CIT Group/Equipment Financing, Inc. v. ACEC Maine, Inc.

782 F. Supp. 159, 1992 U.S. Dist. LEXIS 848, 1992 WL 10566
CourtDistrict Court, D. Maine
DecidedJanuary 16, 1992
DocketCiv. 90-0304-B
StatusPublished
Cited by1 cases

This text of 782 F. Supp. 159 (CIT Group/Equipment Financing, Inc. v. ACEC Maine, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CIT Group/Equipment Financing, Inc. v. ACEC Maine, Inc., 782 F. Supp. 159, 1992 U.S. Dist. LEXIS 848, 1992 WL 10566 (D. Me. 1992).

Opinion

ORDER AND MEMORANDUM OF DECISION

BRODY, District Judge.

This matter is before the Court on Plaintiff’s Motion for Partial Summary Judgment and the mirror image, Defendants’ Cross Motion for Partial Summary Judgment. The issue before the Court is the Plaintiff’s claim, as secured lender and assignee of a construction contract, for liquidated damages and Defendant’s counterclaim challenging the enforceability of the contract provision.

*160 I. BACKGROUND

On July 12, 1985, Third Party Defendant Down East Peat, L.P. (“Down East”) entered into a contract with Defendants, ACEC-SKG, a consortium consisting of ACEC, S.A. (now, ACEC Union Miniere) and Standardkessel Gellschaft (“SKG”), for the engineering, design, procurement and construction of an electrical generating facility (the “Facility”) in Deblois, Maine. This contract (“Construction Contract”) was amended on Nov. 19, 1985, September 18, 1986, and again on March 17, 1987.

Pursuant to various loan documents and agreements, Plaintiff CIT Group/Equipment Financing Inc. (“CIT”) provided construction and working capital financing to Down East. In all, CIT advanced $55,273,-516.94, none of which has been repaid. In order to secure its obligations to CIT, Down East assigned to CIT, among other things, all its rights, title and interest in the Construction Contract.

Defendants ACEC, S.A., and SKG each undertook to be jointly and severally liable for each obligation under the Construction Contract. On March 16, 1987, ACEC-SKG assigned its interest in the Construction Contract to Defendant ACEC Maine. By this agreement ACEC Maine acquired all the rights and obligations of ACEC-SKG under the Construction Contract. ACECSKG, however, remained liable under the Construction Contract to Down East and its assignee CIT. Both ACEC-SKG and ACEC Maine consented to the assignment of the Construction Contract to CIT as the entity providing financing for the project.

Pursuant to Section 8.2.2 of the Construction Contract, the Contractor was required to conduct certain performance tests one year after the date of Substantial Completion of construction (the “One Year After Test”) to demonstrate the efficiency and reliability of the Facility.

On June 16, 1989 Down East issued a Certificate of Substantial Completion. Nine months later, in what has been described as a highly unusual event, turbine generator No. 2 failed. On June 16, 1990, the date on which the One Year After Test was to have been performed, the turbine generator was still undergoing warranty repairs. As a result, the Facility was incapable of meeting the output and heat rate efficiencies at the Guaranteed Performance Level until August 11, 1990, 56 days after the tests were to have been performed.

II. SECTION 8.2.2

Plaintiff brings this action to enforce Section 8.2.2 of the Construction Contract and seeks damages from Defendants ACEC Maine, ACEC Union Miniere (as successor-in-interest to ACEC, S.A.), SKG and Insurance Company of North America, in the amount provided under this section’s provision for liquidated damages. Section 8.2.2 of the Construction Contract provides:

“One year after Substantial Completion, Contractor shall again perform the Performance Tests. If the actual output or heat rate efficiency of the Project’s electrical generating equipment, as demonstrated by such Performance Tests (at the same time as the Project meets all other standards and specifications set forth in Appendix D) and as calculated by the formulae set forth in Appendix D, is less than the Project’s actual output or heat rate efficiency, respectively, finally determined pursuant to Section 8.2.1 (the “Revised Performance Level”), Contractor shall, for a reasonable period not to exceed one month, be required to use its best efforts to repair or replace such structures or equipment as is necessary to achieve the Revised Performance Level. At the end of such period, Contractor shall be liable for a one-time payment of liquidated damages for failure to achieve the Revised Performance Level in amount equal to the net present value (calculated as of the Delivery Date using a discount factor equal to the ten-year Treasury bond rate as of the Delivery Date plus two percentage points of lost revenues) of lost revenues sustained by Owner as a result of such failure to achieve the Revised Performance Level. For the purposes of this Section 8.2.2, “lost revenues” shall be deemed to be equal to (a) with respect to output below *161 the Revised Performance Level, the weighted average price (expressed in cents per kilowatt-hour) required to be paid under the power sales agreements then in effect for the sale of the Project’s output, multiplied by the difference between the actual output of the Project (rounded off to the next highest increment of 228 kilowatts) and the Revised Performance Level over a period of 19 years at an availability of 85% (expressed in kilowatt-hours), and (b) with respect to efficiency below the Revised Performance Level, the amount that would be determined under clause (a) of this sentence after substituting for the actual output of the Project the output that would have been achieved if the Project had used only the Revised Guarantee Level Fuel Amount. For purposes of this Article 8, the “Revised Guarantee Level Fuel Amount” is the quantity of fuel that would be required to generate electrical output at the Revised Performance Level, assuming efficiency of the Project equal to the Revised Performance Level.”

Section 8.2.3 further provides:

“In no event shall the liquidated damages payable pursuant to this Section 8.2 (when added to any liquidated damages payable pursuant to Section 7.2) exceed the Contract Price. Owner and Contractor hereby acknowledge and agree that the term conditions and amounts fixed pursuant to this Article 8 for liquidated damages are reasonable considering the damages the Owner would sustain in the event of Contractor’s failure to achieve the Guaranteed Performance Level, and these amounts are agreed upon and fixed as liquidated damages because of the difficulty of ascertaining as of the date hereof the exact amount of damages that would be sustained by Owner, and shall be applicable regardless of the actual amount of damages sustained. Owner and Contractor further acknowledge and agree that payment of these liquidated damages shall be the sole remedy of Owner against Contractor and the sole liability of Contractor to Owner for the Failure to achieve the Guaranteed Performance Level, and that Contractor shall not be otherwise liable for any incidental or consequential damages or for lost profits as a result of such failure; provided, however, that such payment of liquidated damages shall not affect Owner’s right to terminate this agreement pursuant to Section 15.2, or (b) right to liquidated damages pursuant to 7.2.

III. APPLICABILITY

It is undisputed that on June 16, 1990, the Facility was unable to perform at the Guaranteed Performance Level. It is further undisputed that at no time within the 30 day repair period was the Facility capable of performing at the performance level required by Section 8.2.2.

Pursuant to Section 8.2.2 Plaintiff seeks liquidated damages in accordance with the formula set forth therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
782 F. Supp. 159, 1992 U.S. Dist. LEXIS 848, 1992 WL 10566, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cit-groupequipment-financing-inc-v-acec-maine-inc-med-1992.