Cincinnati Ambulatory Surgery Center v. Ohio Certificate of Need Review Board

574 N.E.2d 529, 62 Ohio App. 3d 1, 1988 Ohio App. LEXIS 5097
CourtOhio Court of Appeals
DecidedDecember 13, 1988
DocketNo. 88AP-478.
StatusPublished
Cited by2 cases

This text of 574 N.E.2d 529 (Cincinnati Ambulatory Surgery Center v. Ohio Certificate of Need Review Board) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cincinnati Ambulatory Surgery Center v. Ohio Certificate of Need Review Board, 574 N.E.2d 529, 62 Ohio App. 3d 1, 1988 Ohio App. LEXIS 5097 (Ohio Ct. App. 1988).

Opinion

McCormac, Judge.

On July 6, 1984, Hamilton-Surgical Care, Inc. filed an application for a Certificate of Need (“CON”) to build an ambulatory surgery facility to be known as Cincinnati Ambulatory Surgery Center (“CASC”) with the State Health Planning and Development Agency (“SHPDA”), now known as the Ohio Department of Health (“ODH”). On September 21, 1984, SHPDA declared the application complete. The application stated that the project site was to be located at 3234 Jefferson Avenue, Cincinnati, Ohio 45220. Written notification to the public and affected persons was provided on October 5, 1984. Once an application is complete, SHPDA reviews it to determine whether to approve or disapprove the application. Ohio Adm.Code *3 3701-12-09. Ohio Adm.Code 3701-12-30 provides SHPDA with the criteria to be utilized when reviewing CON applications for ambulatory surgical facilities.

On December 12, 1985, the applicant notified SHPDA that it had selected a new site that would be located in the 45230 zip code area. On February 7, 1986, SHPDA granted the CON to CASC upon the condition that CASC provide SHPDA with an exact site location within sixty days. On April 1, 1986, CASC provided the exact site:

“ ‘Our Anderson Township facility will be located on a parcel of land located between Nimitzview Drive and Five Mile Road, containing approximately one acre. . Said premises is located south of the office development known as Admiral’s Walk.’ ” (Letter from Joseph J. Frank of Surgical Care Affiliates to Louis Pomerantz, Chief of the Office of Resources Development of ODH, March 31, 1986.)

This location is approximately one mile from Our Lady of Mercy Hospital (“OLMH”).

On April 8, 1986, Pomerantz, Chief of the Office of Resources Development of ODH, wrote a letter to CASC stating that CASC had complied with the condition of approval. On April 10, 1986, OLMH requested SHPDA to reconsider its decision to grant the CON. SHPDA dismissed the request on the grounds that it had rendered its final decision on February 7, 1986, and that reconsideration requests needed to be made within thirty days pursuant to former Ohio Adm.Code 3701-12-15(A), now Ohio Adm.Code 3701-12-15(B).

On May 8, 1986, OLMH appealed SHPDA’s dismissal to the Certificate of Need Review Board (“CONRB”) and requested an adjudication hearing. A CONRB hearing examiner found that the CON should not have been granted until an exact site was provided; that CONRB did have jurisdiction to hear the case; and that the hearing was qualified de novo. The hearing examiner considered all relevant evidence up to the time of the hearing. The hearing examiner found an excess of need in the pertinent health service area. On October 5, 1987, the board found that Ohio Adm.Code 3701-12-30(A) prohibits SHPDA from approving applications for new ambulatory surgery facilities unless a need exists. CONRB adopted the findings of fact and conclusions of law of the hearing examiner and reversed SHPDA’s decision to grant the CON to CASC.

CASC appealed CONRB’s decision to the Court of Common Pleas of Franklin County, asserting that CONRB did not have jurisdiction to consider the appeal of OLMH because OLMH had not requested an adjudication hearing in time. OLMH intervened in this proceeding and joined CONRB as an appellee.

*4 Based upon its reading of Ohio Adm.Code 3702-2-03(B), the court determined that the February 7, 1986 decision of SHPDA was an appealable decision and that the thirty-day time period for requesting an adjudication hearing began running at that time. Because OLMH did not request an adjudication hearing within thirty days of February 7, the court reversed the decision of CONRB, holding that it lacked subject matter jurisdiction.

Appellant, OLMH, asserts the following two assignments of error:

“I. The decision of ODH was final on April 8, 1986. That decision was appealable to the board.
“II. If the conditional approval is determined to be the final order, then thereafter the change in the site of the project rendered the Certificate of Need invalid.”

Appellant reasons that an application for an ambulatory surgical center cannot be properly ruled complete without a specific site location, and that there can be no valid final approval of a CON until it is complete.

No statute or administrative rule defines how specific a site location must be before a CON application may be deemed complete and subsequently approved. This court has held that the definition of “site” and its application to a particular case are left to the discretion of CONRB, the trier of fact. In re Akron Ambulatory Surgical Ctr. (Apr. 11, 1985), Franklin App. No. 84AP-581, unreported, 1985 WL 10240. In Akron, the disputed application provided a site location of “Market Street in Fairlawn, Ohio.” The CONRB hearing examiner determined that this statement of site was insufficient for approval. The examiner based his decision on pertinent statutes and regulations. Former R.C. 3702.55(C) was one of the statutes; it provided that a CON became inoperative if the site of the proposed facility were changed from that identified in the approved application. The examiner reasoned that, unless the site were specifically identified in the application, this statute would be, in our characterization, nothing more than a paper tiger.

Former R.C. 3702.55 is not the only regulation which supports the examiner’s • determination in Akron. Ohio Adm.Code 3701-12-30(B) contains language which indicates that a site location must be more specific than an area code:

“(B) Availability/accessibility.
U * * *
“(3) Each applicant shall include with the application a map delineating at least the following:
“(a) The ‘proposed primary service area,’ which shall be the area within thirty minutes travel time of the proposed ASF, and the ‘proposed secondary *5 service area/ which shall be the area within sixty minutes travel time of the proposed ASF, both to be shown by zip codes;
<< * * *
“(5) Each applicant shall document that the proposed location will meet local zoning requirements.”

In order for these two provisions to have substance, the location needs to be a more specifically defined area: the thirty-minute travel time requirement would be difficult to apply to two zip code areas; zoning requirements are not uniform throughout a zip code area.

Ohio Adm.Code 3701-12-07 lends additional support to the position that a site location which only identifies the zip code area is insufficient. Subsection (C) sets forth the notice of intent requirements for a construction project:

“ * * * The notice of intent shall contain the following information:
“(1) Name of sponsoring organization;
“(2) Name of [proposed] facility;
“(3) Location of project (address, city, county);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Cooper
697 N.E.2d 1049 (Ohio Court of Appeals, 1997)
In Re Continental Medical Systems of Ohio, Inc.
627 N.E.2d 1018 (Ohio Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
574 N.E.2d 529, 62 Ohio App. 3d 1, 1988 Ohio App. LEXIS 5097, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cincinnati-ambulatory-surgery-center-v-ohio-certificate-of-need-review-ohioctapp-1988.