BAZELON, Chief Judge:
Petitioners operate municipal gas distribution systems which purchase their entire supply of natural gas from Panhandle Eastern Pipeline Company (Panhandle). They contest the issuance of a certificate of public convenience and necessity to Pan Eastern Exploration Company (Pan Eastern), a wholly owned subsidiary of Panhandle, under section 7 of the Natural Gas Act.
Granted September 20, 1972, the certificate authorized Pan Eastern to sell gas under contract to Panhandle, from producing properties transferred to it by Panhandle,
at applicable area rates. Consistent with existing FPC policy with respect to production facilities owned or controlled by interstate pipelines, the gas from these
properties had previously been valued for sale on a cost-of-service basis.
The certificate was conditioned to require Pan Eastern to spend the excess over cost-of-service rates, some $43,609,-250 over a five-year period, in the development of new gas reserves.
This amount was to be spent over and above amounts already projected by Panhandle for expenditure on exploration and development. Assuming an average exploration and development cost of 11 cents per Mcf, the Commission calculated that Panhandle’s scheme would yield 400,000,-000 Mcf of gas that would not otherwise have been available. The Panhandle system was to absorb the reserves generated by this spin-off scheme, and the certificate provided for refunds to Panhandle’s customers, at the rate of 11 cents per Mcf, for each Mcf by which Pan Eastern’s effort fell short of the 400,-000,000 mark. Pan Eastern was also required, by the terms of the Commission’s order, to undertake further exploration and development “to the extent of at least 3 cents per Mcf of recoverable gas reserves and 50 cents per barrel of recoverable oil reserves found as a result of this proposal.”
The certificate was limited to five years, at the end of which “rates for gas from leases acquired on or before October 7, 1969, will be determined on a cost of service basis, in the absence of a showing by Applicants that some other method of determination is in the public interest.”
I.
There is some dispute over the standard which should govern our review of the Commission’s action. The Government and intervenor Panhandle argue strenuously that because this case involves the issuance of a certificate under section 7, the appropriate standard is the “public convenience and necessity” rather than the more stringent “just and reasonable” test applicable in rate-making proceedings under sections 4 and 5 of the Act. We think this contention is substantially foreclosed by Atlantic Refining Co. v. Public Service Commission of New York (CATCO),
which strongly suggests that the FPC may not approve under section 7 rates which would not pass muster under section 4.
Our view that the “just and reasonable” standard applies, with whatever force it still retains in the wake of recent Supreme Court decisions,
finds additional support from a review of events leading to the FPC’s decision in this case.
Historically, the Commission has required that pipeline-produced gas be priced to the consumer at cost-of-service. In the course of its
Hugoton-Anadarko Area Rate Proceeding,
the Commission
decided to explore the question of whether gas produced by an interstate pipeline company or its affiliate should be allowed area rate treatment. This inquiry was subsequently severed from the
Hugoton-Anadarko Proceeding
and became the
Pipeline Production Area Rate Proceeding,
Phases I and II. Phase I dealt with the application of area rates to gas produced after the FPC’s decision in the matter, which came on October 7, 1969, and granted area rate treatment to new pipeline-produced gas.
Phase II, which covered gas produced prior to October 7, 1969, was never formally instituted. In June 1972, the FPC terminated Phase II, indicating its intent to determine the appropriate rates for vintage pipe-produced gas on a “company by company” basis.
In the prologue to its opinion in this case, which issued soon afterward in September 1972, the Commission acknowledged that “[t]he applications herein considered represent our first opportunity to implement this new policy.”
This progression makes clear that the Panhandle-Pan Eastern proposal was viewed from the outset as nothing more than a device for revising the applicable rates. And, consistent with this, in its opinion denying rehearing, the FPC acknowledged the relevance of the stricter standard: “we are dealing with an adjustment in rates to a level which has been found by the Commission to be just and reasonable.”
We think it appropriate, under these circumstances, to deal with the order in the terms by which the Commission itself has sought to justify it.
