Chloeta Fire, LLC

CourtArmed Services Board of Contract Appeals
DecidedNovember 9, 2015
DocketASBCA No. 59211
StatusPublished

This text of Chloeta Fire, LLC (Chloeta Fire, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chloeta Fire, LLC, (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Chloeta Fire, LLC ) ASBCA No. 59211 ) Under Contract No. W9128F-l l-M-E023 )

APPEARANCE FOR THE APPELLANT: Mr. Mark D. Masters Chief Executive Officer

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Melissa M. Head, Esq. Engineer Trial Attorney U.S. Army Engineer District, Omaha

OPINION BY ADMINISTRATIVE JUDGE THRASHER

This appeal arises out of a contract to perform a prescribed bum on approximately 650 acres of federal land at Fort Randall, South Dakota. The government does not believe the contractor, Chloeta Fire, LLC (Chloeta), completed the prescribed bum on all the acres required and refused to remit Chloeta the full contract price. Chloeta asserts it did complete the contract and is entitled to the full contract price. The parties have chosen to proceed solely upon the record submitted, 1 pursuant to Board Rule 11. We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. Only entitlement is before the Board for decision.

FINDINGS OF FACT

A. Background

1. The U.S. Army Corps of Engineers (government or USACE) administers approximately 18,066 acres of federal land located on Fort Randall, South Dakota, through the USACE Fort Randall Project (project). The government awarded Contract No. W9128F-l l-M-E023 (contract) to Chloeta on 23 September 2011 to provide a prescribed bum of vegetation on a specific track of approximately 650 acres of the project land. The initial period of performance was from 30 September 2011 to 30 September 2012. (R4, tab 4 at 1, 5) The original contract price was $52,888.30 (id. at 3).

1 The submitted record consist solely of the Rule 4 file (tabs 1-7) and appellant's supplemental Rule 4 file (tabs 1-4). 2. The performance work statement (PWS) stated the objectives of the contract were:

To effectively bum all vegetation on approximately 650 acres of federal land administered by the USACE Fort Randall Project. The purpose of the prescribed bum is to suppress and control invasive eastern red[ ]cedar, reduce the biomass of cedar piles that were cut and stacked in 2009, increase the abundance of native cool and warm season grasses and forbs, and to decrease the abundance of non-native species.

(R4, tab 4 at 5, if 1.3)

3. The contract defined the scope of work in relevant part as follows: '"The contractor shall complete the prescribed bum on approximately 650 acres of federal land administered by the USACE Fort Randall Project that complies with the standards in this PWS. Services include ... 2) a complete bum of all the vegetation and downed cedar piles located within the 650 acre unit." (R4, tab 4 at 5, if 1.4)

4. The PWS described the specific tasks under the contract in pertinent part as:

5.1. Basic Services: The contractor shall provide prescribed bum services on approximately 650 acres of federal land administered by the USACE Fort Randall Project. Services include 1) the preparation of a bum plan that has been approved ... ,2) a complete bum of all the vegetation and downed cedar piles located within the 650 acre unit ....

5.2.1. Bum Plan and Prescribed Bum: The contractor shall be required to write a bum plan[21that has been approved ... to completely bum all vegetation and downed cedar piles located within the 650 acre unit of federal land administered by the USACE Fort Randall Project.

(R4, tab 4 at 15)

2 The bum plan was not included within the record.

2 5. Contract paragraph 1.6.10 describes the point of contact's (POC's) pertinent general duties as:

The POC monitors all technical aspects of the contract and assists in contract administration. The POC is authorized to perform the following functions: assure that the contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including government drawings, designs, specifications; monitor contractor's performance and notifies both the KO and contractor of any deficiencies; coordinate availability of government furnished property; and provide site entry of contractor personnel.

(R4, tab 4 at 7) Paragraph 4.6.8 provides the POC with the responsibility to determine when the work has been satisfactorily completed and the authority to accept the work stating in pertinent part, "Payment will be made after satisfactory completion, inspection, and acceptance by the POC of all contract work performed" (R4, tab 4 at 15). Mr. Cody Wilson was the POC during performance (app. supp. R4, tab 1 at 2, if 8) 3

B. Contract Performance

6. In March 2012, Chloeta personnel mobilized to the site to begin site preparation for the bum. Burning operations were halted due to an extreme drought. As a result, the contract was amended by Modification No. POOOOl to extend the period of performance until 31May2013 (R4, tab 6). Chloeta submitted an invoice for services rendered to that point and was paid a partial payment of $19,000 to cover on-site preparations, travel, and planning. (App. supp. R4, tab 1 at 1, if 5)

7. On 27 February 2013, the contract was further modified by Modification No. P00002 to make an equitable adjustment due to unavoidable weather delays. The price of the contract was increased by $21, 801.11 to include costs for additional mobilization and demobilization, and other direct and indirect costs, increasing the total contract price to $74,689.41. (R4, tab 7; app. supp. R4, tab 1 at 1, if 6)

3 Ms. Dawn Rodriguez was appointed POC at award. The contract also stated that a letter would be issued identifying the POC's specific responsibilities and limitations. (R4, tab 4 at 7, if 1.6.11) No such letter was included in the record.

3 8. Chloeta personnel performed a bum on 27 April 2013. Approximately 60-70% of Eastern Red Cedars on-site were consumed, and all Eastern Red Cedar piles were burned. (App. supp. R4, tabs 1, 2, 3, ~ 7) Mr. Stanton, Chloeta's fire management officer, testified that:

The evening of the bum I met with Cody Wilson in his office. Wilson told me that he expected a consumption rate of Eastern Red Cedar of approximately 30%. I asked Mr. Wilson ifthe bum had met his objectives and he said yes. He estimated a mortality rate of approximately 70% of the cedars, which I concurred with.

(App. supp. R4, tab 3 at 2, ~ 8)

9. Mr. McAffrey, Chloeta's division chief, testified that the following day he accompanied Mr. Wilson as he conducted a final inspection of the project site during which Mr. Wilson told him that the project was complete and extremely successful. He also testified that he asked Mr. Wilson if Chloeta could demobilize from the work site, to which Mr. Wilson replied yes. (App. supp. R4, tab 2 at 2, ~ 10)

10. On 5 May 2013, Chloeta submitted an invoice in the amount of $55,689.41. The government refused to pay the full amount, and instead calculated payment for $43,739.10. 4 On 9 May 2013, Chloeta resubmitted its invoice in the amount of$43,739.10, the total remaining balance according to the government, minus an earlier payment of $19,000. In May 2013, Chloeta was paid the $43,739.10. (R4, tab 2 at 3-4, ~~ 16-17, 19)

C. Chloe ta 's Claim

11. On 3 June 2013, Chloeta submitted a claim for $11,950.31, asserting it completed the work under the contract and was entitled to payment of the remaining contract price (R4, tab 3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Chloeta Fire, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chloeta-fire-llc-asbca-2015.