City of Boston v. Pagliaro

294 N.E.2d 531, 1 Mass. App. Ct. 117, 1973 Mass. App. LEXIS 429
CourtMassachusetts Appeals Court
DecidedFebruary 23, 1973
StatusPublished
Cited by4 cases

This text of 294 N.E.2d 531 (City of Boston v. Pagliaro) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Boston v. Pagliaro, 294 N.E.2d 531, 1 Mass. App. Ct. 117, 1973 Mass. App. LEXIS 429 (Mass. Ct. App. 1973).

Opinion

Hale, C.J.

The city of Boston (city) by this bill of complaint seeks to enjoin the construction of a seventeen-story apartment building at 1410 Columbia Road in South Boston, alleging that the building will be in violation of the floor area ratio requirements of articles 13 and 15 of the Boston Zoning Code (1968), (Code). The bill was filed on July 14,1971. A temporary injunction against the construction of the building was denied.

The case was tried before a Superior Court judge who voluntarily filed “Findings, Rulings, and Order” pursuant to which a final decree was entered dismissing the bill. The case is before us on the city’s appeal. The evidence is reported.

We summarize the facts found by the judge and additional facts not specifically found by him which we find from the record and which we consider material. The property at 1410 Columbia Road, South Boston, was purchased by Bay Towers Trust (Trust) in December, 1970. The lot, which was in an H-2 zoning district, was occupied by a four-story building which formerly housed a brewery. On January 12, 1971, the Trust applied for a building permit and submitted plans for a proposed seventeen-story building containing 153 apartments with three basement levels for off-street parking. After the plans were submitted, a representative of the owner’s architect (architect) conferred with John Curtis, the zoning administrator in the city building department. During their discussion Curtis advised the architect that there was a zoning setback problem affecting the garage structure. The architect stated that he could redraft the plans to bring them into compliance with the setback requirements. Curtis then *119 informed the architect that the floor area ratio requirements of the Code permitted this structure to be built with a maximum floor area ratio of 2.5 instead of 2.0, as the lot abutted public open space having a width of more than 100 feet. 1 According to Curtis the proposed building was in compliance with the floor area ratio requirements of the Code. The architect thereafter submitted revised plans and Curtis approved the plans on March 24, 1971, but the building commissioner told a representative of the owners that although the plans were in order, a building permit could not issue until certain microfilms of the plans were received. The fee for the permit was then paid. Demolition of the old brewery building on the site was then begun. On March 29, 1971, the microfilms of the plans were received by the building department.

On April 8,1971, no building permit having been issued, the Trust instituted a petition in the Superior Court for a writ of mandamus against the building commissioner and the city to compel the building commissioner to issue the building permit. The petition for the writ of mandamus in the prior proceeding averred (1) that the submitted plans and specifications “conform in all respects to the City of Boston Building Code and Zoning Ordinances” (emphasis supplied). The petition also averred (2) that “[I]t is [the building commissioner’s] official duty to issue Building Permits pursuant to the Building Code and Zoning Ordinances of the City of Boston.” The petition further averred *120 (3) that the building department of the city had examined the plans and specifications and determined that they conformed in all respects to the building code and zoning “ordinances.” The answer to the petition admitted the second of these averments. The other two were not specifically controverted and must be taken to have been admitted. A trial was held in April, 1971, at which Curtis testified that the plans conformed to the zoning requirements for the district in which the building was to be erected. No question was put to Curtis with respect to the floor area ratio requirements, nor did he testify on this subject. The building commissioner testified that he had received a telephone call from the mayor directing him not to issue the building permit and that he had received another call from a legislator. His attention was directed by these calls to the possibility that the premises were incorrectly zoned. He testified that he had stopped action on the issuance of the permit so that he could “examine those conditions that were alleged to exist around this fact. I did examine them and I find that the building is properly zoned in an H-2 district.” The building plans examiner of the building department testified that before a building permit could issue an affidavit of a structural engineer to the effect that he would make an on-site inspection during the construction would have to be furnished. This requirement was complied with during an overnight recess in the trial. At the conclusion of the trial the judge ordered the writ to issue. The building permit was issued to the Trust on April 16, 1971, in compliance with the mandate of the writ. No appeal was pursued in that case.

On May 5, 1971, Curtis sent a letter to the Federal Housing Administration, which agency was to insure a mortgage under which the building was to be financed. The letter stated that the proposed building fully complied with the code for an H-2 district. Title to the property was transferred from the Trust to the present defendants, who are partners doing business as Bay Towers Associates. The mortgage closing with the Federal Housing Administration took place the same day. Work on the project was continued *121 and excavation of the site undertaken. By June 15,1971, a pile driving rig was on the site and was in operation on June 17,1971, driving test piles.

On July 6, 1971, a conference was held between city officials and the defendants during which the defendants were informed for the first time that a new interpretation of the existing provisions of the Code relating to floor area ratio requirements had been made. This new interpretation was conceived by a representative of the mayor’s office prior to the mandamus proceeding, but it appears that it was not publicly announced until this meeting. The building commissioner was aware of it prior to the mandamus proceeding, had discussed it with the mayor, and had been instructed by the mayor not to issue a building permit. The effect of this new interpretation, contrary to what Curtis had instructed the architect prior to the mandamus proceeding, was to set the maximum permissible floor area ratio, after the application of the credit for land abutting certain public open space, at 2.0 instead of 2.5. The defendants were told that nothing could be done to make the building, as planned, comply with the floor area ratio requirements as newly interpreted. The officials then requested the defendants to return the building permit which they refused to do.

The present suit was instituted on July 14, 1971. As of that date the defendants had expended or irrevocably committed $1,300,000 to the project. A condition of their loan agreement with the Federal Housing Administration required the building to be completed within eighteen months and provided that if work stopped for more than twenty days the mortgage could be foreclosed. Despite the suit work was continued on the project and by the end of November, when this case was tried, eight stories of structural steel had been erected. 2

The defendants 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Coutu
90 Mass. App. Ct. 227 (Massachusetts Appeals Court, 2016)
Morganelli v. Building Inspector of Canton
388 N.E.2d 708 (Massachusetts Appeals Court, 1979)
Tisei v. Building Inspector of Marlborough
363 N.E.2d 262 (Massachusetts Appeals Court, 1977)
Turner v. Guy
311 N.E.2d 921 (Massachusetts Appeals Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
294 N.E.2d 531, 1 Mass. App. Ct. 117, 1973 Mass. App. LEXIS 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-boston-v-pagliaro-massappct-1973.