II.
Of course, “just and reasonable” is not self-defining, and it has proven a particularly difficult test with regard to incentive schemes such as the one before us.
We have questioned elsewhere whether those who framed the Natural Gas Act envisioned an alternative to regulation on a traditional cost-of-service basis, which includes a rate of return thought necessary to attract new capital.
But the use of selective rate increases as a functional tool to elicit needed supplies was countenanced by the Supreme Court in the
Permian Basin Area Rate
Cases
and again in Mobil Oil Co. v. FPC.
And
Mobil
made it clear that injections of consumer dollars for this purpose could be drawn from customers relying on supplies already committed to the interstate market. Under the shadow of the nationwide shortage of natural gas, the incentive device has been seized upon increasingly by the FPC and paraded before the courts in a number of guises,
perhaps on the assumption that the courts would not be inclined to reject them all.
Although we continue to view this spectacle with some skepticism, we are inclined to test these incentive schemes somewhat less rigorously after the
Mobil Oil
decision. The Court in
Mobil
Free access — add to your briefcase to read the full text and ask questions with AI
BAZELON, Chief Judge:
Petitioners operate municipal gas distribution systems which purchase their entire supply of natural gas from Panhandle Eastern Pipeline Company (Panhandle). They contest the issuance of a certificate of public convenience and necessity to Pan Eastern Exploration Company (Pan Eastern), a wholly owned subsidiary of Panhandle, under section 7 of the Natural Gas Act.
Granted September 20, 1972, the certificate authorized Pan Eastern to sell gas under contract to Panhandle, from producing properties transferred to it by Panhandle,
at applicable area rates. Consistent with existing FPC policy with respect to production facilities owned or controlled by interstate pipelines, the gas from these
properties had previously been valued for sale on a cost-of-service basis.
The certificate was conditioned to require Pan Eastern to spend the excess over cost-of-service rates, some $43,609,-250 over a five-year period, in the development of new gas reserves.
This amount was to be spent over and above amounts already projected by Panhandle for expenditure on exploration and development. Assuming an average exploration and development cost of 11 cents per Mcf, the Commission calculated that Panhandle’s scheme would yield 400,000,-000 Mcf of gas that would not otherwise have been available. The Panhandle system was to absorb the reserves generated by this spin-off scheme, and the certificate provided for refunds to Panhandle’s customers, at the rate of 11 cents per Mcf, for each Mcf by which Pan Eastern’s effort fell short of the 400,-000,000 mark. Pan Eastern was also required, by the terms of the Commission’s order, to undertake further exploration and development “to the extent of at least 3 cents per Mcf of recoverable gas reserves and 50 cents per barrel of recoverable oil reserves found as a result of this proposal.”
The certificate was limited to five years, at the end of which “rates for gas from leases acquired on or before October 7, 1969, will be determined on a cost of service basis, in the absence of a showing by Applicants that some other method of determination is in the public interest.”
I.
There is some dispute over the standard which should govern our review of the Commission’s action. The Government and intervenor Panhandle argue strenuously that because this case involves the issuance of a certificate under section 7, the appropriate standard is the “public convenience and necessity” rather than the more stringent “just and reasonable” test applicable in rate-making proceedings under sections 4 and 5 of the Act. We think this contention is substantially foreclosed by Atlantic Refining Co. v. Public Service Commission of New York (CATCO),
which strongly suggests that the FPC may not approve under section 7 rates which would not pass muster under section 4.
Our view that the “just and reasonable” standard applies, with whatever force it still retains in the wake of recent Supreme Court decisions,
finds additional support from a review of events leading to the FPC’s decision in this case.
Historically, the Commission has required that pipeline-produced gas be priced to the consumer at cost-of-service. In the course of its
Hugoton-Anadarko Area Rate Proceeding,
the Commission
decided to explore the question of whether gas produced by an interstate pipeline company or its affiliate should be allowed area rate treatment. This inquiry was subsequently severed from the
Hugoton-Anadarko Proceeding
and became the
Pipeline Production Area Rate Proceeding,
Phases I and II. Phase I dealt with the application of area rates to gas produced after the FPC’s decision in the matter, which came on October 7, 1969, and granted area rate treatment to new pipeline-produced gas.
