Christian Fitchett v. Dolezal Creative Design Build Inc.

CourtCourt of Appeals of Minnesota
DecidedJune 22, 2026
Docketa251569
StatusUnpublished

This text of Christian Fitchett v. Dolezal Creative Design Build Inc. (Christian Fitchett v. Dolezal Creative Design Build Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Christian Fitchett v. Dolezal Creative Design Build Inc., (Mich. Ct. App. 2026).

Opinion

This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA IN COURT OF APPEALS A25-1569

Christian Fitchett, et al., Respondents,

vs.

Dolezal Creative Design Build Inc., et al., Appellants.

Filed June 22, 2026 Affirmed Smith, Tracy M., Judge

Hennepin County District Court File No. 27-CV-22-18746

Kyle S. Willems, Amanda M. Williams, Beth L. LaCanne, James C. Kovacs, Bassford Remele, P.A., Minneapolis, Minnesota (for respondents)

Patrick H. O’Neill, Jr., Patrick H. O’Neill, III, Larson • King, LLP, St. Paul, Minnesota (for appellants)

Considered and decided by Wheelock, Presiding Judge; Connolly, Judge; and

Smith, Tracy M., Judge.

NONPRECEDENTIAL OPINION

SMITH, TRACY M., Judge

Appellants challenge the district court’s grant of default judgment against them as

well as the denial of their motion under Minnesota Rule of Civil Procedure 60.02(a) to

vacate the default judgment. We affirm. FACTS

On October 6, 2021, respondents Christian Fitchett and Layla Dowlatshahi entered

into a contract with appellant Dolezal Creative Design Build Inc. (Dolezal Creative),

owned by appellant Jessica Dolezal (Dolezal), for a home-remodeling project. The project

included substantial renovations to the home’s kitchen, dining area, mudroom, powder

room, greenhouse, basement, stairs, attic space, and HVAC system. The contract price was

$273,617, with partial payments due as provided over the course of the contract.

Section 5(d) of the contract provided:

Substantial completion of the Improvements is expected to occur on or about March 15, 2022[.] Owner acknowledges, however that this date is only an estimate and is subject to change due to many factors including, but not limited to: (i) changes in the Plans requested by Owner; (ii) delays in receiving materials specified in the Plans; (iii) delays caused by shortages of labor, materials or equipment; . . . (vi) other causes reasonably beyond Builder’s control.

Appellants began work on the remodel, and respondents temporarily moved out of

the home during construction. Progress stalled several times, and the project passed the

March 15 substantial-completion date. After several extensions of the substantial

completion date, respondents retained counsel, who contacted appellants in September

2022 in an effort to get the project “back on track.” Respondents requested a project-

completion plan and documents related to the remodel, including invoices and proof of

payments exchanged between appellants and subcontractors and material suppliers,

contracts with subcontractors and material suppliers, work orders and permits, and an

accounting of how respondents’ partial payments had been used. Appellants did not comply

2 with respondents’ requests. By letter dated October 10, 2022, respondents informed

appellants that they would hire a new contractor to complete the work and that appellants

were in breach of the contract.

In November 2022, appellants served and filed for record a mechanic’s lien

statement for the lien on respondents’ home, asserting that respondents owed Dolezal

Creative $60,833.90 for work completed on their home. Appellants assert that respondents

prevented them from accessing the property and inspecting or completing the work.

Respondents sued appellants in December 2022, asserting claims of breach of

contract, negligence, breach of express and implied warranties, slander of title, fraud by

omission, negligent misrepresentation, fraudulent misrepresentation, consumer fraud in

violation of the Minnesota Statutes section 325F.69 (2024), 1 civil theft in violation of

Minnesota Statutes section 604.14 (2024), conversion, and nonpayment for improvement

in violation of Minnesota Statutes section 514.02 (2024). Respondents also asserted a claim

to pierce the corporate veil. Appellants, represented by their first counsel (first counsel),

counterclaimed for breach of contract, unjust enrichment, account stated, and quantum

meruit.

