CHRISTOPHER HOUGHTON VS. STEVE HOURAN VS. SHEILA HOUGHTON (L-1982-15, BERGEN COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedAugust 28, 2019
DocketA-0101-18T1
StatusUnpublished

This text of CHRISTOPHER HOUGHTON VS. STEVE HOURAN VS. SHEILA HOUGHTON (L-1982-15, BERGEN COUNTY AND STATEWIDE) (CHRISTOPHER HOUGHTON VS. STEVE HOURAN VS. SHEILA HOUGHTON (L-1982-15, BERGEN COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CHRISTOPHER HOUGHTON VS. STEVE HOURAN VS. SHEILA HOUGHTON (L-1982-15, BERGEN COUNTY AND STATEWIDE), (N.J. Ct. App. 2019).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-0101-18T1

CHRISTOPHER HOUGHTON,

Plaintiff-Respondent,

v.

STEVE HOURAN, HOURAN FUCETOLA CONSTRUCTION, LLC, and HOURAN USA CONSTRUCTION, LLC,

Defendants/Third-Party Plaintiffs-Appellants,

SHEILA HOUGHTON,

Third-Party Defendant- Respondent,

and

S&L ARCHITECTURE STUDIO, LLC,

Third-Party Defendant. ______________________________ Submitted June 25, 2019 – Decided August 28, 2019

Before Judges Rothstadt and Suter.

On appeal from the Superior Court of New Jersey, Law Division, Bergen County, Docket No. L-1982-15.

Hegge & Confusione, LLC, attorneys for appellants (Michael J. Confusione, of counsel and on the brief).

Hedinger & Lawless, LLC, attorneys for respondent (Jeffrey S. Wilson, on the brief).

PER CURIAM

Following remand, defendants Steve Houran (Houran), Houran Fucetola

Construction, LLC (Houran Fucetola), and Houran USA Construction, LLC

(Houran USA) (collectively defendants) appeal from the August 31, 2018 order

that found Houran personally liable for $41,493.06 in compensatory damages

and $26,700 in attorney's fees. We reverse the compensatory damages award

against Houran and vacate the attorney fee award, remanding only that issue to

the trial court to determine a reasonable attorney fee for the regulatory violation.

I

In the underlying case, plaintiff sued defendants for breach of contract,

misrepresentation and violation of the Consumer Fraud Act (CFA), N.J.S.A.

56:8-1 to -210, arising from a home improvement contract. Our unreported

opinion summarized testimony from the 2016 bench trial:

A-0101-18T1 2 Kenneth Schier of S&L Architecture Studio was hired to prepare architectural plans for an addition to plaintiff's home in Ridgewood, New Jersey. Plaintiff searched for a contractor through Home Advisors. Defendant Steve Houran received the referral, contacted plaintiff and met with him. Plaintiff gave Houran a copy of the architectural plans. Houran prepared the written contract based on these plans. It was signed on September 16, 2013, by plaintiff and Houran Fucetola.

The contract did not include the business address of Houran Fucetola, the start and completion date for the project or the total price to be paid by plaintiff. It did include sub-categories of work to be completed and the price for the foundation, framing, roofing, siding, flooring, electrical, and plumbing. The contract included a schedule of payments that were due upon certain benchmarks.

Work commenced on the addition in March 2014, after building permits were obtained. The construction project immediately struck a sour note, with the defendants undertaking demolition work while the Houghtons were away, contrary to their instruction. The work proceeded until April 23, 2014, when Houran sent a termination notice, claiming that delays were attributable to the owner's interference with the scope of the work and "trigger[ed]" by "the decision to remove portions of the contract." By that point, plaintiff had paid $51,861.74, which was 80% of the contract. The construction was not finished. Plaintiff hired contractors to remediate and complete the work.

Schier testified as an expert in residential construction that there were multiple problems with the construction which was "[b]elow acceptable reasonable standards," describing it as "the worst construction project [he] had ever seen in [his] career." He testified that the

A-0101-18T1 3 foundation was improperly constructed, the ridge beam was not made of microllam as required by the plans, the construction used improper fasteners, lacked headers, used improper joist hangers, did not have hurricane straps, was missing floor joists, and the second floor stairs now were sagging. There were other workmanship problems as well.

