Cify of Everett v. Barletta Engineering Corp.

19 Mass. L. Rptr. 406
CourtMassachusetts Superior Court
DecidedMay 20, 2005
DocketNo. 004884
StatusPublished

This text of 19 Mass. L. Rptr. 406 (Cify of Everett v. Barletta Engineering Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cify of Everett v. Barletta Engineering Corp., 19 Mass. L. Rptr. 406 (Mass. Ct. App. 2005).

Opinion

Haggerty, S. Jane, J.

This is an action brought by the plaintiff, the City of Everett (“Everett”), against the defendant, Barletta Engineering Corporation (“Bar-letta”), arising out of an owner-contractor agreement entered into by the parties. Barletta, as a third-party plaintiff, also brings claims against several third-party defendants involved in the construction project of the Lafayette Elementary School in Everett, Massachusetts, including the architect of the project, Flans-[407]*407burgh Associates, Inc. (“Flansburgh”). Everett brings two claims against Barletta. Count I alleges Barletta’s failure to complete the construction of the Lafayette School Building in accordance with the Contract Documents, and Count II alleges Barletta’s failure to construct a ballfield in accordance with the agreement. Included in Barletta’s claim against the third-party defendants are two claims against Flansburgh. Count I alleges negligence in preparation of the Contract Documents used to solicit bids by Everett, and Count II alleges negligent misrepresentation in Flansburgh’s depiction of the site conditions in the contract.

Flansburgh asserts that the owner-contractor agreement between Barletta and Everett contains a covenant not to sue Flansburgh which is enforceable, and that the economic loss doctrine bars the third-party claims. Barletta responds that the covenant not to sue does not apply to the claims against Flansburgh based on active negligence, and is unenforceable, and that the economic loss doctrine is inapplicable to the claims. The matter is before this court on Flansburgh’s motion for summary judgment as to all of Barletta’s claims against them.

For the reasons set forth below, Flansburgh Associates, Inc.’s motion for summary judgment as to all of Barletta Engineering Corporation’s claims against Flansburgh is ALLOWED.

BACKGROUND

This dispute arises as the result of defects in the fitness of the Lafayefte School Building. At this sum-maryjudgment stage, the facts are reported in the light most favorable to the non-moving party. Anderson Street Associates v. City of Boston, 442 Mass. 812,816 (2004), citing Augat Inc. v. Liberty Mut. Ins. Co., 410 Mass. 117, 120 (1991).

Barletta and Everett entered into a general contract for the construction of the school building on March 5, 1998. The project was to be completed by July 5, 1999. Flansburgh prepared the Contract Documents, including the Plans and Specifications, which Everett utilized for the purpose of soliciting bids from potential general contractors. Barletta commenced construction in accordance with the Plans and Specifications after receiving the General Contract from Everett. Included in the Contract Documents was information regarding the site conditions at the project site, which Barletta also relied on.

During the construction process, Everett authorized certain change orders which resulted in adjustments to the contract price, as well as an extension of time to complete the project. Barletta was unable to meet the extension deadline, and did not achieve substantial completion of the project until October 25, 1999. However, the building was still not able to be occupied for its use as a school building until February 28, 2000 due to several problems. These included breakdowns of the heating system, problems with air balancing, broken ceiling tiles, and required cleaning of the building. In addition, significant water leaks have plagued the project, causing damage to the walls, ceilings, and floors. Covino Environmental Associates, Inc. was hired by Everett to conduct a visual inspection and environmental sampling of the building, and the resulting assessment revealed the presence of mold and microbial contamination.

As a result of these problems, as well as several other defects in the construction of the building, Everett has been denied its use and enjoyment of the property, the benefit of contract compliance, and has incurred significant expenses in maintenance and repair costs. In addition, Barletta’s failure to submit the required documentation verifying the sufficient fill and topsoil cover for the ball field on the properly led to Everett’s hiring of an independent consultant to verify the depth of the cover. The consultant reported that the cover was insufficient, and that the field was required to be closed down. Everett has incurred costs in assessing the cover for the field, as well as in contracting for remediation of the defects.

