CITIROOF, COPR. v. Tech Contracting Co.

860 A.2d 425, 159 Md. App. 578, 2004 Md. App. LEXIS 172
CourtCourt of Special Appeals of Maryland
DecidedOctober 29, 2004
Docket2211, September Term, 2003
StatusPublished
Cited by7 cases

This text of 860 A.2d 425 (CITIROOF, COPR. v. Tech Contracting Co.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CITIROOF, COPR. v. Tech Contracting Co., 860 A.2d 425, 159 Md. App. 578, 2004 Md. App. LEXIS 172 (Md. Ct. App. 2004).

Opinion

SHARER, J.

In this dispute between a general contractor and a potential subcontractor, judgment was entered in favor of the former, appellee Tech Contracting Company, Inc., (“Tech”) against the latter, Citiroof Corporation, (“Citiroof’) appellant. The judgment, entered following a bench trial in the Circuit Court for Baltimore City, has prompted this appeal, in which Citiroof presents for our review one question which, as slightly recast, is:

Was the circuit court clearly erroneous in finding that Tech
had proven the elements of detrimental reliance?
We find no error, and shall affirm.

Factual History

In March 2000, Tech, a general contractor, in response to a request for bids, submitted a bid to Baltimore County for construction of the Winfield Police Athletic League Center project (“the project”). As part of the process of calculating prices and assembling its bid, Tech solicited proposals from potential subcontractors. In that context, Tech received bids for the roofing portion of the project, including a bid from appellant Citiroof, a contracting company that performs both general contracting and subcontracting services.

*582 At the time, Paul Welch was Citiroofs project estimator. Welch received plans and partial specifications for two similar Baltimore County construction projects, one of which was the project. That information was supplied not by Tech, but by another general contractor who was also a potential bidder. Welch did not have plans and specifications for the entire project, only the specifications for the roofing and a roof plan without dimensions. Based upon the information available to him, Welch, on March 16, 2000, faxed unsolicited bids to a number of general contractors, including Tech. Citiroofs price for the work was $32,200, which, as we shall discuss, was in error. Because the original bid day was postponed by Baltimore County, Tech did not immediately look closely at Citiroofs bid until the rescheduled bid day, March 21, 2000.

On March 21, 2000, Tech received a second bid of $62,803 for the roofing subcontract work from Jottan, Inc. Richard Chapolini, 1 Tech’s president, testified that he realized, given the difference between the two prices, that “somebody has got to be right, and somebody has got to be wrong [sic].” While Chapolini recognized that one of the bids was “grossly” wrong, he did not know then whether it was Citiroofs or Jottan’s.

Chapolini telephoned Welch and informed him that Citiroofs price was “rather low.” The only factor affecting the price that was discussed between Chapolini and Welch during that call was the wage scale. Square footage was not discussed. Until that time, Welch was unaware that the project was subject to a Davis-Bacon wage scale. 2 When informed of this fact, Welch recalculated the price to include the higher *583 wage rates. He then faxed Citiroofs amended bid to Tech on March 21, 2000, increasing the price by $6,700.

Chapolini then asked Welch if he “had everything included in the bid .. . and [if he] was comfortable with it ... [because] if his price held up,” Tech planned to use it in its bid to the owner. By “held up,” Chapolini confirmed that he meant, if Citiroof was the lowest bidder, Tech would incorporate Citiroofs price into its bid. Welch testified that during this same conversation, he asked Chapolini how Citiroofs revised bid stood in comparison to the other roof subcontract bids. Chapolini responded that Citiroofs revised bid was “more in line,” When Tech’s bid was submitted to the owner, it included the price quoted by Citiroof for the roofing phase of the project. Chapolini testified that, based upon Welch’s assurance that he was “comfortable” with Citiroofs figures, Tech used Citiroofs price.

The Means Construction Guide is a construction industry publication that is used by contractors to estimate prices for construction projects. Witnesses for both parties testified to their general reliance on the Means Guide. Chapolini told the court that, after the Tech bid was submitted to Baltimore County, he consulted the Means Guide to reconcile the large disparity between the Jottan and Citiroof bid numbers. In doing so, he determined that Jottan’s final price was “fair and reasonable.”

Timothy Maloney, president of Citiroof, was qualified as an expert 3 and told the court that a reasonably prudent contractor, upon receiving two bids with a disparity of such magnitude, should contact the subcontractors to advise of the disparity. The discussion should include the dominant unit measure of square footage and other aspects of the submitted price. *584 He also testified that the general contractor ought to obtain additional bids, or if time did not permit such verification or substantiation, the exceptionally low bid should be disregarded. Maloney also provided an opinion that the disparity would indicate to a reasonably prudent general contractor that there was an error in square footage used in the calculation of the low bid.

Chapolini testified that on March 22, the day after submitting Tech’s bid to the County, Welch came to his (Chapolini’s) office. 4 He recounted the visit:

Well, he obviously was anxious to know what was going to happen with the bid. I told him that we were the low bidder, but that’s really about all we knew at that point. There’s so many variables in awarding a contract that we have to wait and see exactly what the County is going to do .... all of the documents have to be reviewed by their Contracts Administration Department, and we typically don’t comment on a bid until we get some positive reaction from the owner.

At that time, Chapolini said nothing about awarding the contract to Citiroof. On March 28, 2000, Tech received notification from Baltimore County that its bid was low and that it would be awarded the contract. Tech faxed a standard “Letter of Intent” to Citiroof, dated April 19, 2000, stating:

This letter of intent will be subject to your successful execution of our contract which will be forwarded to you as soon as possible. This letter of intent supersedes all previous contracts and or proposals and does not include any exclusions, terms or conditions of any previous contracts or proposal otherwise indicated.

On April 25, 2000, at Citiroof s request, Tech forwarded a full set of drawings and specifications to Citiroof. Although Citiroof received the drawings and plans on April 25, 2000, they were not reviewed until just before the final submittals were due on May 8,2000.

*585 It was that review that caused Welch to realize that the roof plan upon which he calculated Citiroof s bids was “half sized.” 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kantsevoy v. Lumenr LLC
301 F. Supp. 3d 577 (D. Maryland, 2018)
Wm. T. Burnett Holding LLC v. Berg Bros. Co.
175 A.3d 876 (Court of Special Appeals of Maryland, 2017)
200 North Gilmor, LLC v. Capital One, National Ass'n
863 F. Supp. 2d 480 (D. Maryland, 2012)
Kuechler v. Peoples Bank
602 F. Supp. 2d 625 (D. Maryland, 2009)
Nationwide Mutual Insurance v. Regency Furniture, Inc.
963 A.2d 253 (Court of Special Appeals of Maryland, 2009)
Scott v. State
494 A.2d 992 (Court of Special Appeals of Maryland, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
860 A.2d 425, 159 Md. App. 578, 2004 Md. App. LEXIS 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citiroof-copr-v-tech-contracting-co-mdctspecapp-2004.