City of Akron v. Public Utilities Commission

378 N.E.2d 480, 55 Ohio St. 2d 155, 9 Ohio Op. 3d 122, 1978 Ohio LEXIS 632
CourtOhio Supreme Court
DecidedJuly 19, 1978
DocketNo. 77-613
StatusPublished
Cited by31 cases

This text of 378 N.E.2d 480 (City of Akron v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Akron v. Public Utilities Commission, 378 N.E.2d 480, 55 Ohio St. 2d 155, 9 Ohio Op. 3d 122, 1978 Ohio LEXIS 632 (Ohio 1978).

Opinions

Per Curiam.

A commission finding will not be disturbed unless manifestly against the weight of the evidence and so clearly unsupported by the record as to show misapprehension, mistake, or willful disregard of duty. Ford Motor Co. v. Pub. Util. Comm. (1977), 52 Ohio St. 2d 142, 152.

[157]*157Appellants assert in their first proposition of law that the commission erred in setting a rate of return of 9.07 percent based solely upon a stipulation between Ohio Edison and the commission staff. Appellants assert further that the only witness at the hearing mentioning this 9.07 percent rate of return specifically refused to recommend it when questioned on direct examination. Appelants allege that the maximum rate Ohio Edison sought in its application was 8.50 percent, a figure that the utility thought was fully compensable.

This proposition has three parts: (1) the weight accorded the stipulation; (2) the refusal of the staff’s witness to recommend the 9.07 rate of return; and (3) the contention that the authorized rate of return was higher than the maximum sought by the utility.

In alleging that the commission gave undue weight to the stipulation, appellants assert that Ohio Edison did not meet its burden of proving its existing rates were unjust and unreasonable. There is no doubt that this burden is on the applicant utility. See Mt. Vernon Telephone Corp. v. Pub. Util. Comm. (1955), 163 Ohio St. 381. Further, it is true that Ohio Edison chose not to present any rate-of-return witnesses to prove its existing rates inadequate, but rather to stipulate to the cost of capital and the rate of return determined by the commission staff. Appellants urge that because Ohio Edison presented no such witnesses, its burden could not have been met as a matter of law.

The commission encourages agreement on issues raised in an application. But here, there was not total agreement — appellants stipulated only to the rate base, not the cost of capital or the rate of return. Thus, the agreement between Ohio Edison and the commission was not a * ‘ stipulation,” as all parties had not agreed to it.

The commission, of course, is not bound to the terms of any stipulation; however, such terms are properly accorded substantial weight. Likewise, the commission is not bound by the findings of its staff. Nevertheless, those findings are the result , of detailed investigations and are-entitled to careful consideration.

[158]*158Ohio Edison agreed to the staff’s determination of rate base, rate of return and cost of capital. Thus, this accord was not a negotiated agreement, but rather an acquiesenee of the staff’s findings. The resulting recommendations were given substantial weight by the commission because they were the result of the staff’s investigation, mot because they were part of a “stipulation.” The record shows that the commission afforded appellants full opportunity to present evidence with respect to all contested issues.

Ohio Edison was justified in relying on the staff report to demonstrate that its present rates were inadequate. There is an inherent risk in so doing, but the staff report, if accepted by the commission, may be sufficent evidence as a matter of law to meet the burden of showing the existing rates inadequate. This has long been the standard followed by this commission. See Re Dayton Power & Light Co. (1961), 39 PUR 3d 390, 403.

The second part of this first proposition concerns appellants’ allegation that the only staff witness who mentioned 9.07 percent return specifically refused to recommend it.

In its report filed on September 20, 1976, the staff estimated the weighted cost of capital to be 7.26 percent. In reaching that figure, the cost of common equity used was adjusted downward to account for the inflationary characteristics of the then-effective statutory RCNLD rate base.

Such a downward adjustment, as the staff pointed out in its report, is not permitted under this court’s decision in General Telephone Co. v. Pub. Util. Comm. (1976), 46 Ohio St. 2d 281.2 Therefore, in complying with this court’s [159]*159interpretation of the then-existing law, the staff concluded in its report:

“By excluding the inflation adjustment previously made, the rate of return computed above would increase to 8.96%. While the staff recognizes that 8.96% may be a legally appropriate rate of return, it does not recommend this figure from an economic standpoint.” (Emphasis added.)

At the hearing the staff witness updated the cost of capital calculation to include data as of September 30, 1976, resulting in a figure of 9.07 percent.

