Citizens Awareness Network, Inc. v. U.S. Nuclear Regulatory Commission

854 F. Supp. 16, 38 ERC (BNA) 1929, 1994 U.S. Dist. LEXIS 6904, 1994 WL 227317
CourtDistrict Court, D. Massachusetts
DecidedMay 20, 1994
DocketCiv. A. No. 94-30071-MAP
StatusPublished
Cited by1 cases

This text of 854 F. Supp. 16 (Citizens Awareness Network, Inc. v. U.S. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens Awareness Network, Inc. v. U.S. Nuclear Regulatory Commission, 854 F. Supp. 16, 38 ERC (BNA) 1929, 1994 U.S. Dist. LEXIS 6904, 1994 WL 227317 (D. Mass. 1994).

Opinion

MEMORANDUM REGARDING PLAINTIFF’S MOTION FOR A PRELIMINARY INJUNCTION

(Docket No. 06)

PONSOR, District Judge.

I. INTRODUCTION.

This complaint arises from the Nuclear Regulatory Commission’s oversight of the decommissioning of the Yankee Rowe Nuclear Power Plant, one of the first nuclear facilities to be shut down in the United States. Plaintiff, Citizens Awareness Network (“CAN”), alleges that the Nuclear Regulatory Commission (“NRC”) violated the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321 et seq. and related federal regulations, by failing to conduct an environmental impact study (“EIS”) prior to NRC approval of Yankee Rowe’s early component removal plan. Implementation of this plan, CAN maintains, will result in the removal of approximately 90% of the nuclear waste from Yankee Rowe’s facility without any independent assessment of the risks to the environment, particularly the local community.

CAN has requested issuance of a preliminary injunction against the NRC, which would stop further implementation of Yankee Rowe’s early component removal plan and enjoin the disassembly and shipment of nuclear waste to a treatment facility in Barn-well, South Carolina. The NRC denies that it violated NEPA and, more importantly, asserts that this court lacks subject matter jurisdiction to hear this claim. Defendant claims that the Hobbs Act, 28 U.S.C. §§ 2341 et seq., requires that plaintiffs claims be heard by the court of appeals.

[17]*17 II. FACTS.

The relevant facts are as follows.

In February of 1992, Yankee Rowe Nuclear Power Station (“Yankee Rowe”), located in Rowe, Massachusetts, notified the NRC of its decision permanently to close down its facility. By August 1992, NRC amended Yankee Rowe’s operating license to a possession only license (“POL”). Federal regulations require Yankee to submit a decommissioning plan within two years of cessation of its operations. 10 CFR 50.82.

Prior to January of 1993, the NRC held the position that the decommissioning of a nuclear plant could not begin before the NRC formally approved the decommissioning plan. It is undisputed that this approval process would include NEPA review and preparation of an EIS. In January of 1993, the NRC changed its position regarding the permitted scope of a licensee’s decommissioning activities prior to NRC’s final approval of a decommissioning plan. According to the NRC’s current interpretation of its regulations, Yankee is entitled under the terms of its POL and without further NRC approval, to undertake any decommissioning activity that does not (a) foreclose the release of the site for possible unrestricted use, (b) significantly increase decommissioning costs, (c) cause any significant environmental impact not previously reviewed, or (d) violate the terms of the licensee’s existing license or 10 CFR § 50.59.

In February of 1993, Yankee Rowe requested NRC approval of early removal of nuclear plant components from its facility. NRC met with Yankee Rowe and members of CAN in June of 1993 to discuss various aspects of the early decommissioning plan. In July of 1993, NRC informed Yankee Rowe that its possession only license permitted the early component removal plan and that Yankee’s license did not need to be amended to carry out the plan. The upshot of this change in policy was that Yankee Rowe, through its early component removal plan, would be permitted to carry out a large part of the physical work of decommissioning before the final decommissioning plan was formally approved by the NRC.

On three separate occasions, members of CAN requested formal hearings to discuss its safety and environmental concerns regarding Yankee’s early component removal plan. On March 31, 1994, NRC issued an order denying CAN’S request for an adjudicatory hearing, reasoning that CAN was not entitled to an adjudicatory hearing. According to the Commission, Yankee’s early component removal plan was being performed pursuant to 10 CFR § 50.59, which permits a licensee to make changes in its facility as long as the changes do not present “an unreviewed safety question.” The Commission concluded that, in removing the nuclear waste from its facility, Yankee Rowe was properly acting under its possession only license which permitted transportation of certain hazardous materials without prior NRC approval. As such, the NRC reasoned, CAN was not entitled to an adjudicatory hearing.

On the same day that CAN received the letter from the NRC denying their request for a hearing, it filed suit in this court seeking to stop Yankee’s early component removal plan until NRC complies with NEPA and performs an appropriate plan EIS.

III. DISCUSSION.

The Hobbs Act provides, in part, that the court of appeals has exclusive jurisdiction to set aside, suspend, (in whole or in part), or determine the validity of, all final orders of the NRC under 42 U.S.C. § 2239. 28 U.S.C. § 2342(4). Section 2239, in turn, makes reviewable “the granting, suspending, revoking, or amending of any license.” 42 U.S.C. § 2239. In Florida Power & Light v. Lotion, 470 U.S. 729, 105 S.Ct. 1598, 84 L.Ed.2d 643 (1985), the Supreme Court broadly interpreted this jurisdictional grant, holding that decisions that are ancillary to licensing decisions may be challenged only in the court of appeals.

In this case, CAN is, in essence, challenging a final order by the NRC in a licensing or related proceeding. As such, the court of appeals, not the district court, is the appropriate forum to address the merits of plaintiffs claims.

On March 31, 1994, the NRC sent CAN representative Frederick Katz a letter in[18]*18forming him that CAN was not entitled to receive an adjudicatory hearing regarding the activities at Yankee Rowe. See Defendant’s Exhibit 3. In this letter, the NRC explained that the Commission had issued a decision denying a request by a similar group, Environmentalist, Inc., for an adjudicatory hearing regarding ongoing component removal activities at Yankee Rowe. The letter continued

The Commission has now issued a decision in response to that petition. As you can see from that decision, a copy of which is enclosed for your review, the Commission has ruled that the Component Removal Program (“CRP”) at Yankee NPS does not involve any activity that requires the offer of an adjudicatory hearing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
854 F. Supp. 16, 38 ERC (BNA) 1929, 1994 U.S. Dist. LEXIS 6904, 1994 WL 227317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-awareness-network-inc-v-us-nuclear-regulatory-commission-mad-1994.