Cinbar Engineering Co. v. Delta Leasing & Investment Corp.

404 S.W.2d 626, 1966 Tex. App. LEXIS 2739
CourtCourt of Appeals of Texas
DecidedJune 8, 1966
Docket11412
StatusPublished
Cited by6 cases

This text of 404 S.W.2d 626 (Cinbar Engineering Co. v. Delta Leasing & Investment Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cinbar Engineering Co. v. Delta Leasing & Investment Corp., 404 S.W.2d 626, 1966 Tex. App. LEXIS 2739 (Tex. Ct. App. 1966).

Opinion

ARCHER, Chief Justice.

Appellants were defendants in the trial court and appellee was plaintiff.

Summary judgment was granted for plaintiff on its pleadings and the affidavit of its president, J. C. Youdan.

The motion for summary judgment was opposed by the defendants’ pleading and the affidavit of Barnhart, president of Cinbar, and certain exhibits.

The pleadings of the parties consisted of:

(1) Plaintiff’s Original Petition against both Cinbar and Barnhart alleging a sworn account. ■

(2) Defendants’ Answer alleging failure of consideration and a general denial *628 to Plaintiff’s original cause of action and a countersuit by Cinbar against Delta alleging joint adventure, breach of warranties, express or implied, and damages.

(3) Plaintiff’s Answer to Defendant’s eountersuit by general denial and special answer alleging disclaimer of any warranties and no joint adventure.

(4) Defendants’ Supplemental Petition on its eountersuit alleging waiver and es-toppel of Plaintiff’s disclaimer of any warranties.

Cinbar is in the sheet metal business in Austin, Texas; Barnhart is its president. Barnhart was told of a machine manufacturer in Houston, Texas, who reportedly could make a machine which would automatically measure, cut and stack sheet metal from a rolled coil. The manufacturer was Lawler Manufacturing Co., hereinafter sometimes called “Lawler.”'

Cinbar contacted Lawler and Lawler said it could manufacture such a machine for $14,250.00. Cinbar refused because of the terms which were cash.

Cinbar was next contacted by Delta who said it would have the machine built and lease it to Cinbar on a monthly lease of $475.00 for 36 months.

The parties agreed and executed a lease agreement to that effect, and payments were made for about twelve months.

Appellants contend that the machine would not operate automatically and refused to pay a balance on a lease agreement, and Delta filed this suit.

The appeal is predicated on six points and are that the trial court erred in granting the motion for summary judgment because there were disputed material facts as to waiver and estoppel of the disclaimer, that the two writings were one transaction, that there was a disputed question of fact' as to a joint adventure and a fact question as to failure of consideration, that the court erred in treating plaintiff’s- cause as one for a sworn account, and in determining that no warranty had been made.

Appellee takes the position that there were no disputed material facts raised by the evidence as to waiver of or estoppel to assert that plaintiff had made no warranties as to the performance of the machine, and no fact issue raised that the two writings were one transaction, and no fact issue raised as to the existence of a j-oint venture, or as to a failure of consideration, and the court did not err in treating the cause of action as a sworn account, and the contract being in writing and the “no warranty” provisions being unambiguous, the trial court acted properly in determining as a matter of law the effect of the contract; and there was no evidence raising any disputed material fact issues of waiver of or estoppel to assert that plaintiff made no warranties as to the performance of the leased machine.

We believe the court was justified in granting the motion for summary judgment.

A pleading unsupported by evidence is insufficient to raise fact issues, and, the existence of an affirmative defense must be done by “summary judgment evidence,” such as depositions, admissions, affidavits, or the like. Keahey v. Dallas Teachers Credit Union, Tex.Civ.App., 3-74 S.W.2d 450; Smith v. Campbell, Tex.Civ.App., 361 S.W.2d 462.

The equipment lease involved in this case reads in part:

“Lease, dated May 7, 1964, by and between NATIONAL ACCEPTANCE COMPANY OF AMERICA (hereinafter called ‘Lessor’) and Cinbar Engineering Company, Inc. a Texas corporation (hereinafter called ‘Lessee’).
1. EQUIPMENT AND RENT. Lessor hereby leases to Lessee, and Lessee hereby rents from Lessor, at a to *629 tal rent for the term of this lease of Seventeen thousand one hundred two and 88/100.Dollars ($17,102.88), which Lessee agrees to pay to Lessor as hereinafter set forth, the following personal property (hereinafter called ‘Equipment’) :
(Describe fully, giving name of manufacturer, model, serial no.)
LAWLER SPECIAL PROCESSING EQUIPMENT
2. TERM. This lease, upon the rents, promises, terms and conditions set forth herein, is for a term of Thirty-Six (36) months commencing on the date (the ‘Commencement Date’) that Equipment is delivered to Lessee or shipped via common or other carrier for delivery to Lessee, whichever shall be earlier.
3. PURCHASE AND DELIVERY OF EQUIPMENT. Lessee hereby directs that Equipment (which Lessee has requested Lessor to purchase) be shipped via common or other carrier to Lessee at 711 St. John, City of Austin, County of Travis, State of Texas.
4. PAYMENT OF RENT. Lessee agrees to pay to Lessor the total rent specified above in monthly payments as follows:
36 consecutive payments, each of $475.08; then

The foregoing payments shall be made as follows:

(a) Time: Upon signing this lease, Lessee sliall pay Lessor the sum of $1,- 425.24, constituting the payment in advance of the 1st, 35th and 36th. * * *
20. NO WARRANTIES: ENTIRE AGREEMENT. Lessee agrees that Lessor has made no representation or warranty of any kind, nature or description, express or implied, with respect to Equipment. This lease contains the entire agreement between the parties, and may not be changed, modified, terminated or discharged except in writing.”

The provisions of the lease are clear and unambiguous and the lease was executed by Cinbar and attested by its secretary, a lawyer of ability who was well trained in contracts and in no wise was Cinbar overreached or not informed as to the contents of the lease including the “no warranty” provision.

Prior to the execution of the lease appellant had contacted by letter, Lawler Engineering Manufacturing in Houston, Texas in regard to equipment needed, and was advised that a machine such as inquired about could be manufactured for a cash price of $14,250.00. Appellant was unable to pay such sum in cash and Lawler suggested a credit-lease purchase arrangement, and would make such.

J. C. Youdan contacted Cinbar and represented himself as president of a company, now appellant, and said that he had been contacted by Lawler, relative to financing the sale of the machine, and that he would finance the purchase, and would lease the machine to Cinbar on a monthly basis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker v. Eason
631 S.W.2d 560 (Court of Appeals of Texas, 1982)
Patriot General Life Insurance v. CFC Investment Co.
420 N.E.2d 918 (Massachusetts Appeals Court, 1981)
Bill Stremmel Motors, Inc. v. IDS Leasing Corp.
514 P.2d 654 (Nevada Supreme Court, 1973)
Mills v. Rice
441 S.W.2d 290 (Court of Appeals of Texas, 1969)
Womack v. I. & H. DEVELOPMENT COMPANY
433 S.W.2d 937 (Court of Appeals of Texas, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
404 S.W.2d 626, 1966 Tex. App. LEXIS 2739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cinbar-engineering-co-v-delta-leasing-investment-corp-texapp-1966.