Citizens For An Orderly Energy Policy, Inc. v. Cuomo

159 A.D.2d 141, 559 N.Y.S.2d 381, 1990 N.Y. App. Div. LEXIS 8392
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 12, 1990
StatusPublished
Cited by15 cases

This text of 159 A.D.2d 141 (Citizens For An Orderly Energy Policy, Inc. v. Cuomo) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens For An Orderly Energy Policy, Inc. v. Cuomo, 159 A.D.2d 141, 559 N.Y.S.2d 381, 1990 N.Y. App. Div. LEXIS 8392 (N.Y. Ct. App. 1990).

Opinion

OPINION OF THE COURT

Per Curiam.

Petitioners commenced these CPLR article 78 proceedings to challenge determinations by respondents Governor of New York, Long Island Power Authority (hereinafter LIPA), Power [146]*146Authority of the State of New York (hereinafter PASNY), Long Island Lighting Company, Inc. (hereinafter LILCO) and Public Service Commission (hereinafter the PSC) approving or executing agreements involving the closing and decommissioning of the Shoreham Nuclear Power Station in the Town of Brookhaven, Suffolk County. Specifically, petitioners contend that the agreements are in excess of the public respondents’ statutory and constitutional authority and that they were adopted in accordance with improper procedures. The proceedings were commenced by two different sets of petitioners, each of which includes individuals, business groups and interest groups.1 The claims raised in each proceeding are essentially the same, although petitioners in proceeding No. 2 raise additional claims under the State Environmental Quality Review Act (ECL art 8) (hereinafter SEQRA). For convenience, we shall not distinguish among petitioners. Because of the far-reaching social and political ramifications of this dispute and the complicated nature of the case, we shall provide a detailed background.

I. THE LONG ISLAND POWER AUTHORITY ACT

In 1986, the Long Island Power Authority Act (hereinafter the Act) was enacted (L 1986, ch 517). The Act began with the Legislature’s declaration that excessive electricity rates have caused "a serious threat to the economic well-being, health and safety” in the Long Island service area of LILCO, an investor-owned utility servicing Suffolk, Nassau and part of Queens Counties (Public Authorities Law § 1020-a; see, Public Authorities Law § 1020-b [10], [17]).1 LILCO’s investment in Shoreham specifically was declared "imprudent” and the cause of "significant rate increases” (Public Authorities Law § 1020-a). Shoreham’s ability to operate was questioned, as was its ability to provide sufficient electricity if it does operate (see, § 1020-a). For these and other reasons, the Legislature declared that "a situation threatening the economy, health and safety exists in the service area” (§ 1020-a). To ensure an adequate, reliable and efficient economic electrical supply, to retain business and to attract new business, the Legislature declared the situation to be a matter of State concern under NY Constitution, article IX, § 3 (a) (3) (see, § 1020-a).

The Legislature found that the situation "best can be dealt [147]*147with by replacing [LILCO] with a publicly owned power authority” (Public Authorities Law § 1020-a) and created LIPA as a political subdivision of the State to be operated on a nonprofit basis (see, Public Authorities Law § 1020-c [1], [3]). LIPA is authorized to acquire LILCO’s securities or assets through negotiated agreement, tender offer or eminent domain (see, Public Authorities Law § 1020-h). It is specifically empowered to acquire "all or any part of the securities or assets of LILCO” provided that it determines that "the rates projected to be charged after such acquisition and for such reasonable period of time as [LIPA] may determine will not be higher than the rates projected to be charged by LILCO during such period if such acquisition had not occurred” (Public Authorities Law § 1020-h [2]).

Under the Act, LIPA must close and decommission Shore-ham and consider possible alternative uses "[a]s soon as practicable after [it] has acquired sufficient shares of LILCO stock to do so or after it has acquired all the property of LILCO” (Public Authorities Law § 1020-h [9]). The Act further prohibits LIPA from constructing or operating a nuclear power plant in the service area (see, Public Authorities Law § 1020-t), although it has power "to determine the location, type, size, construction, lease, purchase, ownership, acquisition, use and operation of any generating, transmission or other related facility” (Public Authorities Law § 1020-g [c]), and "[t]o proceed with the physical construction or completion of any generating, transmission or related facility” (Public Authorities Law § 1020-g [d]). Since the Act and this resulting controversy centers largely around Shoreham, it is appropriate to consider this facility in some detail.