The Village of Ridgefield building inspector, Carlo Madrachimov, testified, "there [were] multiple failures on this . . . project," which included the depth of the footing, framing deficiencies, and use of a ridge beam made of "regular nominal lumber." He said that the architect's plans were not followed.

Houran testified that he had many years' experience in the construction industry and completed hundreds of home improvement renovations. He said they ran into some issues in the construction that required four change orders, all of which were agreed to by plaintiff through email. His firm was not able to complete the project because plaintiff "excised" parts of the contract. He blamed Sheila Houghton for interfering with their work. Houran was not permitted to testify about issues he had with the architectural plans because defendants had not named any expert witnesses in their answers to discovery. David Sanchez, who was employed by Houran USA on the project, testified that Sheila would not let the project go forward as she "was always there having little comment or asking something or saying something to do their own way."

[Houghton v. Houran, No. A-2056-16 (App. Div. June 21, 2018) (slip op. at 3-6).]

The trial court found that defendants breached the contract with plaintiff

by sending a termination notice to plaintiff. Id. at 6. It "found plaintiff suffered

A-0101-18T1 4 actual damages of $41,493.06, consisting of the cost to remediate and to

complete the work, less the balance remaining on the contract." Ibid.

It also found a violation of the "Home Improvement Practices"

regulations, N.J.A.C. 13:45A-16.2(a)(12), "because [the contract] did not

include defendants' business address, the dates or time period the work would

begin or be completed by, or the total price to be paid by the buyer." Ibid.

Because plaintiff's "damages arose from 'shoddy work and breach of contract'

and were not causally related to the CFA violations[,]" the trial court denied

plaintiff's request for treble damages. Ibid. The trial court's judgment stated

"sufficient evidence had been presented that the defendant Steven Houran was

individually liable under the 'Home Improvement Practices' regulations of the

CFA[.]" Id. at 7. The trial court "entered a judgment against all defendants,

including Houran individually, in the amount of $68,193.06, consisting of

$41,493.06 in compensatory damages and $26,700 in attorney's fees and costs."

Ibid. Defendants appealed the judgment.

In our June 2018 opinion, we affirmed the trial court's finding that the

contract with Houghton was breached and that defendants were liable for

damages in the amount of $41,493.06. Id. at 8. However, we vacated the

judgment against Houran individually for breach of contract. Id. at 12-13. He

was not a signatory to the contract with Houghton. Id. at 12. He could not be

A-0101-18T1 5 liable to plaintiff merely as the managing member of an LLC. Ibid. And,

although the corporate form could be pierced upon proof of fraud or injustice,

the court had not made any findings about that issue when it imposed individual

liability on Houran. Ibid. We remanded the issue to the trial court "for

appropriate findings of fact and conclusions of law." Id. at 12-13.

We affirmed the trial court's finding that the contract violated the CFA

home improvement regulations. Id. at 2. However, because it had not made

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Masone v. Levine
887 A.2d 1191 (New Jersey Superior Court App Division, 2005)
Touch of Class Leasing v. Mercedes-Benz Credit of Canada, Inc.
591 A.2d 661 (New Jersey Superior Court App Division, 1991)
Bender v. Adelson
901 A.2d 907 (Supreme Court of New Jersey, 2006)
Flagg v. Essex County Prosecutor
796 A.2d 182 (Supreme Court of New Jersey, 2002)
Pomerantz Paper Corp. v. New Community Corp.
25 A.3d 221 (Supreme Court of New Jersey, 2011)
Rachele Louise Castello v. Alexander M. Wohler, M.D.
139 A.3d 1218 (New Jersey Superior Court App Division, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
CHRISTOPHER HOUGHTON VS. STEVE HOURAN VS. SHEILA HOUGHTON (L-1982-15, BERGEN COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/christopher-houghton-vs-steve-houran-vs-sheila-houghton-l-1982-15-njsuperctappdiv-2019.