Chopelas v. City Clerk of Malden

295 N.E.2d 395, 1 Mass. App. Ct. 241, 1973 Mass. App. LEXIS 452
CourtMassachusetts Appeals Court
DecidedApril 24, 1973
StatusPublished

This text of 295 N.E.2d 395 (Chopelas v. City Clerk of Malden) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chopelas v. City Clerk of Malden, 295 N.E.2d 395, 1 Mass. App. Ct. 241, 1973 Mass. App. LEXIS 452 (Mass. Ct. App. 1973).

Opinion

Keville, J.

This is an appeal from the allowance in the Superior Court of a motion to dismiss a petition for a writ of mandamus brought against the city clerk, the registrars of voters and the treasurer of the city of Malden for the certification of signatures upon a referendum petition.

*242 We summarize the essential allegations of the petition. On November 23, 1971 the Malden city council passed a bond order authorizing the treasurer, with the approval of the mayor, to borrow $8,000,000 for the purpose of building an incinerator. The mayor signed the order on November 24, 1971. On December 14, 1971 the petitioners, who are registered voters of the city, filed a referendum petition, which they had circulated, with the city clerk. The referendum petition requests that “the question of approving or disapproving” the bond order be submitted to the voters of Malden. The city clerk refused to deliver the referendum petition to the registrars of voters for certification of signatures. See G. L. c. 43, § 38. 1

The sole question presented is whether the referendum petition was seasonably filed under the provisions of G. L. c. 44, § 8A. 2

The petitioners’ assertion is that, but for the filing of the referendum petition, the “effective” day of the order would be November 24, 1971, the day of the mayor’s approval, and, since the referendum petition was filed with the city *243 clerk within twenty days of that day, the petition was seasonably filed under § 8A. The respondents argue that the “effective” day would be November 23,1971, when the city council passed the bond order, and that not having filed the petition until the twenty-first day thereafter, the petitioners failed to comply with the requirement of § 8A.

We take judicial notice of the city charter of Malden (St. 1881, c. 169) and amendments thereto. Grant v. Aldermen of Northampton, 316 Mass. 432,435. When G. L. c. 44, § 8A, is read in conjunction with § 11 of the charter, as amended by St. 1958, c. 286, § 2, 3 it becomes apparent that the bond order could become effective without the approval of the mayor only if passed by a two-thirds vote of the city council over his objections. Scalley v. Registrars of Voters of Woburn, 358 Mass. 815.

The respondents rely heavily upon the provisions of G. L. c. 43, § 42, 4 and upon Corriere v. Registrars of Voters of Fitchburg, 257 Mass. 287, interpreting that statute. Explicit under § 42 is the fact that the twenty-day period starts to run from the final passage of a measure by a city council. A comparison of § 42 with G. L. c. 44, §§ 7 and 8A, read in conjunction with G. L. c. 43, § 38, makes it clear that § 42 and the Corriere case are not applicable to a referendum petition challenging this bond order.

It does not appear, however, that the city of Malden adopted one of the municipal charter plans set out in G. L. c. 43; and the applicability of this chapter to a city is expressly conditioned upon its acceptance of one of the *244 plans described therein. Everett v. Curnane, 329 Mass. 490,491. But, through the enactment of St. 1950, c. 29, § l, 5 the Malden city charter was amended to include precisely the then language of G. L. c. 43, §§ 38 and 42, with respect to referendum petitions. It is significant that the amendment did not alter the previous acceptance of G. L. c. 44, § 8A, by the city relating to referenda on bond issues.

There is no merit in the further assertion of the respondents based upon Corriere v. Registrars of Voters of Fitchburg, 257 Mass. 287, 288, 6 that the referendum petition must be filed with the city clerk sufficiently early within the statutory period of twenty days to allow the respondents’ functions (see fn. 1) also to be performed within that period. To follow that argument would be to thwart the obvious legislative intent “to provide a simple, practicable method of obtaining municipal referenda.” O’Shea v. Holyoke, 345 Mass. 175, 179.

The order allowing the motion to dismiss is reversed and the case is to stand for trial in the Superior Court.

So ordered.

1

Section 38 (second paragraph) reads, “Within five days after the filing of said petition the registrars of voters shall ascertain by what number of registered voters the petition is signed, and what percentage that number is of the total number of registered voters, and shall attach thereto their certificate showing the result of such examination.

“The city clerk shall forthwith transmit the said certificate with the said petition to the city council.”

2

Section 8A, inserted by St. 1939, c. 108, § 1, accepted by the city of Malden on November 14,1939, reads, “[Ajn order authorizing the issue of bonds ... for any purpose specified in any applicable clause of section seven, * other than clause (11)... shall not become effective before the expiration of a period of twenty days from the day upon which such order would become effective except for this section. If within said period a petition signed by registered voters of the city ... and conforming to the provisions of section thirty-eight of chapter forty-three relative to initiative petitions in cities governed by said chapter, shall be filed with the city clerk, such filing in cities subject to said section thirty-eight to be in the manner therein provided, asking that the question of approving or disapproving such order be submitted to the registered voters of the city, such order shall be further suspended from becoming effective and said city clerk shall forthwith transmit such petition to the city council, which shall immediately reconsider such order.... If a petition relative to any such order is not filed within said period of twenty days, such order shall become effective upon the expiration of said period.”

*

General Laws, c. 44, § 7 (4A), as amended through St. 1965, c. 206, § 1, authorizes borrowing for the purpose of constructing an incinerator.

3

“Every ordinance, order, resolution or vote shall be presented to the mayor. If he approves thereof he shall signify his approval by signing the same; but if he does not approve thereof, he shall return the ordinance, order, resolution or vote, with his objections in writing, to the city council.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Shea v. City of Holyoke
186 N.E.2d 608 (Massachusetts Supreme Judicial Court, 1962)
City of Everett v. Curnane
109 N.E.2d 135 (Massachusetts Supreme Judicial Court, 1952)
Carriere v. Board of Registrars of Voters
153 N.E. 564 (Massachusetts Supreme Judicial Court, 1926)
Grant v. Aldermen of Northampton
55 N.E.2d 705 (Massachusetts Supreme Judicial Court, 1944)
Scalley v. Board of Registrars of Voters
266 N.E.2d 677 (Massachusetts Supreme Judicial Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
295 N.E.2d 395, 1 Mass. App. Ct. 241, 1973 Mass. App. LEXIS 452, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chopelas-v-city-clerk-of-malden-massappct-1973.