Cissel v. Western Plumbing & Heating, Inc.

612 P.2d 206, 188 Mont. 149, 1980 Mont. LEXIS 753
CourtMontana Supreme Court
DecidedJune 4, 1980
Docket14865
StatusPublished
Cited by5 cases

This text of 612 P.2d 206 (Cissel v. Western Plumbing & Heating, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cissel v. Western Plumbing & Heating, Inc., 612 P.2d 206, 188 Mont. 149, 1980 Mont. LEXIS 753 (Mo. 1980).

Opinion

MR. JUSTICE HARRISON

delivered the opinion of the Court.

Appellant Gary Cissel initiated this action by filing a complaint in the Sixth Judicial District, Park County, before the Honorable Jack D. Shanstrom. The complaint alleged the respondent, Western Plumbing and Heating, Inc. (herein Western), negligently installed a water closet valve in a home being constructed by him resulting in damage to the home which rendered it worthless. Western *151 answered the complaint by asserting the damages complained of by Mr. Cissel were caused by negligence on his part.

The parties presented the case to a jury on the complaint and answer. The jury returned special interrogatories finding negligence on the part of both parties but finding only Mr. Cissel’s negligence caused damages to the house. The jury returned a general verdict for defendant. The District Court entered judgment accordingly and this appeal followed.

Mr. Cissel and William Patenaude entered into a joint venture agreement to construct and sell a house in Livingston, Montana. Under the terms of the agreement Mr. Cissel was to provide the financing for the project and do the electrical work. Patenaude was to act as the general contractor. Construction of the house began in November 1976 and continued at a slow pace until March 1977. At that time Mr. Cissel terminated his agreement with Patenaude and hired John Sexton to complete construction of the home.

When Mr. Sexton began working on the house he discovered that one corner of the structure had settled approximately five-eighths of an inch. Sexton also ascertained that the house was moving in a side-to-side fashion. Sexton installed a cement “deadman” below the foundation of the house to correct these problems. Sexton stated that no further slippage or settling occurred in the foundation for about the next eight months while he completed construction of the structure.

Mr. Cissel contracted with Western to do the plumbing in the house. As of February 4, 1978, all the plumbing had been completed except for the installation of a toilet in a bathroom on the first floor of the house. Western had installed the pipe that supplied water to the toilet and sealed it off with a water closet valve.

On February 4, 1978, Mr. Cissel conducted a routine inspection of the house. He found that the water closet valve installed on the toilet pipe had blown off and that water was flowing through the inside of the house. Mr. Cissel presented evidence at trial that the water flow from the pipe washed away a large portion of the fill dirt around the foundation of the house. He also presented *152 testimony that the erosion of the fill dirt caused the house to settle approximately five inches which in turn caused cracks in the footings and foundation of the house, cracks in the stone veneer installed on the outside of the house, separation of the house’s interior walls, buckling of sheet rock inside the house, and eventually the buckling of the floor in the house. These damages rendered the house unsaleable and worthless according to Mr. Cissel.

Western presented evidence along two lines to refute Cissel’s theory that the leaking pipe caused the damage to the house. First, Western introduced testimony that both the fill and foundation systems used by Cissel in constructing the house were inadequate to support the structure. Second, Western introduced evidence that water run-off from a snow melt, rather than water leaking from the toilet pipe, caused a substantial amount of the erosion of the fill dirt.

Mr. Cissel’s attorney put William Patenaude on the stand at trial. On direct examination Mr. Patenaude testified as to the procedure followed in setting the foundation of the house and placing the fill dirt around the house. On cross-examination Patenaude was allowed to testify as to an incident that occurred after the filing of this lawsuit. He related an incident before trial in which Mr. Cissel allegedly grabbed him, threw him to the ground and threatened “to blow his brains out” if he did not testify favorably to Cissel’s case at trial.

Mr. Cissel raises the following issues on appeal:

1. Was there substantial evidence before the jury to support the finding of no causal connection between Western’s negligent installation of the water closet valve and the damages sustained by Mr. Cissel?

2. Did the District Court err in admitting the testimony of William Patenaude concerning the assault Mr. Cissel made on him and the threats Cissel made to him?

Mr. Cissel frames the first issue raised on appeal in terms of substantial evidence to support the jury verdict. The standard for *153 review of an issue presented in this fashion is well settled. The Court will not disturb the jury’s verdict if the record contains substantial evidence to support the verdict. Dodds v. Gibson Products Company (1979), 181 Mont. 373, 593 P.2d 1022, 1026; McGuire v. American Honda Co. (1977), 173 Mont. 171, 177, 566 P.2d 1124, 1127; Big Sky Livestock Inc. v. Herzog (1976), 171 Mont. 409, 414, 558 P.2d 1107, 1109-1110. Further the evidence must be viewed in the light most favorable to the prevailing party in the trial court on review. Herzog, 171 Mont. at 414, 558 P.2d at 1110.

Several witnesses presented testimony that there was no causal connection between Western’s negligence and the damage to the house. The evidence indicated two causes of the settling of the house and resulting damages other than the leaking pipe. First, Western introduced evidence that improper design of the house and improper compaction of the fill dirt placed under the house caused the settling. Two expert witnesses testified to that effect. Kent Brewer, a structural engineer, testified that the foundation system of the house was inadequate; that the pylons that supported the front of the house were not set in bedrock; and that the fill under the house was improper. Brewer did state that water flow would accelerate settling in a loose fill situation, but that the settling would occur eventually even without the water flow. On cross-examination Brewer said the house would have settled in zero to five years without any water flow.

Walter Jones also testified. Jones is a civil engineer with a specialty in soil mechanics. He stated that the back of the house has been placed on bedrock and had not settled. He further observed that the front of the house had not been placed on bedrock and had settled. Jones explained that his company had taken soil samples and run tests to determine the compaction of the fill dirt under the house. Jones stated the tests showed the fill dirt was not compacted very well and that the house could be expected to settle about six inches under the existing fill conditions. Based on this data, Jones concluded the main reason for the settling of the house *154 was improper compaction of the fill dirt under the house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. Johnson
2009 MT 254 (Montana Supreme Court, 2009)
State v. Flores
1998 MT 328 (Montana Supreme Court, 1998)
Lutz v. National Crane Corp.
884 P.2d 455 (Montana Supreme Court, 1994)
State v. Short
702 P.2d 979 (Montana Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
612 P.2d 206, 188 Mont. 149, 1980 Mont. LEXIS 753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cissel-v-western-plumbing-heating-inc-mont-1980.