Cincinnati Gas and Electric Company v. Westinghouse Electric Corporation

465 F.2d 1064, 65 Ohio Op. 2d 123, 1972 U.S. App. LEXIS 7727
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 29, 1972
Docket72-1103
StatusPublished
Cited by4 cases

This text of 465 F.2d 1064 (Cincinnati Gas and Electric Company v. Westinghouse Electric Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cincinnati Gas and Electric Company v. Westinghouse Electric Corporation, 465 F.2d 1064, 65 Ohio Op. 2d 123, 1972 U.S. App. LEXIS 7727 (6th Cir. 1972).

Opinion

WILLIAM E. MILLER, Circuit Judge.

The appellants, Cincinnati Gas and Electric Company, Columbus and Southern Ohio Electric Company, and Dayton Power and Light Company (the utilities), brought this action in the United States District Court for the Southern District of Ohio against Oberle-Jordre Company, Inc. and the appellee, Westinghouse Electric Corporation. Federal court jurisdiction is based on diversity of citizenship. After a preliminary hearing the district court, pursuant to Rule 56 of the Federal Rules of Civil Procedure, granted Westinghouse a summary judgment.

The appellants in order to construct a unit for the generation of electric power entered into a number of contracts. One contract was with Westinghouse for the construction of components of the generating unit. Another of the contracts was with Oberle-Jordre for the erection of the components into a generating unit. The Westinghouse contract provided, in addition to supplying the components, that it was to provide “competent erecting supervisor (s) who shall supervise and be responsible for the erection of the equipment

One of the components provided by Westinghouse was a three-way valve. The purpose of this valve was to divert oil flow from one oil cooler to another. The coolers provide a method of cooling the oil that lubricates the turbine bearings. On October 4, 1968, during start-up procedures, this valve was turned ostensibly to divert the oil flow from one cooler to another. The flow of oil, however, was completely blocked and consequently the turbine’s bearings were severely damaged.

The complaint alleges that on April 18-19, 1968, an Oberle-Jordre crew disassembled the three-way valve and then reassembled it improperly. The complaint further alleges that Westinghouse was negligent in failing properly to inspect and supervise the disassembly and reassembly of the valve. The utilities’ claim against both defendants is for damages in excess of 10 million.

Westinghouse in its answer relied upon several defenses, only one of which is relevant here. This defense is based on Section (11) of the contract between the utilities and Westinghouse:

(11) Contractor warrants that the recommendations of the Field Engineers shall accurately reflect the best judgment of a qualified engineer on the premises but no other warranty or obligation of any kind shall extend thereto or be implied therefrom and Contractor shall not be liable for any act or omission of those not its employees nor for any injury, loss, damage, delay, failure to operate, or other thing whatsoever due in whole or in part to any cause other than the failure of its engineering recommendations to fulfill such warranty. The liability of Contractor with respect, to the Field Engineer’s services shall not, in any event, exceed the cost of correcting defects in the apparatus, and Contractor shall not be liable for consequential damages.

Westinghouse claims that this provision not only limits its liability to the cost of repairing the apparatus but also exonerates it from liability altogether. 1

*1066 After filing its answer Westinghouse moved for a summary judgment under. Rule 56, also based on Section (11) of the contract, on the ground that there was no genuine issue of material fact and that Westinghouse was entitled to judgment as a matter of law. After a preliminary hearing, the district court granted Westinghouse’s motion.

The district court held that Section (11) of the contract clearly and unambiguously absolved Westinghouse from all liability where Westinghouse’s negligence was not the sole cause of an accident. Thus, as here, where the accident is alleged to have been due to the combined acts of negligence of Oberle-Jordre and Westinghouse, Section (11) exculpated Westinghouse completely. Accordingly judgment was entered dismissing the action as to Westinghouse. For purposes of the present appeal the district court certified that there was no just cause for delay. In so ruling the district court emphasized that portion of the contract which provided that Westinghouse should not be liable “for any injury . . . due ... in whole or in part to any cause other than the failure of its engineering recommendations to fulfill such warranty . . .,” and that it should not be liable “for any act or omission of those not its employees.” Since the injury was due at least in part to a cause other than a failure of Westinghouse’s warranty (Oberle-Jordre’s negligence), Westinghouse was held to have no liability to the utilities. We think that the district court misapprehended the provisions of the contract and erred in granting Westinghouse’s motion for summary judgment.

Rule 56 of the Federal Rules of Civil Procedure provides that a party is entitled to a summary judgment upon a showing that “there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” While we agree with the district court that there is no genuine issue of material fact 2 we disagree that Westinghouse is entitled to a judgment as a matter of law. See 6 Moore’s Federal Practice If 56.04 [1].

In cases involving the interpretation of contract language extensive examination of precedent is of little value since the controlling rhetoric will vary from case to case. Yet since this is a diversity case we must look for guidance to the applicable Ohio precedents. An examination of the Ohio authorities makes it clear to us that while contracts seeking to relieve a party from the consequences of his own negligence or breach of duty are strictly construed, general rules of contract construction are not invoked where the contract is clear and unambiguous. See George H. Dingledy Lumber Co. v. Erie R. R., 102 Ohio St. 236, 131 N.E. 723 (1921); Kay v. Pennsylvania R. Co., 156 Ohio St. 503, 103 N.E.2d 751 (1952); Dayton Fabricated Steel Co. v. Dayton Town and Country, Inc., 99 Ohio App. 309, 133 N.E.2d 423 (1954); General Accident Fire and Life Assurance Corp. v. Smith and Oby Co., 272 F.2d 581 (6th Cir. 1959).

As we are of the opinion that the contract in unambiguous terms does not exonerate Westinghouse from liability for its breach of warranty of proper supervision, it is unnecessary, in keeping with the Ohio decisions, to invoke general rules of contract interpretation. Since Westinghouse relies upon Section (11) of the contract to exonerate it from liability altogether, we first turn to an analysis of that provision. A close scru *1067 tiny of the section discloses that the first sentence may be divided into four discrete parts. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nahra v. Honeywell, Inc.
892 F. Supp. 962 (N.D. Ohio, 1995)
W. William Graham, Inc. v. City of Cave City
709 S.W.2d 94 (Supreme Court of Arkansas, 1986)
Baker v. Kimberly-Clark Corp.
364 F. Supp. 63 (S.D. Ohio, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
465 F.2d 1064, 65 Ohio Op. 2d 123, 1972 U.S. App. LEXIS 7727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cincinnati-gas-and-electric-company-v-westinghouse-electric-corporation-ca6-1972.