Citizens First National Bank v. Board of County Commissioners

267 P. 12, 126 Kan. 90, 1928 Kan. LEXIS 26
CourtSupreme Court of Kansas
DecidedMay 5, 1928
DocketNo. 28,049
StatusPublished
Cited by3 cases

This text of 267 P. 12 (Citizens First National Bank v. Board of County Commissioners) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens First National Bank v. Board of County Commissioners, 267 P. 12, 126 Kan. 90, 1928 Kan. LEXIS 26 (kan 1928).

Opinion

[91]*91The opinion of the court was delivered by

Hutchison, J.:

This action involves the question of priority of right to the balance of funds due a contractor from a county for building a road, as between two assignees of such funds and one furnishing labor and material. Two actions were consolidated and tried together by agreement in the district court. The first was by the Citizens First National Bank, of Independence, against the board of county commissioners of Jefferson county to recover from the county the balance due J. K. Shinn on a road-building contract by virtue of an assignment by Shinn to the bank of all sums due or to become due and payable to him under such contract. The other action was brought by Land & Skilbred against Shinn, the board of county commissioners of Jefferson county, the iEtna Casualty and Surety Company, surety on the bond of the contractor, and the county clerk and county treasurer of Jefferson county, to collect for material furnished and labor performed in connection with the construction of the road at the request of the contractor. The first suit was commenced May 17, 1926, and the other September 10, 1926. All defendants except Shinn appeared and answered, the surety company on October 7, 1926, and the board of county commissioners, the county clerk, and the county treasurer on February 7, 1927. The State Bank of Oskaloosa, by leave of court, filed an interplea January 24, 1927. The consolidated case was tried to the court without a jury, findings of fact and conclusions of law were made, and judgment was rendered against the plaintiff bank and in favor of the other litigants, from which judgment the plaintiff bank appeals.

The contract for constructing the road was let to Shinn on May 17, 1924. His surety bond was given the same day. On July 24, 1924, Shinn, on the strength of such contract, borrowed $13,500 from the appellant bank and assigned to it all sums of money due or to become due and payable to him by virtue of such contract, representing that he needed the amount borrowed to pay for material and labor on the project. This amount was placed to his checking account, as were payments on estimates from time to time to the extent of $100,000 or more, none of which was applied to the payment of the amount borrowed. The assignment was filed with the county board and indorsed by the chairman and county clerk with the county seal affixed. The balance due the contractor from the county at the completion of the contract was $13,311.54, and [92]*92this is the amount for which the plaintiff bank prays judgment against the county.

Shortly before the final settlement was made, Shinn arranged with the State Bank of Oskaloosa for a loan for the purpose of paying all claims for labor and material, and directed the county to deliver to the State Bank of Oskaloosa the warrant when issued. This loan amounted to $3,682.50, and was found by the trial court to have been entirely used- in paying labor and material claims on the road project. Because of the conflicting demands of the two banks for the final warrant, the Oskaloosa bank indemnified the county and was given the warrant for $13,311.54. It took out its $3,682.50 and, under instructions from the county, sent the balance to the plaintiff bank, which returned it, claiming to be entitled to the whole of the final payment under its assignment. It thus reached the county treasurer and is still in his hands. The claim of Land & Skilbred seemed to have been overlooked, hence their suit. The court found they were entitled to recover $5,879.61 for material and labor that went into the road project. The trial court directed that the balance of less than $4,000 should be paid by the county to the plaintiff bank, that the surety company recover its costs, and that the county pay all the costs. The court also found that the evidence does not show that any part of the funds loaned Shinn by the plaintiff bank was used by him for the purpose of paying for labor or material used in the construction of the road; also that the concrete work on the project'was completed in December, 1925, and the project was otherwise completed at that time except for the placing and painting of certain guard rails thereon, and that such work was completed March 24, 1926.

Appellant raises the question of the statute of limitations as to the claim of Land & Skilbred and those alleged to be contained within the interplea of the State Bank of Oskaloosa, because the petition of the former and the interplea of the latter were filed more than six months after the completion of the work. (R. S. 60-1414.) Appellant urges that some of the evidence shows it was only the repainting of the guard rails that was done after December. Regardless of the amount of work done, the matter is determined by the fact of whether the unfinished work was a part of the original contract, necessary to be done to complete the job and comply with the requirements of that contract. (Badger v. Parker, 85 Kan. 134, 116 Pac. 242; Dickey v. Guaranty Co., 107 Kan. 605, 193 Pac. 346; Sonner v. Mollohan, 112 Kan. 148, 210 Pac. 649; White Lumber Co. [93]*93v. Fulton, Adm’r, 116 Kan. 694, 229 Pac. 363; Sash & Sales Co. v. Early et al., 117 Kan. 425, 232 Pac. 232.) There is no question here of any subsequent contract. It was simply a matter of com•pleting an unfinished part of the original and only contract, and the statute does not commence to run until the unfinished portion thereof is completed, which in this case, by the evidence and findings, is March 24, 1926.

“Where, even after the contract is substantially completed, claimant does further work or furnishes further material which is necessary for the proper performance of his contract, and this is done in good faith, at the request of the owner or his agent or architect, or in the case of a subcontractor at the request of the contractor, or for the purpose of fully completing the contract, and not merely for the purpose of fixing a later date from which to compute the time for filing the lien claim or statement, or as a gratuity or act of friendly accommodation, the period for filing the lien will run from the doing of such work or the furnishing of such materials, regardless of the value thereof, at least where there are no intervening rights.” (40 C. J. 204.)

The action of Land & Skilbred was commenced September 10, 1926, which was less than six months from March 24, 1926. If the interplea of the Oskaloosa bank was the first assertion of the claims mentioned therein against the county, the interplea would not be within the required time, but these claims were, by direction of the .contractor, asserted by the Oskaloosa bank before the county board on May 4, 1926, and allowed and paid by the board at that time. The interplea simply related such assertion and allowance to the court for its confirmation and approval.

Reference is made in the findings and one of the briefs to a possible defect in the assignment by the contractor to the plaintiff bank, but the decision in this case does not hinge upon that point. So, regardless of that suggested defect, we shall for this case consider the assignment to the Citizens First National Bank as good and valid — such an assignment as would have entitled it to hold any of the funds coming into its hands thereunder. But the plaintiff bank is here claiming a right to the recovery of such funds from the county as against the claims of the laborers and materialmen, directly and indirectly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ottawa Plumbing, Heating & Air Conditioning, Inc. v. Moore
372 P.2d 1011 (Supreme Court of Kansas, 1962)
OTTAWA PLUMBING, HEATING & AIR CONDITIONING CO v. Moore
372 P.2d 1011 (Supreme Court of Kansas, 1962)
W. S. Dickey Clay Manufacturing Co. v. Snyder
23 P.2d 592 (Supreme Court of Kansas, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
267 P. 12, 126 Kan. 90, 1928 Kan. LEXIS 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-first-national-bank-v-board-of-county-commissioners-kan-1928.