II. SHOREHAM

The Shoreham Nuclear Power Station is an 809-megawatt nuclear-powered electricity generating facility on the north shore of Long Island. It initially was proposed by LILCO in 1965 to help meet substantially increasing electricity demand in the burgeoning New York City suburbs on Long Island. First conceived of as a 540-megawatt nuclear reactor, Shore-ham was to cost $124 million and be operational in 1973. Throughout the 1960’s and 1970’s, construction delays, some with legal origins and others caused by labor, management or construction problems, occurred so that by 1979 the PSC had commenced a proceeding to investigate whether the cost of Shoreham had been incurred prudently. By this time, Shore-[148]*148ham’s cost had exceeded $2 billion with a completion date sometime in the early 1980’s (see generally, Matter of Long Is. Light. Co. v Public Serv. Commn., 134 AD2d 135).

In 1979, an accident involving Unit 2 at the Three Mile Island Nuclear Power Station in Pennsylvania occurred. This incident served to raise public consciousness about nuclear power safety. In response, stringent emergency plan requirements were imposed as part of the licensing procedure by the Nuclear Regulatory Commission (hereinafter the NRC) for nuclear-powered plants (Pub L 96-295, 94 US Stat 780). Concerned about the ability to meet these, or even any, emergency plan requirements, the Governor and Suffolk County have not assisted LILCO in devising or presenting an emergency plan since 1983 and this controversy over the plan continued throughout the 1980’s while construction continued (see, e.g., Cuomo v Long Is. Light. Co., 71 NY2d 349). Further delays resulting from construction problems occurred throughout the early 1980’s but, by 1984, Shoreham was substantially completed. By 1986, preliminary licenses for Shoreham’s operation were authorized by the NRC despite the Governor’s opposition (see, Cuomo v United States Nuclear Regulatory Commn., 772 F2d 972). The emergency plan remained essentially the only impediment to Shoreham’s full operation. By this time, Shoreham had cost almost $5 billion with carrying costs of some $30 million per month. LILCO’s financial condition deteriorated throughout this period.

The licensing process continued and, in April 1989, following protracted, detailed and hotly contested administrative hearings (see, e.g., Matter of Long Is. Light. Co. [Shoreham Nuclear Power Sta., Unit 1] 29 NRC 211), the NRC granted LILCO a full operating license for Shoreham. By the time these proceedings were commenced shortly after issuance of the license, Shoreham costs had totaled some $5.5 billion. During these latter phases of the controversy and following enactment of the Act, LIPA began to pursue a takeover of LILCO and acquisition of its assets. This phase of these proceedings will now be addressed.

III. THE ACQUISITION PROCESS

Following enactment of the Act, LIPA apparently commenced a tender offer in an attempt to acquire control of LILCO. This effort was unsuccessful.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NYC C.L.A.S.H., Inc. v. New York State Office of Parks, Recreation & Historic Preservation
125 A.D.3d 105 (Appellate Division of the Supreme Court of New York, 2014)
Bryan v. Hammons
173 Misc. 2d 894 (New York Supreme Court, 1997)
Suffolk County Department of Public Works v. Public Service Commission
229 A.D.2d 652 (Appellate Division of the Supreme Court of New York, 1996)
Bruno v. Recore
227 A.D.2d 709 (Appellate Division of the Supreme Court of New York, 1996)
In re Wabash Valley Power Ass'n
72 F.3d 1305 (Seventh Circuit, 1995)
Long Island Lighting Co. v. Assessor for Brookhaven
202 A.D.2d 32 (Appellate Division of the Supreme Court of New York, 1994)
City of Yonkers v. County of Westchester
183 A.D.2d 823 (Appellate Division of the Supreme Court of New York, 1992)
Long Island Lighting Co. v. Long Island Power Authority
177 A.D.2d 686 (Appellate Division of the Supreme Court of New York, 1991)
CITIZENS FOR ENERGY v. Cuomo
78 N.Y.2d 398 (New York Court of Appeals, 1991)
Citizens for an Orderly Energy Policy, Inc. v. Cuomo
582 N.E.2d 568 (New York Court of Appeals, 1991)
Multiple Intervenors v. Public Service Commission of the State
166 A.D.2d 140 (Appellate Division of the Supreme Court of New York, 1991)
City of Ithaca v. Tompkins County Board of Representatives
164 A.D.2d 726 (Appellate Division of the Supreme Court of New York, 1991)
Nassau Suffolk Contractor's Ass'n v. Public Service Commission
163 A.D.2d 700 (Appellate Division of the Supreme Court of New York, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
159 A.D.2d 141, 559 N.Y.S.2d 381, 1990 N.Y. App. Div. LEXIS 8392, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-for-an-orderly-energy-policy-inc-v-cuomo-nyappdiv-1990.