Choy v. Circle, Inc.

905 So. 2d 1118, 2005 La. App. LEXIS 1454, 2005 WL 1278370
Louisiana Court of Appeal·Decided May 31, 2005·No. No. 05-CA-81·Published

Opinion

THOMAS F. DALEY, Judge.

The plaintiff, Joseph Wong Choy, filed suit against the Parish of Jefferson, Circle Inc., N-Y Associates, Inc., and Bayou Land and Marine, Inc. alleging that work performed by these defendants on the Suburban canal caused damage to plaintiffs property, which is located adjacent to the canal. Following a trial, the trial court found in favor of the defendants dismissing [1120]*1120plaintiffs claims. For the reasons that follow, we affirm.

FACTS:

In 1995, the Parish of Jefferson contracted with N-Y Associates, (N-Y) an engineering firm, to design improvements to the Suburban canal. The Parish contracted with Circle, Inc., (Circle) a general contractor, to install concrete bulkheads along the sides and bottom of the canal. Bayou Land and Marine (Bayou) was hired to install and remove sheet piling as part of the construction process. This project began in August 1995 and was completed in September 1996.

|4Mr. Choy filed suit against the Parish, N-Y, Circle, and Bayou alleging that the construction on the canal was performed improperly in that the water was removed from the canal prior to sheet piles being driven to stabilize the ground and that the area between the cement wall in the canal was improperly backfilled allowing the ground between his property and the canal to remain unstable causing increased subsidence on his property resulting in holes around the building through which the pilings could be seen. He claims this led to the building sinking and shifting horizontally towards the canal.

Mr. Choy testified that he purchased a four-plex located at 4200 Eporia Street in Metairie in July 1992. Prior to purchasing the property the lender required that he make certain repairs to the property involving the roof and balconies, as well as the walls and ceiling in two of the apartments. Plaintiff was also required to have a plumber check a leak in apartment three and certify that all plumbing met code standards. An addendum to the appraisal report states that the property is nine to ten feet from “a large drainage canal which is separated from the property by a wooden fence.” The report goes on to state: “There could possibly be some subsidence caused by water flow in the future.”

Plaintiff acknowledged being aware of problems with subsidence and explained that he “checked with the parish” and understood there would be future repairs to the canal. Plaintiff testified that in February 1995, a civil engineer, Glenn Snyder, inspected the property at his request because plaintiff felt the driveway and sidewalks were “sinking more.” Plaintiff testified that he was not advised by Mr. Snyder of any damage to the building at that time. In October 1995, Wallace Treadway, a building inspector, inspected the property and found the front corner of Apartment Four was lower that the rest of the building.

Lin conjunction with plaintiffs testimony, numerous copies of photographs were introduced into evidence. Plaintiff testified that these photographs depicted his property prior to, during, and after construction. Numerous cracks to the driveway and sidewalks on plaintiffs property, as well as cracks in the bricks and slab were visible in these photographs. While plaintiff acknowledged that cracks in the driveway and sidewalk were present prior to construction, he testified that the cracks got larger and stoops on the apartment had migrated towards the canal during and after construction. Plaintiff testified that there were no cracks in the brick prior to construction. Plaintiff testified that since the construction on the canal, water seeps up through the slab in Apartment One. He denied that this occurred prior to construction. Throughout plaintiffs testimony, he explained what was depicted in the numerous photographs. However, when questioned as to the dates the photographs were taken, plaintiff could not provide specific answers. Plaintiff testified that these photographs were taken between March 1996 and October 1996, [1121]*1121with the exception of a small number that were taken just prior to trial. Plaintiff was unable to provide any documentation regarding the dates these photographs were taken.

With regard to certain photographs that depicted construction 'in the area behind plaintiffs property, plaintiff testified that the photographs showed that the water in the canal was removed prior to the sheet piles being driven. Plaintiff testified that other photographs showed that the area between the concrete bulkhead and his property was backfilled without removing a concrete sidewalk from behind the property. Plaintiff explained that the construction on the canal caused an increase in the subsidence resulting in the pilings under the building to be visible.

| fiPlaintiff claimed that the damage caused to the apartments by the construction resulted in difficulty renting the apartments. However, on cross-examination, plaintiff admitted that family members lived in two of the apartments and did not pay rent, and that the probable reason for the lack of a tenant in Apartment Four was due to water damage unrelated to the construction. Plaintiff did not submit any documentation with regard to loss of rental income.

During plaintiffs testimony, a video was played that depicted the property on October 11, 1995, prior to construction being done adjacent to plaintiffs property. This video shows numerous cracks in the driveway, sidewalks, and stoops on plaintiffs property, as well as several areas of damage to walls and ceilings. The video shows a missing shingle and damage to the overhang of the property. Cracks in the corners of the slab foundation can also be seen.

Lance Creel testified that he was hired to perform the pre-construction inspection and videotape for this project. He viewed photographs submitted during plaintiffs testimony and. testified that these conditions of subsidence and cracking were not in his video. He explained that this meant he did not see these conditions.

Glynn Snyder was accepted by the court as an expert in civil engineering. Mr. Snyder testified that he examined the exterior of plaintiffs property three times. In 1992, Mr. Snyder inspected the property after sewer work was performed. He found the building to be sound with the parking lot and sidewalks in good condition with “normal cracking.” When he inspected the building in February 1995, he noted more subsidence and more cracks in the driveway. He did not recommend 'any repairs at that time. Mr. Snyder testified that when he returned to inspect the property after .1995, subsidence of the ground beneath the house was visible. Mr. Snyder opined that even if construction was not performed, he would have expected subsidence to continue to erode the ground beneath the building and |7the sidewalks. Mr. Snyder explained that this subsidence was caused by normal fluctuations in the water table and the fact that the canal filled and drained following rain. Mr. Snyder denied taking any photographs or measurements during any of these inspections.

Ron Calcagno testified that he was employed by N-Y as the resident inspector on the Suburban Canal project. He explained that it was his job to make sure the contractor constructed the project according to the plans and specifications set forth by N-Y. Mr. Calcagno testified that he was on the jobsite everyday and filled out daily progress reports. Mr. Calcagno testified that sheet piles were driven into the ground prior to the cement walls being constructed.

Free access — add to your briefcase to read the full text and ask questions with AI

Choy v. Circle, Inc., 905 So. 2d 1118, 2005 La. App. LEXIS 1454, 2005 WL 1278370 (La. Ct. App. 2005).

905 So. 2d 1118 (Choy v. Circle, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lasyone v. Kansas City Southern RR
786 So. 2d 682 (Supreme Court of Louisiana, 2001)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)