City of Brookfield v. Milwaukee Metropolitan Sewerage District

414 N.W.2d 308, 141 Wis. 2d 10, 1987 Wisc. App. LEXIS 3974
CourtCourt of Appeals of Wisconsin
DecidedAugust 5, 1987
Docket87-0004
StatusPublished
Cited by7 cases

This text of 414 N.W.2d 308 (City of Brookfield v. Milwaukee Metropolitan Sewerage District) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Brookfield v. Milwaukee Metropolitan Sewerage District, 414 N.W.2d 308, 141 Wis. 2d 10, 1987 Wisc. App. LEXIS 3974 (Wis. Ct. App. 1987).

Opinion

SCOTT, C.J.

The cities of Brookfield, Mequon and New Berlin and the villages of Butler, Elm Grove and Menomonee Falls (municipalities) appeal a judgment affirming a Public Service Commission (commission) order. The municipalities had filed a complaint against the Milwaukee Metropolitan Sewerage District (district) under sec. 66.912(5), Stats., alleging that the district’s method of capital cost recovery was unreasonable or unjustly discriminatory. The commission found in favor of the district, concluding that the inclusion of the cost of "construction work in progress” (CWIP) in its capital cost rate base was a reasonable method recovering those costs. The municipalities sought review under sec. 227.52, Stats. 1 The circuit court affirmed the commission’s decision. We conclude that there is substantial evidence to support *13 the commission’s decision, and we therefore affirm the trial court.

The district is a municipal corporation which provides sewage treatment services for Milwaukee county (with the exception of the city of South Milwaukee). The district has also provided sewage treatment services for the municipalities involved in this appeal. At issue here is the method used by the district to finance certain construction work known as the Milwaukee Water Pollution Abatement Program. This project has an estimated cost of $2.8 billion in interest and capital charges. The project will extend from 1983 to 1996, although construction is divided into segments, each of which will take approximately two years to finish.

In the field of utility or public service financing there are a number of ways in which large construction projects are financed. One method is called CWIP (construction work in progress) because it adds the cost of plant expansion to the rate base as the plant is being constructed rather than waiting until the project is completed and the plant operational. The CWIP method, therefore, generates revenue immediately. However, current customers, not future customers, are paying for the cost of construction.

In an alternative method, the district finances the cost of the project and recovers it in the future through higher depreciation charges and an additional dollar return on capital for the increased cost of the plant. This method, called "allowance for funds used during construction” (AFUDC), means that until a project is actually in service, it does not generate cash to pay for itself and, in fact, builds up additional interest or carrying charges for future customers to pay.

*14 The primary issue in this case is not which of the methods is the best or the fairest, nor is it which method the commission would have adopted for a utility directly under its regulatory jurisdiction. The issue before the commission and now before this court is whether the CWIP method used by the district was unreasonable or unjustly discriminatory within the meaning of sec. 66.912(5), Stats. 2 The municipalities claim that it is. They also contend that the rate base is inconsistent with officially stated policy or prior practice and that the case should be remanded to the commission to enable it to make proper findings of fact and conclusions of law.

Application of a legal standard to a particular set of facts presents a question of law. Wisconsin Dep’t of Transp. v. Office of the Comm’r of Transp., 135 Wis. 2d 195, 198, 400 N.W.2d 15, 16 (Ct. App. 1986). Generally, we need not defer to the administrative agency’s decision. Id. However, labeling the commission’s determination a conclusion of law does not result in this court totally disregarding the commission’s determination. See Nottelson v. DILHR, 94 Wis. 2d 106, 116-17, 287 N.W.2d 763, 768 (1980). The determination of whether the district’s charges are unreason *15 able or unjustly discriminatory calls for a value judgment. Moreover, rate setting is an area in which the commission has special expertise. When an administrative agency’s determination calls for a value judgment, an appellate court must decide to what extent it should substitute its evaluation for that of the agency. When the expertise of the agency is significant to the value judgment, the agency’s decision, although not controlling, should be given weight. Nigbor v. DILHR, 120 Wis. 2d 375, 383-84, 355 N.W.2d 532, 537 (1984).

In its decision, the commission stated:

[T]he standard to be used upon a complaint under s. 66.912(5), Stats., requires that in order for the commission to change a rate or practice under the complaint, the commission must find that the rate or practice is unreasonable or unjustly discriminatory. Otherwise, the rate or practice that is in effect must remain, even though the rate or practice is not one that the commission agrees with or would itself provide.
... [W]hile there are arguments for both sides on the CWIP issue, the arguments against including CWIP were not sufficient to conclude that such procedure was unreasonable. Therefore, the commission will not determine that the charges based on such procedures are unreasonable.

The inclusion of CWIP in the rate base of the district may discriminate against future generations, but the municipalities have the burden of showing that CWIP unjustly discriminates. The commission concluded that the municipalities have failed to meet that burden.

*16 If legal conclusions of an administrative agency are reasonable, they will be sustained on appeal even if an alternate view is equally reasonable. Chappy v. LIRC, 128 Wis. 2d 318, 323, 381 N.W.2d 552, 555 (Ct. App. 1985), aff’d, 136 Wis. 2d 172, 401 N.W.2d 568 (1987). Since the commission’s determination is in an area in which it has special expertise, and in light of our decision to give deference to the commission’s determination because of that expertise, we conclude that the commission’s determination is reasonable and therefore affirm it.

The municipalities also contend that the commission’s authorization to include CWIP in the district’s rate base is inconsistent with the commission’s officially stated policy or prior practice and ask this court to reverse or remand the case. The municipalities rely upon a commission decision setting forth the reasons why and the circumstances under which CWIP could be included in the rate base of an investor-owned utility. 3 We reject the municipalities’ argument.

The commission decision that the municipalities rely on concerns investor-owned utilities rather than a municipal corporation such as the district.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wisconsin Bell, Inc. v. Public Service Commission
2004 WI App 8 (Court of Appeals of Wisconsin, 2003)
Barron Electric Cooperative v. Public Service Commission
569 N.W.2d 726 (Court of Appeals of Wisconsin, 1997)
City of Brookfield v. Public Service Commission
519 N.W.2d 718 (Court of Appeals of Wisconsin, 1994)
Century 21 Associated Realty v. Hoffman
503 N.W.2d 861 (South Dakota Supreme Court, 1993)
GTE North Inc. v. Public Service Commission
486 N.W.2d 554 (Court of Appeals of Wisconsin, 1992)
Wisconsin Title Service, Inc. v. Kirkland & Ellis
483 N.W.2d 275 (Court of Appeals of Wisconsin, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
414 N.W.2d 308, 141 Wis. 2d 10, 1987 Wisc. App. LEXIS 3974, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-brookfield-v-milwaukee-metropolitan-sewerage-district-wisctapp-1987.