City Gas Co. v. Florida Public Service Commission

501 So. 2d 580, 12 Fla. L. Weekly 27, 1987 Fla. LEXIS 1389
CourtSupreme Court of Florida
DecidedJanuary 5, 1987
DocketNo. 68283
StatusPublished
Cited by1 cases

This text of 501 So. 2d 580 (City Gas Co. v. Florida Public Service Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City Gas Co. v. Florida Public Service Commission, 501 So. 2d 580, 12 Fla. L. Weekly 27, 1987 Fla. LEXIS 1389 (Fla. 1987).

Opinion

BOYD, Justice.

This cause is before the Court on a petition for review of orders of the Public Service Commission. The orders in question constitute agency action relating to rates and service of utilities providing gas service. Therefore, we have jurisdiction to “review” the orders. Art. V, § 3(b)(2), Fla. Const.1; § 366.10, Fla.Stat. (1985).2 The commission’s action is challenged on the grounds that it was in excess of statutory authority and that the underlying factual determinations were not supported by competent, substantial evidence. We find the arguments without merit and approve the action of the commission.

[582]*582The Dade County Water and Sewer Authority operates a water treatment plant that includes a kiln employed to dry the lime used in the water purification and treatment process. While the kiln was previously powered by another source of fuel, in 1983 the county authority determined to change to natural gas as a source of power for the kiln. As a result of the authority's inquiries and negotiation concerning the provision of natural gas to the facility, petitioner City Gas Company and respondent Miller Gas Company both submitted tariff filings to the Public Service Commission for its approval.3

Both gas companies were already serving customers in the general area of the water plant. Respondent Miller Gas Company was already providing gas service to the water plant itself, such power being used to fuel the plant’s water pumps. The proposed tariff filed by Miller Gas Company established a classification for large-volume users of interruptible service. That filed by City Gas Company proposed a special classification for service to the county government providing a preferred rate to the water treatment plant. Each company filed objections to the tariff proposal filed by the other. The commission consolidated both petitions into one proceeding, held a hearing, and issued Order No. 15268 approving the rate filed by Miller Gas Company and disapproving that filed by City Gas Company. The effect of the commission’s action is that Miller Gas is authorized to provide gas service to the lime kiln at the water treatment plant.

In Order No. 15268 the commission found the following facts:

1) The tariff of each utility contains a map or narrative that purportedly describes the service area in which each utility is obliged to provide natural gas service. Miller’s purported service area is within and completely surrounded by City’s purported service area;
2) The entire Water Plant area, to include the gas-powered water pump presently served by Miller and the lime kiln, is located within Miller’s described service area;
3) Miller is a relatively small utility having (as of December 1984) only 4,822 residential customers, 61 commercial customers and one interruptible customer. The single interruptible customer is the Dade County Water and Sewer Authority Department (WASA), which operates the Water Plant;
4) Miller has provided natural gas service to the Water Plant for over 22 years through a 4" dedicated line. In 1984, 28% of Miller’s total annual sales of 2,293,865 therms were to the WASA Water Plant. The projected combined annual demand of the water pump and lime kiln is between 2,000,000 and 3,000,000 therms;
5) City, with two natural gas sales divisions, is substantially larger than Miller. As of mid-1985, City had 68,840 [583]*583residential customers, 3,734 commercial/industrial customers and 28 interrup-tible customers. For the 12 months ended August, 1985, City had total sales in excess of 72 million therms;
6) WASA desires the lowest cost gas and has requested and received bids from both City and Miller. WASA intends to take service from only one natural gas company for all of its requirements at the Water Plant;
(7) The additional costs for each utility to serve the Water Plant (both lime kiln and water pumps) are:
Miller Gas City Gas
Water Pumps 0 33,000
Lime Kiln 70,475 149,000
Total $70,475
8) In the event City were to serve all the load at the Water Plant, the “stranded [sic] investment” associated with Miller’s existing facilities to serve the WASA water pumps would be a net book value of $7,783.

The commission concluded that the rate submitted by Miller Gas was cost-justified, reasonable, and nondiscriminatory, while that proposed by City Gas was discriminatory and not cost-based. In approving the petition of Miller Gas and denying that of City Gas, the commission concluded “that Miller Gas Company is the appropriate utility to continue providing service to WASA’s water pumps and to provide natural gas service to WASA’s lime kiln when that service is required.”

City Gas filed a motion for reconsideration on the grounds that the commission failed to consider evidence establishing City Gas’s right to serve the lime kiln, failed to give effect to evidence justifying approval of City Gas’s proposed service, and failed to characterize the lime kiln as a separate and distinct new account. The commission denied this motion in Order No. 15511, finding that City Gas did not have a right to serve the lime kiln, that the evidence presented by City Gas concerning cost allocations and discriminatory impact was wanting, and that the lime kiln was not a separate and distinct new account, and even if it were, it would still be more efficient for Miller to serve both the water pumps and the lime kiln than have these services split between the two utilities.

In its petition for review, City Gas presents two arguments: (1) whether the commission abused its discretion by not approving City Gas’s interruptible rate tariff, and (2) whether the commission exceeded its statutory authority by awarding an exclusive service territory to Miller Gas. We reject the arguments presented by City Gas and therefore approve the action of the Public Service Commission.

It is not this Court’s function on review of a decision of the Public Service Commission to re-evaluate the evidence or substitute our judgment on questions of fact. Citizens of Florida v. Public Service Commission, 435 So.2d 784 (Fla.1983). If the commission acted within its authority and there is competent, substantial evidence to support the action, we must approve it. We find that the commission did not abuse its discretion in rejecting City Gas’s petition to provide interruptible gas service to the water treatment plant. In fixing the rates to be charged by public utilities, the commission is authorized to consider, among other things, “the efficiency, sufficiency, and adequacy of the facilities provided and the services rendered; the cost of providing such service and the value of such service to the public; the ability of the utilities to improve such service and facilities; and energy conservation and the efficient use of alternative energy resources.” § 366.041, Fla.Stat. (1985). The commission must also consider “the cost of providing service to the class, as well as the rate history, value of service, and experience of the utility; the consumption and load characteristics of the various classes of customers; and public acceptance of rate structures.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
501 So. 2d 580, 12 Fla. L. Weekly 27, 1987 Fla. LEXIS 1389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-gas-co-v-florida-public-service-commission-fla-1987.