City of Ashland v. Steele

292 S.W. 1098, 219 Ky. 341, 1926 Ky. LEXIS 127
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedNovember 30, 1926
StatusPublished
Cited by1 cases

This text of 292 S.W. 1098 (City of Ashland v. Steele) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Ashland v. Steele, 292 S.W. 1098, 219 Ky. 341, 1926 Ky. LEXIS 127 (Ky. 1926).

Opinion

*342 Opinion op ti-ie Court by

Commissioner Sandidge—

Affirming.

This is a proceeding’ under the Declaratory Judgment Act (Laws 1922, c. 83), and the facts are agreed. There are three of the appeals. The city of Ashland is •appellant in'one of them, and Sam L. Steele and S. S. Moore are appellees. Sam L. Steele is appellant in one. of them, and the city of Ashland and Mr. Moore are •appellees. In the other appeal S. S. Moore is the appellant and the city of Ashland and Mr. Steele are appellees. For convenience we will refer to them hereinafter as the municipality, Mr. Moore, and Mr. Steele.

It first becomes necessary to determine whether three •contracts for the construction of certain of the streets of the municipality entered into by it with Mr. Steele are valid under the steps taken to that end. The municipality is a city of the second class. This action was instituted to determine the rights and liabilities of the parties before any of the work has been done. The only •question affecting, the validity of the contract between the municipality and Mr. Steele arises from the provisions ■of section 3096, Kentucky Statutes, that “no- ordinance for the original improvement of any public street or sidewalk as contemplated in this section shall pass both boards of said general council on the same day, but at least two weeks shall elapse between the passage of any such ordinance from one board to the other.” Two weeks did not elapse between the passage of the ordinance for the construction of the streets involved in the controversy herein, by the two boards of the municipality. It is insisted for Mr. Steele, however, that, in view of the fact that these ordinances were enacted pursuant to a petition to the -general council of the municipality, which was signed by all of the owners of property fronting and abutting on the streets to be improved, who, by the' petition, asked to have the -streets constructed at their expense, and agreed that their property fronting and abutting thereon might be put in lien for the payment of ,same, the requirement of the statute, supra, that two weeks must elapse between the passage of the proposed ordinance by the two boards of the municipality’s general council was waived; and that, therefore, the ordinances so enacted are not invalid. Whether that would be true in a case where no interest is involved other than that of the property holders with property abutting on the streets *343 proposed to be improved is not here presented, and consequently will not be determined. We find that by the further provisions of section 3096, supra, it is required that the city .shall pay the cost of the improvement of intersections with other public ways, including one-half of the width of the street or alley being improved opposite other streets or alleys which run into but do not cross, the street or -alley -so being improved. It appears from the ordinances in controversy herein that the street intersections on the street to be constructed had not theretofore been constructed by the city, but were required to be constructed under the ordinances and contracts in controversy at the expense of the city. Consequently, w-e have a case in which the interest of those owing property fronting and abutting on the -streets- proposed to be- constructed is not the sole interest involved. The city being required at its expense to construct all of the street intersections from funds derived from taxation generally, the interest of all of the taxpayers of the city necessarily was involved in the proposed street construction and in the ordinances and other steps required to the end that valid ordinances and contracts may be enacted -and entered into by the municipality. That interest being involved herein, it seems impossible to escape the conclusion that ordinances for the construction of streets and contracts to that end can validly be enacted and entered into by the municipality only when done in accordance with the statutory authority for so doing.

It was held in this court in Thomas v. Woods, 128 Ky. 555, 108 S. W. 878, 32 Ky. Law Rep. 1405, that the provision that two weeks must elapse between the passage of such ordinances in the- two boards of the general council is mandatory, and that ordinances passed otherwise are invalid. Though the statute in question has been amended in some particulars, as attorney for Mr. Steele suggests, the amendments cannot be said to have had the effect of removing the cause and the reason for this court’s holding that the provision,.supra, is mandatory. The provision that two weeks must elapse between the passage- of such ordinances -by the two' boards, which had been construed and held to be mandatory by this court in the Thomas Case, supra, was left intact in the statute as amended, clearly indicating the legislative intention that it should continue to be so regarded by the courts. It is agreed, and the records of the municipality in evidence herein disclose, that the ordinances for the *344 construction of the streets in question were enacted by the two hoards of the general council of the municipality in much less than two weeks. Mr. Steele’© right to a contract and to be permitted to construct those streets must rest upon the validity of the ordinances so passed. For the reasons indicated, this court is .of the opinion that he has failed to> manifest 'his right to the relief sought by him herein. The judgment of the chancellor denying him such right, therefore, will be affirmed. .

After the enactment of the ordinances under which Mr. Steele claimed the right to a contract with the city for the construction -of the streets in question, the municipality, advised that they were invalid because the ordinances were enacted by the two boards within less than two weeks, again enacted ordinances for construction of the streets in question, and more than two weeks elapsed between their passage by the two boards. Mr. Moore asserts his right herein under the ordinances last enacted.

Section 3097, Kentucky Statutes, provides:

“Before the1 general council shall order the improvement of any street, alley, public way or sidewalk as provided in section 3096 it shall adopt a resolution designating the street or other public way or sidewalk proposed to be improved, .setting out in general terms the character and extent of the proposed improvement 'and declaring such improvement to be a necessity. ’ ’

Section 3059, Kentucky Statutes, provides:

“No ordinance and no resolution shall be passed unless a majority of the members-elect in each board shall vote therefor on a viva voce vote, which shall be entered in full on the journals of the two boards, ■and until it shall have been read in each board at two several meetings and free discussion allowed thereon; so. much of this provision as requires a reading at two several meetings may be suspended by a vote of two-thirds of all the members-elect of the board in which the proposed ordinance or resolution is pending. ”

It appears herein that, in adopting the resolution declaring the necessity for the improvement of the streets in question required to be done by section ;3'097, supra, *345

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dixon v. Louisville Asphalt Co.
20 S.W.2d 470 (Court of Appeals of Kentucky (pre-1976), 1929)

Cite This Page — Counsel Stack

Bluebook (online)
292 S.W. 1098, 219 Ky. 341, 1926 Ky. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-ashland-v-steele-kyctapphigh-1926.