CHOCTAW NATION v. ROBINS & MORTON CORP.

2022 OK CIV APP 22, 513 P.3d 563
CourtCourt of Civil Appeals of Oklahoma
DecidedSeptember 30, 2021
StatusPublished

This text of 2022 OK CIV APP 22 (CHOCTAW NATION v. ROBINS & MORTON CORP.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CHOCTAW NATION v. ROBINS & MORTON CORP., 2022 OK CIV APP 22, 513 P.3d 563 (Okla. Ct. App. 2021).

Opinion

CHOCTAW NATION v. ROBINS & MORTON CORP.
2022 OK CIV APP 22
513 P.3d 563
Case Number: 119325
Decided: 09/30/2021
Mandate Issued: 06/15/2022
DIVISION III
THE COURT OF CIVIL APPEALS OF THE STATE OF OKLAHOMA, DIVISION III


Cite as: 2022 OK CIV APP 22, 513 P.3d 563

THE CHOCTAW NATION OF OKLAHOMA, Plaintiff/Appellee,
v.
(1) ROBINS & MORTON CORPORATION, Defendant/Appellant,
and
(2) JAMES CHILDERS, ARCHITECT, INC.,
(3) BUILDING & EARTH SCIENCES, INC.,
(4) BARKER & ASSOCIATES, INC.,
(5) VILHAUER ENTERPRISES, LLC,
(6) ALLISON LANDSCAPE AND POOL, LTD.,
(7) CHAVES-GRIEVES CONSULTING ENGINEERS, INC.,
(8) HOWARD-FAIRBAIN SITE DESIGN, INC.,
(9) HP ENGINEERING, INC.,
(10) BERNHARD MCC, LLC,
(11) AIRTECH CORPORATION,
(12) NORTHWEST CONTROLS SYSTEM, INC.,
(13) CLIMACOOL CORPORATION,
(14) EMPIRICAL ENERGY SOLUTIONS, LLC, Defendants.

APPEAL FROM THE DISTRICT COURT OF
BRYAN COUNTY, OKLAHOMA

HONORABLE MARK R. CAMPBELL, TRIAL JUDGE

REVERSED

P. Scott Hathaway, M. Freeman-Burney, Chris Warzecha, CONNER & WINTERS, LLP, Tulsa, Oklahoma,
Michael Burrage, John B. Norman, J. Renley Dennis, Austin R. Vance, WHITTEN BURRAGE, Oklahoma City, Oklahoma, for Plaintiff/Appellee,

Monty B. Bottom, Ashley M. Thul, FOLIART, HUFF, OTTAWAY & BOTTOM, Oklahoma City, Oklahoma, for Defendant/Appellant, Robins & Morton Corporation.

Trevor S. Pemberton, Presiding Judge:

¶1 Robins & Morton Corporation (R&M) seeks review of the trial court's denial of a Motion to Compel Mediation and, if Necessary, Arbitration and Dismiss or, Alternatively, Stay Litigation. The dispositive issue is whether a mandatory arbitration provision in a construction management contract between The Choctaw Nation of Oklahoma (Nation) and R&M is void under 12 O.S. § 1855

BACKGROUND

2 In 2015, the Nation and R&M entered into a Construction Management Contract (Contract) pursuant to which R&M was to provide to the Nation construction management services associated with the construction of a medical center. The Contract had the following stated purposes:

ARTICLE 1 PURPOSE AND INTENT
The primary purpose and intent of [the construction manager's consultations services part] of this procurement is to secure the services of a Construction Manager to provide design consultation on the project; to monitor project costs and endeavor to keep costs within established limitations; to schedule the project efficiently for the construction phases so that the project will be ready for occupancy at the earliest possible date; and to review the design of the project with the intent that the most efficient use of materials and methods will be employed to provide quality construction at the least cost.
. . .
ARTICLE I PURPOSE AND INTENT

The primary purpose and intent of [the construction management services part] of this procurement is to secure the services of a Construction Manager to organize and direct the complete construction of the project and to assume all risks and responsibilities of constructing the project within a Guaranteed Maximum Price and Time.