The staff witness used methods long employed by economists testifying before the commission to calculate the cost of capital of applicant utilities. The record shows that, as an economist, the staff witness would not recommend a 9.07 percent rate. In other words, that witness apparently did not agree with this court’s holding in General Telephone, supra. While the witness may be “free” to disagree on an economic basis, the commission may not ignore the then-existing statute and its interpretation by this court. Appellants have not shown that this legally appropriate rate is unreasonable or unlawful.

The third portion of this proposition alleges that, in its application, the maximum rate Ohio Edison sought was 8.50 percent, which it believed to be “fully compensable. ’ ’

The rate of return is the dollar return generated under the proposed rates as a certain percentage of the statutory rate base. The commission adopted a rate base which was some $91 million less than that originally proposed by Ohio Edison, about a 15 percent reduction. Thus, it is inaccurate for appellants to imply, if not state, that the approved 9.07 percent rate generates more revenue than the 8.50 percent rate which the utility originally sought. The 8.50 percent figure which the utility believed to be fully compensable is not a meaningful figure because the commission used a different rate base in arriving at the final 9.07 percent rate. What remains meaningful is the [160]*160dollar increase, which was about 67 percent of that requested. This increase has not been shown to be unreasonable or unlawful.

Accordingly, appellants’ first proposition of law is overruled.

As their second proposition, appellants allege that when a public utility raises common, debt and preferred capital in the public markets and further eonsistantly presents a consolidated capital structure to potential investors, the utility has the burden of proof to show why the consolidated capital structure is inappropriate for use in a rate analysis case.

Ohio Edison is the sole shareholder of a Pennsylvania utility. The commission used only the Ohio Corporate capital structure rather than the consolidated structure in calculating the weighted cost of capital. Appellants assert that since Ohio Edison paints a consolidated picture to potential investors, it should be estopped from including only the Ohio structure here.

The commission’s determination was reasonable and lawful. There is a substantially different set of laws for federal and state securities regulation and for ratemaking in Ohio.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Application of Alamo Solar I, L.L.C.
2023 Ohio 3778 (Ohio Supreme Court, 2023)
In re Application of Ohio Edison Co. (Slip Opinion)
2019 Ohio 2401 (Ohio Supreme Court, 2019)
Ohio Consumers' Counsel v. Public Utilities Commission
114 Ohio St. 3d 340 (Ohio Supreme Court, 2007)
City of Reading v. Public Utilities Commission
109 Ohio St. 3d 193 (Ohio Supreme Court, 2006)
AK Steel Corp. v. Pub. Util. Comm.
2002 Ohio 1735 (Ohio Supreme Court, 2002)
AK Steel Corp. v. Public Utilities Commission
95 Ohio St. 3d 81 (Ohio Supreme Court, 2002)
Kentucky American Water Co. v. Commonwealth
847 S.W.2d 737 (Kentucky Supreme Court, 1993)
Myers v. Public Utilities Commission
595 N.E.2d 873 (Ohio Supreme Court, 1992)
Myers v. Pub. Util. Comm.
1992 Ohio 135 (Ohio Supreme Court, 1992)
Office of Consumers' Counsel v. Public Utilities Commission
64 Ohio St. 3d 123 (Ohio Supreme Court, 1992)
Consumers' Counsel v. Pub. Util. Comm.
1992 Ohio 122 (Ohio Supreme Court, 1992)
Industrial Energy Consumers v. Public Utilities Commission
589 N.E.2d 1289 (Ohio Supreme Court, 1992)
Ohio Edison Co. v. Public Utilities Commission
589 N.E.2d 1292 (Ohio Supreme Court, 1992)
Attorney General v. New Mexico Public Service Commission
808 P.2d 606 (New Mexico Supreme Court, 1991)
Atwood Resources, Inc. v. Public Utilities Commission
538 N.E.2d 1049 (Ohio Supreme Court, 1989)
Senior Citizens Coalition v. Public Utilities Commission
433 N.E.2d 583 (Ohio Supreme Court, 1982)
Ohio-American Water Co. v. Public Utilities Commission
428 N.E.2d 860 (Ohio Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
378 N.E.2d 480, 55 Ohio St. 2d 155, 9 Ohio Op. 3d 122, 1978 Ohio LEXIS 632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-akron-v-public-utilities-commission-ohio-1978.