Phase II, which covered gas produced prior to October 7, 1969, was never formally instituted. In June 1972, the FPC terminated Phase II, indicating its intent to determine the appropriate rates for vintage pipe-produced gas on a “company by company” basis.
In the prologue to its opinion in this case, which issued soon afterward in September 1972, the Commission acknowledged that “[t]he applications herein considered represent our first opportunity to implement this new policy.”
This progression makes clear that the Panhandle-Pan Eastern proposal was viewed from the outset as nothing more than a device for revising the applicable rates. And, consistent with this, in its opinion denying rehearing, the FPC acknowledged the relevance of the stricter standard: “we are dealing with an adjustment in rates to a level which has been found by the Commission to be just and reasonable.”
We think it appropriate, under these circumstances, to deal with the order in the terms by which the Commission itself has sought to justify it.
II.
Of course, “just and reasonable” is not self-defining, and it has proven a particularly difficult test with regard to incentive schemes such as the one before us.
We have questioned elsewhere whether those who framed the Natural Gas Act envisioned an alternative to regulation on a traditional cost-of-service basis, which includes a rate of return thought necessary to attract new capital.
But the use of selective rate increases as a functional tool to elicit needed supplies was countenanced by the Supreme Court in the
Permian Basin Area Rate
Cases
and again in Mobil Oil Co. v. FPC.
And
Mobil
made it clear that injections of consumer dollars for this purpose could be drawn from customers relying on supplies already committed to the interstate market. Under the shadow of the nationwide shortage of natural gas, the incentive device has been seized upon increasingly by the FPC and paraded before the courts in a number of guises,
perhaps on the assumption that the courts would not be inclined to reject them all.
Although we continue to view this spectacle with some skepticism, we are inclined to test these incentive schemes somewhat less rigorously after the
Mobil Oil
decision. The Court in
Mobil
was careful to acknowledge the primary responsibility of the courts of appeals in making the “substantial evidence” determination on review of agen-, cy decisions, and since
Mobil,
we have restated our view that this responsibility prevents us from “acquiescing in a charade or a rubber stamping of nonregulation in agency trappings.”
At the same time,
Mobil
outlined a “broad discretion which has been entrusted to the Commission ‘to devise methods of [natural gas] regulation capable of equitably reconciling diverse and conflicting interests,’ and [emphasized] that this discretion must be given particular respect ‘in this time of acute energy shortage.’ ”
If the bars are not down after
Mobil,
the spaces between them are perceptibly wider. With this in mind, we examine the justification for the FPC’s action in this case.
As grounds for approving this spin-off scheme, the Commission found that Panhandle’s reserves had diminished by more than half since 1961 and that the Panhandle system “anticipated deficiencies of about 100 thousand Mcf per day under existing contracts.”
The FPC asserts in its brief, and we do not find it refuted by petitioners, that “even if Pan Eastern were able to dedicate 400,000,000 Mcf of gas reserves, additional amounts of gas would be needed from other exploratory efforts to meet annual requirements.”
In addition to finding a specific need, the FPC also indicated that Panhandle would have to stretch beyond its “financial capabilities” in order to fund a program requiring an equal amount of additional capital by traditional means. Support for this view appears in the testimony of a company consultant who concluded that “reliance upon debt financing for large-scale exploratory efforts is not possible, and that equity financing cannot be considered a solution to the raising of capital for enlarged exploratory programs.”
And petitioners did not present testimony or exhibits to refute this analysis.
We accept the Commission’s premises as based on substantial evidence. But that does not conclude the matter. A more detailed scrutiny is required to ensure that the FPC has given “reasoned consideration” to the shaping of its order in an effort to protect consumers from paying substantially more than necessary to bring forth the needed supplies.