An initial scheduling order set a trial date of November 27, 2023. In July 2023,

respondents filed a motion to compel discovery from appellants. Before a hearing on the

motion, the parties submitted a stipulation to amend the scheduling order to extend some

deadlines, including the deadline to complete discovery, but leaving the trial date set for

1 We cite the current version of these statutes because the version is irrelevant to the issues in this appeal.

3 November 27. The district court adopted the amended scheduling order. Appellants did not

contest the motion to compel. On July 31, at the hearing on the motion, the district court

held the record open to allow appellants time to complete discovery and for the parties to

engage in mediation. On September 19, the district court held a status conference on the

discovery issue, and respondents submitted correspondence asserting ongoing deficiencies

by appellants. The district court took respondents’ motion to compel under advisement on

October 10.

On September 19, the parties submitted another stipulation to amend the scheduling

order, this time including moving the trial date to the district court’s April-May 2024 trial

block. The district court approved this proposed amended scheduling order.

On December 20, the district court filed its order on respondents’ July motion to

compel discovery. It ruled that, because it was undisputed that appellants’ discovery

responses had been insufficient and because appellants did not raise any defense to the

motion, respondents were entitled to an award of expenses and attorney fees in an amount

to be determined. In January 2024, respondents filed their request for expenses and attorney

fees. That same month, respondents filed a motion for partial summary judgment and a

motion for leave to amend the complaint to assert a claim for punitive damages. After a

hearing, the district court denied the motions for partial summary judgment and to amend

the complaint to seek punitive damages. In the same order, the district court awarded

respondents $14,832.50 in costs and attorney fees for the motion to compel.

Shortly thereafter, appellants’ first counsel withdrew from representation.

According to respondents, appellants could not pay the balance owed to their counsel. On

4 June 12, new counsel for appellants (second counsel) filed a notice of appearance. A status

conference was held on July 9, and on July 15 the district court filed a pretrial order and

order for trial (pretrial order), setting October 28 as the deadline for submitting pretrial

submissions and November 18 for the jury trial to begin. The pretrial order stated in bold:

Failure to comply with this order may subject parties to sanctions, including but not limited to: refusing to allow the noncompliant party to support or oppose designated claims or defenses; prohibiting the noncompliant party from introducing designated matters in evidence; striking pleadings or parts of pleadings; staying further proceedings until the order is obeyed; dismissing the action or a part of the action; or rendering a judgment by default against the noncompliant party. Failure to furnish instructions and/or Proposed Special Verdict Form shall be deemed a waiver by each party as to the right to a trial by jury on the issue so omitted pursuant to the provisions of Rule 49.01(a) of the Minnesota Rules of Civil Procedure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Black v. Rimmer
700 N.W.2d 521 (Court of Appeals of Minnesota, 2005)
Scroggins v. Solchaga
552 N.W.2d 248 (Court of Appeals of Minnesota, 1996)
In RE MARRIAGE OF FITZGERALD v. Fitzgerald
629 N.W.2d 115 (Court of Appeals of Minnesota, 2001)
Frontier Insurance Co. v. Frontline Processing Corp.
788 N.W.2d 917 (Court of Appeals of Minnesota, 2010)
Thorp Loan and Thrift Co. v. Morse
451 N.W.2d 361 (Court of Appeals of Minnesota, 1990)
Charson v. Temple Israel
419 N.W.2d 488 (Supreme Court of Minnesota, 1988)
Finden v. Klaas
128 N.W.2d 748 (Supreme Court of Minnesota, 1964)
Jerry Wayne Cole v. Alexander Allen Wutzke
884 N.W.2d 634 (Supreme Court of Minnesota, 2016)
Michaels v. First USA Title, LLC
844 N.W.2d 528 (Court of Appeals of Minnesota, 2014)
Laymon v. Minnesota Premier Properties, LLC
903 N.W.2d 6 (Court of Appeals of Minnesota, 2017)
Laymon v. Minn. Premier Props., LLC
913 N.W.2d 449 (Supreme Court of Minnesota, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Christian Fitchett v. Dolezal Creative Design Build Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/christian-fitchett-v-dolezal-creative-design-build-inc-minnctapp-2026.