City of Atlanta v. Kovalcik

765 S.E.2d 693, 329 Ga. App. 523, 2014 Ga. App. LEXIS 733
CourtCourt of Appeals of Georgia
DecidedNovember 12, 2014
DocketA14A0768
StatusPublished
Cited by1 cases

This text of 765 S.E.2d 693 (City of Atlanta v. Kovalcik) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Atlanta v. Kovalcik, 765 S.E.2d 693, 329 Ga. App. 523, 2014 Ga. App. LEXIS 733 (Ga. Ct. App. 2014).

Opinion

Doyle, Presiding Judge.

In this interlocutory appeal, the City of Atlanta appeals from the denial of its motion for summary j udgment in a wrongful death action brought by the parents of Stephanie Kovalcik, who died in a nighttime car wreck at a newly reconfigured intersection in the City. The City contends that the trial court erred because (1) the City cannot be liable for any lighting defects in the absence of an underlying roadway defect, (2) the City had no duty to maintain the lighting, and (3) the undisputed facts show that the City had not assumed maintenance responsibility for the lighting. For the reasons that follow, we affirm.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant.1

The background facts in this case are largely undisputed and are the same as those recited in Dept. of Transp. v. Kovalcik,2 in which this Court recently addressed an appeal by the Georgia Department of Transportation (“DOT”) based on the same wreck.3

[T]he DOT, the City of Atlanta, and the Buckhead Community Improvement District (“BCID”) began planning a road improvement project to redesign a portion of Peachtree Road (“Project”), a State route within the City limits. In February 2004, the DOT and the City entered into an agreement to undertake certain improvements including the Project. The agreement stated that the City would [“] accomplish all of the design activities for the project in accordance with the DOT’s Plan Development Process, the applicable guidelines of the American Association of State Highway and Transportation Officials, the DOT’s Standard Specifications Construction of [524]*524Roads and Bridges, the [DOT’s] Plan Presentation Guide, Project schedules, and applicable guidelines of the DOT.[”]
The contract further provided that the DOT [“] shall review and has approval authority for all aspects of the Project provided however this review and approval does not relieve the City of its responsibilities under the terms of this agreement. The DOT will work with the [Federal Highway Administration] to obtain all needed approvals with information furnished by the City.[”]
Pursuant to an agreement between the BCID and the City, the BCID retained URS Corporation to deliver construction plans that included road design, signage, pavement markings, curbs, traffic signals, and landscaping. URS prepared the plans and, through an iterative process of review and feedback, the DOT approved them.
In January 2006, the DOT awarded a construction contract to Infrasource Paving and Concrete Services, and contracted with Parsons Brinkerhoff Shuh & Jernigan (“PBS J”) to provide construction, engineering, and inspection services for the Project. . . .
Active construction ended [with a ribbon cutting ceremony] in October 2007, and a final inspection was performed in January 2008. On a rainy night in March 2008, Cameron Bridges approached the intersection in Stephanie’s car with her as his passenger. The complaint alleges that Bridges was heading south on Peachtree Road, and, intending to turn left onto Piedmont Road, Bridges entered what he believed to be the left-hand turn lane. Instead, the vehicle entered a short left-hand turn lane immediately preceding the Piedmont intersection so that drivers could turn left into a parking lot at the northeast corner of Peachtree and Piedmont. This shorter turn lane was bounded by a concrete divider, which allegedly caused the vehicle to roll when Bridges mistakenly drove into it. [Several newly installed street lights in the area were not illuminated on the night of the crash.]
Stephanie died of injuries she suffered in the crash, and the Kovalciks filed suit against the DOT, the City, BCID, URS, PBSJ, and others.4

[525]*525Following discovery, the City moved for summary judgment, arguing that it was not involved with the design, construction, or inspection activities — all of which were conducted by various contractors according to the agreements between the City, BCID and DOT. The City also argued that the street lighting was not under the purview of the City at the time of the accident. The trial court, in a two-sentence order, denied the City’s motion, concluding that “a jury should determine whether [the City] assumed, or should have assumed, responsibility for the streetlights at issue herein.” The trial court certified its decision for immediate review; this Court then granted the City’s application for interlocutory review.

1. The City first argues that defective lighting cannot give rise to liability on the part of the City absent some underlying defect in the street. The City relies on Roquemore v. City of Forsyth,5 which addressed a suit against a city by a pedestrian hit by a car at an intersection. In that case, the Court summarized the relevant law as follows:

The law is well settled in this State that a municipal corporation is bound to keep its streets and sidewalks in a reasonably safe condition for travel in the ordinary modes, by night as well as by day, and if it fails to do so, it is liable for damages for injuries sustained in consequence of such failure. But it is also undisputed that the decision whether to provide lighting on a particular city street is a discretionary function of a municipality. Such lighting is a discretionary act of the municipality, and for the exercise or failure to exercise such a power no right of action accrues. And it would seem that the discretion to install a system of lighting would include a discretion to discontinue it.
In reconciling a city’s duty to maintain safe streets with its discretion in providing lighting on those streets, the Supreme Court of Georgia has held that “the character of the light at a dangerous point in the street, or its absence, may be shown as a circumstance bearing on” the issue of whether a city has maintained a street in a reasonably safe condition, or whether it was negligent in that regard. But the mere absence of an ordinary street light at a given point will not constitute such negligence as to render the city liable if the city otherwise has performed its obligation to keep the streets safe and free from defects. The [C]ourt explained that “nei[526]*526ther the absence of lights nor defective lights is in itself negligence, but is only evidence on the principal question, whether, at the time and place where an injury occurred, the streets were in a reasonably safe condition.” And Georgia courts have never held that the temporary failure of a street-light to burn at a point where there is no obstruction, excavation, or other extraordinary defect in the street, gives rise to any liability against a city or its agents.6

Based on the emphasized language, the City argues that it has no liability stemming from the mere absence of working street lights at the site of the crash.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glover v. Georgia Power Company
819 S.E.2d 660 (Court of Appeals of Georgia, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
765 S.E.2d 693, 329 Ga. App. 523, 2014 Ga. App. LEXIS 733, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-atlanta-v-kovalcik-gactapp-2014.