Chris Hansen v. Haven Township

Court of Appeals of Minnesota·Decided June 15, 2026·No. a251897·Unpublished

Opinion

This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).

STATE OF MINNESOTA

IN COURT OF APPEALS

A25-1897

Chris Hansen,

Appellant,

vs.

Haven Township,

Respondent.

Filed June 15, 2026

Affirmed

Ede, Judge

Sherburne County District Court File No. 71-CV-24-1884

Gordon H. Hansmeier, Gordon Hansmeier Law Office, P.A., St. Cloud, Minnesota (for appellant)

Paul Donald Reuvers, Andrew A. Wolf, Iverson Reuvers, Bloomington, Minnesota (for respondent)

Considered and decided by Bentley, Presiding Judge; Ede, Judge; and Beane, Judge.

NONPRECEDENTIAL OPINION

EDE, Judge After respondent township denied appellant’s application for an interim-use permit (IUP) to operate a contractor’s yard on certain real property located within the township, appellant sued the township seeking, among other things, a writ of mandamus and declaratory judgment. In this appeal challenging the district court’s order entering judgment for the township and dismissing appellant’s mandamus and declaratory-

judgment claims, appellant argues that the court erred because the township’s decision to deny his IUP application was contrary to law. In addition to contending that its IUP-denial decision complied with applicable law, the township maintains that the issues presented in this appeal are moot because its since-amended zoning ordinance precludes effective relief for appellant. We conclude that the matter is not moot and that the district court did not err in entering judgment for the township and in dismissing appellant’s mandamus and declaratory-judgment claims. Accordingly, we affirm.

FACTS

On March 18, 2024, appellant Chris Hansen submitted to respondent Haven Township (the township) an application for an IUP to operate a contractor’s yard on his property. The next day, the chair of the township board emailed Hansen. The email informed Hansen that his application was incomplete and included a redlined copy detailing what information was missing.

On July 24, Hansen submitted an updated IUP application to the township that included a land survey and a proposed building Hansen planned to construct on his property. In an August 8 email to Hansen, the chair of the township board stated that Hansen’s updated IUP application remained incomplete and that the township had rejected it because, under the township’s ordinances, a “contractor’s yard [was] not allowed in a subdivision.”

At an August 19 board meeting, the township considered whether Hansen’s property was eligible for an IUP in light of the township’s zoning ordinance, which excludes contractor’s yards from operating on certain properties that are within platted subdivisions.

The township’s board unanimously voted to deny Hansen’s updated IUP application on that basis. The board-meeting minutes do not reflect any concern that Hansen’s updated IUP application was incomplete.

Following this board meeting, the township’s attorney sent Hansen an August 26 letter stating that “it ha[d] come to the attention of the town[ship] board that [Hansen was] operating a contractor’s yard within a platted subdivision in the township’s agricultural district, . . . in violation of . . . the township’s zoning ordinance.” The August 26 letter enclosed a “Zoning Violation Abatement Agreement” to address the alleged violation. By letter dated September 4, Hansen’s attorney responded that, because Hansen’s property was registered land and was neither subdivided nor platted, approval of Hansen’s updated IUP application was not precluded by the township’s zoning ordinance.

On September 16, the township sent a letter to Hansen’s attorney stating that, under Minnesota Statutes section 15.99, subdivision 3(f) (2024), it was extending its deadline to respond to Hansen’s updated IUP application by another 60 days. Although the September 16 letter was written to the correct street address for the office of Hansen’s attorney, it bore an incorrect suite number.

The township’s planning commission met on October 16, at which the board considered Hansen’s updated IUP application. Hansen and his attorney were present at the meeting and provided information about the updated IUP application to the planning commission, including that Hansen was “withdrawing” from his application the proposed building that he had planned to construct on the subject property. The planning commission voted to recommend that the township adopt a resolution denying Hansen’s updated IUP

application. Despite the oral amendment of the updated IUP application by Hansen and his attorney, the stated basis for the denial recommendation was that the township could not approve an IUP application that would result in contractor’s yard buildings within the 250- foot setback from the property line required by the township zoning ordinance. At a noticed public hearing that immediately followed the meeting of the planning commission, a township supervisor summarized the board proceedings, and another supervisor moved to accept the planning commission’s recommendation. The supervisors unanimously voted to approve a resolution denying Hansen’s updated IUP application.

By letter dated October 22, the township’s attorney informed Hansen that the township had denied his updated IUP application and enclosed a copy of the resolution. Among other things, the resolution explained that “the updated IUP application still contain[ed] several deficiencies that . . . render[ed] the application . . . incomplete” and that the township could not approve an IUP application that sought approval for contractor’s yard buildings in violation of the township zoning ordinance, “which requires a contractors’ yard to be set back 250 feet from the property line.”

Hansen’s attorney sent the township a November 13 letter asking the township to reconsider the resolution and citing Minnesota Statutes section 15.99, subdivision 3(f). Based on that statute, Hansen’s attorney asserted that the township “had waived its right to deny [the updated IUP] application” because it had not sent the September 16 extension letter “to the correct address of the applicant,” but rather had misaddressed that letter to Hansen’s attorney, which resulted in the attorney receiving the letter 75 days after Hansen

submitted the updated IUP application on July 24. Hansen’s attorney requested that the township immediately grant the updated IUP application.

In December, Hansen sued the township, asserting the following claims relevant to this appeal: peremptory writ of mandamus, seeking “an order directing the township to grant Hansen’s IUP application because the township failed to act to grant or deny [his] request [for an IUP] within 60 days of submission, as required by Minn. Stat. § 15.99” (Count I); an alternative writ of mandamus, seeking an order that the township “show cause why an alternative writ of mandamus should not [be] issue[d] directing the township to grant the IUP application immediately” (Count II); and declaratory judgment, seeking a declaration “pursuant to Minnesota Statutes, Chapter 555, that the IUP Application should have been approved” (Count III). 1 Records from the IUP proceedings before the township were filed in the district court, and the township filed a memorandum requesting that the court affirm the township’s denial of Hansen’s updated IUP application. The matter proceeded to a hearing before the district court in July 2025. In September, the district court entered judgment on a written order affirming the township’s denial of Hansen’s updated IUP application and dismissing Hansen’s mandamus and declaratory-judgment claims (Counts I, II, and III).

This appeal follows.

1 Hansen also asserted a procedural-due-process claim (Count IV) and a claim for attorney fees and costs (Count V), both of which the district court later dismissed. Hansen does not challenge the district court’s dismissal of Counts IV and V in this appeal.

DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Chris Hansen v. Haven Township, (Mich. Ct. App. 2026).

Chris Hansen v. Haven Township (Chris Hansen v. Haven Township) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Breza v. City of Minnetrista
725 N.W.2d 106 (Supreme Court of Minnesota, 2006)
Manco of Fairmont, Inc. v. Town Board of Rock Dell Township
583 N.W.2d 293 (Court of Appeals of Minnesota, 1998)
Clear Channel Outdoor Advertising, Inc. v. City of St. Paul
675 N.W.2d 343 (Court of Appeals of Minnesota, 2004)
City of Minneapolis v. Wurtele
291 N.W.2d 386 (Supreme Court of Minnesota, 1980)
Plowman v. Copeland, Buhl & Co., Ltd.
261 N.W.2d 581 (Supreme Court of Minnesota, 1977)
Matter of Schmidt
443 N.W.2d 824 (Supreme Court of Minnesota, 1989)
Ethan Dean v. City of Winona
868 N.W.2d 1 (Supreme Court of Minnesota, 2015)