplex (the “Contract”).1 In relevant part, the Contract stated that “[t]he services to be performed under this Contract shall commence on the date hereof. The initial term of this Contract shall be through December 31, 2017. Time is of the essence for this Contract. All work must be completed by December 31, 2018.”

1 The City also hired an architecture firm to “supervise, manage, and administer” the contract between the City and Multiplex.

The Contract also specifically incorporated several attachments, including the “Scope of Work” addendum.2 The Scope of Work addendum contained a liquidated damages provision (the “Delay Clause”), which stated that

[Multiplex] shall have 180 days from the notice to proceed to complete the project. Failure to complete the required construction as specified will result in the assessment of Liquidated Damages at the rate of $1,000.00 per calendar day.

The Contract was signed on June 15, 2017. While a “start date” of June 15 was verbally communicated to Multiplex, it is undisputed that the City did not issue a written notice to proceed.3 It appears construction began sometime in July. In October 2017, the City held a meeting with Multiplex to address delays in the project.4 On

2 In contrast to the Contract’s deadline for all work to be completed by December 31, 2018, the Scope of Work addendum provided that “[w]ork is expected to begin within 10 days of approval of the contract and all work must be completed within 180 [] calendar days.”

3 “Notice to proceed” is not defined in the contract and the Delay Clause does not specify whether the notice to proceed must be in writing. According to Section 20 of the “General Conditions” addendum, however, “all notices or other writings which the City is required or permitted to give the Service Provider may be hand delivered, mailed via U.S. Certified Mail or sent next-day delivery by a nationallyrecognized overnight delivery service . . . .”

4 According to Section 3.3 of the “General Conditions” addendum, “[t]he City may order [Multiplex] to suspend, delay, or interrupt all or any part of the work . . . for such period of time as he may determine appropriate for the convenience of the

December 1, the City notified Multiplex that it was in breach of the Contract’s timeline for completion, extended the completion deadline to December 31, and warned Multiplex that the City would enforce the Contract’s Delay Clause if the project was not completed by that date.

The project was not completed by December 31, however, and on January 3, 2018, the City notified Multiplex that it was in breach of the Contract. It is undisputed that the park was substantially completed on September 28, 2018.

In February 2019, the City filed suit against Multiplex, alleging claims of breach of contract, along with interpleader claims against subcontractors of Multiplex, claiming that Multiplex had failed to complete the project and that the City was entitled to liquidated damages in the amount of $271,000.00 for an alleged 271 days of delays. Multiplex answered the complaint and asserted counterclaims, seeking damages due to the City’s alleged failure to pay Multiplex for work performed. The City apparently resolved its claims with the third-party interpleader defendants and

City. The time for completion of the work shall be extended by the number of days the work is suspended. The City shall not be responsible for any claims, damages or costs stemming from any delay of the work.” Multiplex argues that construction was delayed by stop work orders from the City and severe weather.

amended its complaint, leaving only its claims for liquidated damages and attorney’s fees.

In November 2021, Multiplex moved for summary judgment on the City’s breach of contract claim for liquidated damages. The City filed a cross-motion for summary judgment on its claim for liquidated damages and on all of Multiplex’s counterclaims. Following a hearing, the trial court granted summary judgment to Multiplex and denied the City’s cross-motion in its entirety. This appeal followed.

In three enumerations of error, the City argues that the trial court erred in finding that the Contract’s Delay Clause was an unenforceable penalty. We disagree.

In public works contracts, liquidated damages provisions “are not looked upon with disfavor,” Fortune Bridge Co. v. Dept of Transp., 242 Ga. 531, 534 (250 SE2d 401) (1978); rather, “[p]ublic works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value.” OCGA § 36-91-24. OCGA § 13-6-7 further provides that “[i]f the parties agree in their contract what the damages for a breach shall be, they are said to be liquidated and, unless the agreement violates some principle of law, the parties are bound thereby.”

Free access — add to your briefcase to read the full text and ask questions with AI

City of Brookhaven v. Multiplex, LLC, (Ga. Ct. App. 2023).

City of Brookhaven v. Multiplex, LLC (City of Brookhaven v. Multiplex, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golden Peanut Co. v. Bass
547 S.E.2d 637 (Court of Appeals of Georgia, 2001)
Southeastern Land Fund, Inc. v. Real Estate World, Inc.
227 S.E.2d 340 (Supreme Court of Georgia, 1976)
Daniels v. Johnson
381 S.E.2d 87 (Court of Appeals of Georgia, 1989)
Roswell Properties, Inc. v. Salle
430 S.E.2d 404 (Court of Appeals of Georgia, 1993)
Physician Specialists in Anesthesia, P.C. v. MacNeill
539 S.E.2d 216 (Court of Appeals of Georgia, 2000)
Fuqua Construction Co. v. Pillar Development, Inc.
667 S.E.2d 633 (Court of Appeals of Georgia, 2008)
Fortune Bridge Co. v. Department of Transportation
250 S.E.2d 401 (Supreme Court of Georgia, 1978)
Mariner Health Care Management Co. v. Sovereign Healthcare, LLC
703 S.E.2d 687 (Court of Appeals of Georgia, 2010)
Stolte v. Hammack
716 S.E.2d 796 (Court of Appeals of Georgia, 2011)
JR Real Estate Development, LLC v. Cheeley Investment, L.P.
709 S.E.2d 577 (Court of Appeals of Georgia, 2011)
Gwinnett Clinic, Ltd. v. Boaten
798 S.E.2d 110 (Court of Appeals of Georgia, 2017)