III.
Some perspective on this question is afforded by a comparison of this ease
with MacDonald v. FPC,
which was decided by our court shortly after
Mobil.
In the order under review in
MacDonald,
the Commission had authorized the sale of natural gas by an independent producer at 65% above' applicable area rates, subject to the producer’s agreement to plow back 16.5 million dollars of the excess into new well drilling within the continental United States. Our remand of the case was based on the FPC’s failure to consider the producer’s individual costs in determining that the scheme would not yield “excessive profit returns.”
In the case, of Panhandle, of course, cost data covering the properties transferred to Pan Eastern were relied on as a major factor in determining the scope of the company’s obligation under the scheme. The opinion in
MacDonald
expressed our added concern that there appeared to have been no attempt by the Commission, as there was here, to ensure that
all
the proceeds would be sunk into exploration and development.
And we noted the absence of any requirement in that case that all the gas produced as a result of the new exploration be available to the pipeline whose customers would shoulder the increase, or even that it all be committed to the interstate market.
Full plowback, combined with Panhandle’s preemptive rights to the new gas, gives this case a symmetry which we found lacking in the
MacDonald
case, and produces a much tighter fit between Panhandle’s
quid pro quo
and the purposes for which the Commission acted to grant special relief.
The petitioners contend, nevertheless, that the fit is not tight enough to justify the increase, and that three additional conditions were necessary to bring the plan within a zone of reasonableness. We limit full consideration to two of these, as the third was not brought up before the Commission either in the initial hearings or on petition for rehearing.
Petitioners advocated before the Commission that a
dollar floor be set for . . . exploration and development expenditures unrelated to the Panhandle-Pan Eastern scheme in order to insure that the consumer-contributed capital raised through the spin-off scheme would represent
additional
[exploration and development] expenses — not mere substitute dollars.
The Commission’s order made it clear that commitments under the Pan Eastern spin-off were to be in addition to currently projected programs of exploration and development, which the record indicates are pegged at levels of 10-12
million dollars per year.
The Commission required Pan Eastern to make annual reports, “describing its program of exploration and development, setting forth the new reserves dedicated, and resülts of its financial transactions . .
and it holds out the possibility of action under section 20 of the Natural Gas Act,
should these reports reveal that the company has backed off on its commitment. This machinery, while perhaps not the best, is not plainly inadequate to achieve the Commission’s goals.
Petitioners also argue that the FPC erred in not requiring that the excess revenues generated by the spin-off scheme be repaid to Panhandle’s customers, regardless of whether the 400,000,-000 Mcf goal is reached. In the absence of any such provision, they contend, the 43 million dollars, or at least any portion of it not refunded under the terms of the FPC’s order, amounts to a “windfall” to Panhandle’s stockholders, or a “double recovery.” On rehearing, the Commission dealt with this suggestion as follows:
[W]e would point out that the phrase “consumer-contributed dollars” is not applicable here. Rather, we are here dealing with an adjustment in rates to a level which has been found by the Commission to be just and reasonable. Consequently no “windfall profit” is involved.
This reasoning carries a strong hint of circularity. There is no “windfall profit” involved because the rates are “just and reasonable” without the full refund provision. The rates are “just and reasonable,” in turn, because they promise adequate supplies without “windfall profits.” In treating the issue in this conclusory fashion, the Commission misses the hard questions buried at the root of petitioners’ proposal. As we have seen, a major premise of the Commission’s action was the absence of alternative sources of investment capital. Consistent with this, why aren’t capital-producing payments from customers better conceived of as loans or investments, rather than permanent donations, and allowed to be recouped at some later date? Could Panhandle have lived with other consumer-favoring provisions if full repayment had been imposed? Would the insertion of such a requirement have somehow undermined the overall effectiveness of the plan, as limited by the FPC?