At issue is the language of the Owner-Contractor Agreement concerning a covenant not to sue. The Supplementary General Conditions of the agreement contains an additional paragraph that was added to paragraph 3.18 of the General Conditions. Paragraph 3.18.4 states as follows:

The Contractor, or any successor, assign or subro-gee of the Contractor, agrees not to bring any civil suit, action or other proceeding in law, equity or arbitration against the Architect, or the officers, employees, agents or consultants, of the Architect, for the enforcement of any action which the Contractor may have arising out of or in any manner connected with the Work. The Contractor shall assure that this covenant not to sue is contained in all subcontractors and subcontractors of every tier, and shall assure its enforcement. The Architect, its officers, employees, agents, and consultants are intended third-party beneficiaries of this covenant not to sue, who are entitled to enforce this covenant in law or equity.

DISCUSSION

Summary judgment is appropriate where the “pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Highland Ins. Co. v. Aerovox, Inc., 424 Mass. 226, 232 (1997), citing Mass.R.Civ.P. 56(c). In a case such as this, where the opposing party will have the burden of proof at trial, the moving parly is entitled to summary judgment if he can demonstrate by reference to these materials, “unmet by countervailing materials, that the party opposing the motion has no reasonable expectation of [408]*408proving an essential element of that party’s case.” Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991).

The Supreme Judicial Court has stated that “an unambiguous agreement must be enforced according to its terms.” Schwanbeck v. Federal-Mogul Corp., 412 Mass. 703, 706 (1992), citing Freelander v. G.&K. Realty Corp., 357 Mass. 512, 516 (1970). It is appropriate for a court to address the interpretation of such unambiguous terms of a contract as a matter of law. See Allstate Ins. Co. v. Secure, 412 Mass. 442, 446-47 (1992). The SJC has clearly established that there is no general rule in Massachusetts preventing a party from validly contracting for exemption from liability for its own negligence. Cormier v. Central Mass. Chapter of the Nat. Safety Council, 416 Mass. 286, 288-89 (1993).

In addressing the validity of a release in a contractual dispute, the Court has stated that “[a] party may, by agreement, allocate risk and exempt itself from liability that it might subsequently incur as a result of its own negligence.” Sharon v. City of Newton, 437 Mass. 99,105 (2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minassian v. Ogden Suffolk Downs, Inc.
509 N.E.2d 1190 (Massachusetts Supreme Judicial Court, 1987)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Augat, Inc. v. Liberty Mutual Insurance
571 N.E.2d 357 (Massachusetts Supreme Judicial Court, 1991)
Freelander v. G. & K. REALTY CORP.
258 N.E.2d 786 (Massachusetts Supreme Judicial Court, 1970)
Schwanbeck v. Federal-Mogul Corp.
592 N.E.2d 1289 (Massachusetts Supreme Judicial Court, 1992)
Allstate Insurance v. Bearce
589 N.E.2d 1235 (Massachusetts Supreme Judicial Court, 1992)
Cormier v. Central Massachusetts Chapter of the National Safety Council
620 N.E.2d 784 (Massachusetts Supreme Judicial Court, 1993)
Highlands Insurance v. Aerovox Inc.
676 N.E.2d 801 (Massachusetts Supreme Judicial Court, 1997)
Sharon v. City of Newton
769 N.E.2d 738 (Massachusetts Supreme Judicial Court, 2002)
Anderson Street Associates v. City of Boston
817 N.E.2d 759 (Massachusetts Supreme Judicial Court, 2004)
Stone/Congress v. Town of Andover
6 Mass. L. Rptr. 330 (Massachusetts Superior Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
19 Mass. L. Rptr. 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cify-of-everett-v-barletta-engineering-corp-masssuperct-2005.