3 The Contract further contained acute detail about R&M's several obligations to fulfill the purpose(s) and intent(s). Not unlike many, if not most, other construction management contracts, the Contract also contained deep within the document language regarding insurance and bonds to be procured. Also attached were a Tribal Controlled Insurance Program (TCIP) Contract Addendum and a corresponding TCIP Procedures Manual.

¶4 After completion of construction, the Nation raised issues about alleged design and construction defects negligently caused by R&M and the other named defendants. Although they dispute timeframes and each other's cooperation, the Nation and R&M then exchanged communications regarding means by which to resolve the dispute.

¶5 With the dispute unresolved, the Nation later filed the underlying lawsuit, after which the Nation and R&M participated in an unsuccessful dispute resolution conference--a mechanism outlined in the provision of the Contract at issue. Once served with the lawsuit, R&M filed a motion to compel mediation/arbitration, praying for enforcement of the following contractual provision requiring that the dispute be submitted to mediation/arbitration:

4. DISPUTES
All disputes arising under this Construction Management Services contract that remain unresolved after good faith negotiations between the parties first shall be the subject of a dispute resolution conference. Either party may initiate a dispute resolution conference ("DRC") by providing written notice (the "Dispute Notice") to the other party. The written notice shall contain a short summary of the facts. Within five (5) days of receiving the Dispute Notice, a dispute resolution conference between Contracting Official, Project Director and the Construction Manager's representative(s) shall occur. If the parties are unable to resolve the dispute at the DRC, the parties will have an additional five (5) days from the date of the DRC to resolve the dispute. If either party fails to participate in the DRC or if no resolution is achieved by the DRC process, then the dispute shall be submitted to the American Arbitration Association as agreed to below.
If no resolution is achieved by the DRC process, the parties agree that unresolved dispute shall be submitted to the American Arbitration Association pursuant to the Construction Arbitration Rules and Mediation Procedures. The parties further agree that the mediation and arbitration procedures selected herein shall be the exclusive manner by which disputes that are still unresolved at the DRC stage are to be resolved.
. . .

(Disputes Clause).

The Contract also contained a fully executed attachment titled Dispute Resolution Fund Agreement, pursuant to which the Nation agreed to deposit with an escrow agent a certain sum to be held and disbursed in the event "an arbitration award (the "Award") is issued in favor of [R&M][.]"

¶6 The Nation argued in response to the motion to compel, that the arbitration mandate in the Disputes Clause was void under 12 O.S. § 1855

The Uniform Arbitration Act shall not apply to . . . contracts which reference insurance, except for those contracts between insurance companies.

According to the Nation, the insurance provisions and related attachments were essential to the Contract, and the Nation would not have contracted with R&M but for its agreement to comply with the insurance terms. Notably, however, consummation of the Contract was not specifically tied to insurance provisions. The Contract provided:

L-10 ACCEPTANCE OF OFFER
If the offer is accepted, the offeror will receive a notice of award of the Construction Management Contract for the work included under PART A. The notice of award will consummate the contract which will consist of the documents listed in the request for proposal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Preston v. Ferrer
552 U.S. 346 (Supreme Court, 2008)
McMullan v. Enterprise Financial Group, Inc.
2011 OK 7 (Supreme Court of Oklahoma, 2011)
Thompson v. Bar-S Foods Co.
2007 OK 75 (Supreme Court of Oklahoma, 2007)
Hollaway v. UNUM Life Insurance Co. of America
2003 OK 90 (Supreme Court of Oklahoma, 2003)
SPARKS v. OLD REPUBLIC HOME PROTECTION CO. INC.
2020 OK 42 (Supreme Court of Oklahoma, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2022 OK CIV APP 22, 513 P.3d 563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/choctaw-nation-v-robins-morton-corp-oklacivapp-2021.