City Life Dev., Inc. v. Praxus Group, Inc., 88221 (5-3-2007)

2007 Ohio 2114
CourtOhio Court of Appeals
DecidedMay 3, 2007
DocketNo. 88221.
StatusPublished
Cited by2 cases

This text of 2007 Ohio 2114 (City Life Dev., Inc. v. Praxus Group, Inc., 88221 (5-3-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City Life Dev., Inc. v. Praxus Group, Inc., 88221 (5-3-2007), 2007 Ohio 2114 (Ohio Ct. App. 2007).

Opinion

JOURNAL ENTRY AND OPINION *Page 3
{¶ 1} Plaintiff City Life Development, Inc. ("City Life") appeals from the decision of the trial court that entered judgment for defendant Praxus and awarded it $32,217.73 on its counterclaim for breach of contract. For the reasons set forth below, we affirm.

{¶ 2} On September 19, 2005, City Life, a developer and general contractor, filed suit against Praxus, a subcontractor who installed Hardie Board, a cement product, at Kings Terrace II North Building. In relevant part, City Life alleged that Praxus failed to pay the Hardie Board supplier and that an affidavit for mechanic's lien in the amount of $39,966.71 was placed on the property. City Life further alleged that it sustained losses for delays of the project and for slander of title and sought damages in the amount of $75,000 against Praxus. Praxus filed an answer denying liability and also set forth a counterclaim in which it alleged that City Life had breached the parties' contract for labor and materials.

{¶ 3} The matter proceeded to trial on April 10, 2006. City Life presented testimony from City's Life's president John Rocco and foreman Daril Paukner. Rocco testified that the Phase II project consists of two residential buildings with a total of nine units. Rocco determined that the material to be used for the siding and trim for Phase II would be Hardie Board, a cement product. Bedrock Construction installed the siding and trim on the south building. Rocco sought a different *Page 4 contractor to install the siding and trim on the north building, however, and also obtained bids from Praxus and Hornbeck.

{¶ 4} Rocco selected Praxus and, pursuant to the terms of the parties' agreement, Praxus was to supply labor and materials, i.e, Hardie Board siding and trim throughout the structure, including corners, windows and doors, the frieze board, and the bottom of the building. City Life agreed to pay Praxus $56,341.44, with $8,451.16 as a down payment. Rocco further testified that the blueprints for the building were placed on a website to which Praxus and other contractors had access.

{¶ 5} According to Rocco, any changes were to be in writing and approved by him. He admitted, however, that a provision in the contract states:

{¶ 6} "When discrepancies to cost arise, this document and any subsequent documents and verbal agreements that become part of this project take precedence."

{¶ 7} Rocco subsequently paid the down payment, plus three additional payments of $10,000 as the work progressed through March 2005. In March 2005, Thom Sutton of Praxus informed Rocco that there had been overruns and submitted an invoice for an additional $40,000. At this time, Rocco learned that Fagen's Building Centers Inc. ("Fagen"), the supplier of the Hardie Board and trim, had not been paid and intended to file a mechanic's lien on the property. Rocco insisted that Praxus adhere to the original terms of the contract and Praxus then walked off the *Page 5 job. Fagen subsequently filed the lien, asserting that it was owed $39,966.71 in materials for the project.

{¶ 8} According to Rocco, various items were uncompleted, including the car port ceilings, caulking, and the repair of nail holes. Rocco asserted that he had incurred costs exceeding $16,000 for labor and materials to complete the job. He admitted, however, that some of the receipts he provided to the court contained items unrelated to the Hardie Board siding and trim installation.

{¶ 9} City Life's foreman, Darin Paukner, testified that Rocco was to approve all changes and that they were to be in writing. Praxus never presented Paulkner with any bills and he did not approve any changes. He acknowledged that Thom Sutton of Praxus informed him that he had ordered additional materials for the project but he told Sutton to speak with Rocco about it.

{¶ 10} Praxus's evidence revealed that a drywall contractor, John Mancuso, referred Rocco to Thomas Sutton of Praxus. Sutton made quick calculations of "squares" and informed Rocco that, including labor and materials, it would do the job for $80,000. Rocco stated that this was too high. Mancuso testified that he asked Rocco if he had any information to give Sutton to help him revise his bid and Rocco provided him with Bedrock Construction's bid, which was $47,000. Sutton testified that Rocco asked him to look at Bedrock's bid. Without measuring the structure, Sutton reviewed the quantities listed in the Bedrock bid then lowered his own bid to $56,341.44, but he informed Rocco that he believed that the quantities listed in the *Page 6 Bedrock bid were insufficient. Sutton acknowledged, however, that his contract did not list the quantities needed for each required item of siding and that the contract states that he reviewed the architectural drawings in calculating his bid.

{¶ 11} Sutton next established that he sought a down payment of approximately $8,000 to begin the job, but Raymond Rocco, another principal John Rocco's father, would not agree, explaining that the bank requested that he first pay materials suppliers then pay for labor. John Rocco rejected both the down payment request and Raymond Rocco's proposed payment for materials first, but eventually paid $8,451.16 as a down payment, and later made three additional payments of $10,000. By February 2005, Praxus needed to order additional materials. John Rocco verbally assented but it was further agreed that Praxus would use materials left from the construction of the south building. Later, John Rocco asked the architect to determine the quantities of siding needed and, although the architect did not list each item that the job required, many of his calculations were comparable to the amounts that Sutton determined were needed once the job was underway, and substantially less than the amounts computed by Bedrock.

{¶ 12} Sutton testified that he converted the contract to a "labor and materials" agreement after the dispute over the down payment. He asserted that he was owed $32,217.73 and would then pay the outstanding materials cost of $24,000 from this amount. He further established that he calculates his bids by determining the cost of *Page 7 materials, doubling this to additionally reflect the cost of labor, and adding 10% for error and 10% for profit.

{¶ 13} The trial court subsequently entered judgment in favor of Praxus as to all claims. In relevant part, the trial court found:

{¶ 14} "7. Defendant informed Plaintiff that based on measurements that Defendant had performed, the cost of installing the Hardie Board would be between $80,000 and $85,000.

{¶ 15} "10. Defendant * * * learned of the amount of Hardie Board tentatively needed as a result from this other bid.

{¶ 16} "11. Plaintiff and Defendant subsequently entered into a revised agreement at a price for $56,341.44.

{¶ 17} "12. The agreement * * * failed to mention the specific quantities of material.

{¶ 18} "* * *

{¶ 19} "16. The lien [filed by the supplier of the Hardie Board] is in the amount of $39,966.71, of which Plaintiff currently has paid $16,000 toward the lien's satisfaction.

{¶ 20} "17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Home S. & L. Co. of Youngstown, Ohio v. Norfolk S. Ry. Co.
2012 Ohio 1634 (Ohio Court of Appeals, 2012)
Rylee Ltd. v. Izzard Family Partnership
897 N.E.2d 208 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 2114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-life-dev-inc-v-praxus-group-inc-88221-5-3-2007-ohioctapp-2007.