On this last point, Panhandle suggests that a repayment clause of the sort advocated by petitioners would neutralize the existing requirement that Panhandle repay its customers 11 cents for each Mcf by which the program falls short of its goal. The Commission inserted this condition on finding that it
would provide an incentive to maximize its [Pan Eastern’s] effort, as well as insure that Panhandle’s customers will not be incurring a higher rate without receiving a compensatory benefit.
Certainly if Panhandle were required to make refunds regardless of the success of Pan Eastern’s program, the current provision would provide no incentive. But this rationale only breeds further questions: whether the spur in Pan Eastern’s side represented by the current repayment arrangement offers a “compensatory benefit” sufficient to justify the permanent sacrifice of 43 million consumer dollars, or whether the incentive effect might have been achieved in some other way consistent with full refund.
These are questions which only
the Commission can properly address. We conclude that in this aspect of its determinations at least the agency fell short of its responsibility to “ ‘set forth with clarity the grounds for its rejection of opposing views.’ ”
To remand on this ground alone, however, would discount perhaps too harshly a considered effort by the Commission, reflected in the overall contours of its order, to strike a reasonable accommodation between the requirements of the Panhandle system and the interests of its customers. The proposal which Panhandle put before the Commission was already the result of considerable negotiations between Panhandle and its customers, including petitioners.
Even without modification, it offered by the agency’s calculation a cheaper alternative to consumers than suffering further curtailments on the system or importing gas from nonconventional supplies (liquified or synthetic gas).
The proposal did not, however, provide for plowback approximating the entire difference between cost-of-service and area rates.
Nor did it contain a refund requirement of any kind. Nor was it limited to the five years during which Pan Eastern’s exploration and development program was scheduled to run.
These features were inserted by the Commission to increase the benefits per consumer dollar and reduce the risks of failure. The FPC also foreclosed resort by Panhandle to the optional certification procedure provided for in section 2.75 of its regulations, ensuring that the gas discovered as a result of the spin-off would not be sold at rates higher than the applicable area rate.
These adjustments, together with
the substantial evidence supporting the Commission’s underlying determination of the need for a scheme of this sort, are sufficient in our view to bring the Commission’s action within the bounds of its discretion — given the deference which, we are instructed, is to be accorded the agency’s determinations in these times of shortage.
In reaching this result, we are also sensitive that the experiment which the Commission has undertaken here is limited in scope. We are not dealing with an area rate structure, as in the
Texas Gulf Coast Area Rate Cases,
or with a regulation of nationwide applicability, as in Public Service Commission of New York v. FPC.
Only a portion of a single pipeline’s reserves are involved, and the certificate allowing the experiment to go forward is limited to five years, almost half of which has elapsed. During that period the Commission has indicated that it will monitor Pan Eastern’s efforts and their impact on Panhandle’s supply shortage. Prior to a renewal of Pan Eastern’s certificates, it will be in a position to evaluate the results not only against the expectations on which its initial approval was based but also against the performance of pipelines which did not have the benefit of a similar arrangement.
We remain troubled, however, by recent developments in the Commission’s regulatory policy which bring into question even now the continued need for the Panhandle-Pan Eastern plan. Chief among these is the adoption of a national base rate
applicable to new gas produced by pipelines as well as independents.
This order, adopted by the Commission in June 1974, was framed as a response to the “national energy emergency” calculated “to bring forth the requisite supplies to fulfill reasonable demand while protecting ‘the consumer against exploitation at the hands of the natural-gas companies.’ ”
As revised, its practical effort is to double the price which Pan Eastern may charge for its new finds.
The Commission appears to acknowledge that this development may warrant further scrutiny of the Pan Eastern spin-off.
But it may have been reluctant to undertake such scrutiny in formal proceedings while its 1972 orders were under judicial review. Accordingly, we will retain jurisdiction for a period of 90 days for the purpose of allowing the FPC to seek a remand, if so advised, to examine the continued reasonableness of its orders in light of changed circumstances. A remand would also provide an opportunity for
reconsideration of the refund provision proposed by petitioners and rejected by the Commission.
So ordered.